SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2020 Supreme(Del) 913

IN THE HIGH COURT OF DELHI AT NEW DELHI
C. Hari Shankar, J.
Sterna India Oil And Gas Private Ltd. - Appellant
Versus
Nandini Impex Private Limited - Respondent
Arbitration Petition No. 356 of 2020, 358 of 2020; Interlocutory Application No. 7824 of 2020, 7826 of 2020
Decided On : 08-09-2020

Advocates Appeared:
Kamal Mehta, Advocate, Abhishek Chauhan, Advocate, Aseem Chaturvedi, Advocate, Karan Gupta, Advocate

The court's decision emphasized the importance of referring disputes to the appropriate arbitration center for the appointment of an arbitrator, and highlighted the possibility of raising the issue of consolidation of proceedings before the DIAC.

Headnote:

Arbitration - Appointment of Arbitrators - Arbitration & Conciliation Act, 1996 - Section 11(6)

Fact of the Case:

Disputes arose between the petitioner and the respondent regarding alleged liabilities under a Memorandum of Understanding (MoU) and two sub-contracts. The parties failed to agree on the identity of the arbitrator, leading the petitioner to seek the appointment of an arbitrator through the Delhi International Arbitration Centre (DIAC) under Section 11(6) of the Arbitration & Conciliation Act, 1996.

Finding of the Court:

The court disposed of the petitions, referring the parties to the DIAC for the appointment of an arbitrator to arbitrate on the disputes.

Issues: Dispute over alleged liabilities under the MoU and sub-contracts, and disagreement on the identity of the arbitrator.

Ratio Decidendi: The court held that the disputes should be referred to the DIAC for the appointment of an arbitrator, and the issue of consolidation of proceedings could be raised before the DIAC in accordance with the provisions contained in the DIAC (Arbitration Proceedings) Rules, 2018.

Final Decision: The petitions were disposed of, referring the parties to the DIAC for the appointment of an arbitrator to arbitrate on the disputes.

JUDGMENT

C. Hari Shankar, J. - I.A. 7824/2020 in ARB.P. 356/2020 &

    I.A. 7826/2020 in ARB.P. 358/2020

      1. Exemptions allowed, subject to all just exceptions.

        2. The applications stand disposed of.

          ARB.P. 356/2020 &

          ARB.P. 358/2020

            1. These are petitions under Section 11(6) of the Arbitration & Conciliation Act, 1996, for appointment of arbitrators.

            2. Issue notice. Mr Aseem Chaturvedi accepts notice on behalf of the respondent.

            3. With consent of parties, the matter has been heard finally.

            4. The relationship between the petitioner and the respondent is governed by a Memorandum of Understanding (MoU), as well as by two sub-contracts, all of which are dated 22nd August, 2019.

            5. The MoU, between the petitioner and the respondent, was a fallout of bids, submitted by the respondent, for certain projects relating to City Gas Distribution (CGD) network for various customers.

            6. The petitioner and the respondent came to an understanding, formalised in the shape of the aforesaid MoU, dated 22nd August, 2019, to the effect that, in the case of projects awarded to the respondent, the petitioner would be the nominated sub-contractor for execution of part of the works related thereto.

            7. Clause 1(ii)(a) of the MoU may, in this regard, be reproduced, thus:

              "(ii). Projects already awarded in favour of NIPL

                (a) In case of the projects which have already been awarded to NIPL as on the date of this MoU, Sterna shall be the nominated subcontractor for execution of part of works of the projects. NIPL shall subcontract the works or part of the works on the same schedule of rates as per the main contract executed by it with the respective client."

                8. Sub-Clauses (iv) & (v) of clause (1) of the MOU also merit reproduction, thus:

                  "(iv). The Parties will decide on the submission of bank guarantees for the Agreed Projects on case to case basis. In the event Sterna agrees to provide performance bank guarantees for any Agreed Project as per the terms of the respective tender/ the contract, the costs incurred by Sterna in issuance, maintenance or renewal of the said performance bank guarantees will be reimbursed by NIPL if agreed mutually, on case to case basis. Further, in the event bank guarantees submitted by Sterna are invoked by the Client, NIPL shall keep Sterna fully indemnified against any loss or damage that may be caused to Sterna so long as the encashment was not directly due to a sole breach of the contract terms or non-performance on the part of Sterna.

                    (v). The Parties will execute with respect to each Agreed Project, a detailed separate agreement for allocation of scope of work, responsibilities, price and risk sharing as well as for establishing mechanism for execution of the Project (s), resolution of disputes etc., based on the terms of this MoU, prior to submission of proposal for each Agreed Project. Specific agreement executed between the Parties for Patiala GA Project forms part of this MoU as Annexure- 2."

                    9. The petitioner asserts that at the request of the respondent, two bank guarantees were submitted by the petitioner in favour of the respondent''s client, namely, Torrent Gas Pvt. Ltd.

                    10. As contemplated by clause 1(v) of the MoU, extracted hereinabove, two sub-contracts were executed, between the petitioner and the respondent, on the date of the MoU, i.e. 22nd August, 2019, relating to the work to be done for the areas of Patiala, Punjab and Karikal, Puducherry.

                    11. The disputes arose between the parties, consequent on the petitioner asserting that the respondent had defaulted in its obligation under the MoU and the sub-contracts, and the respondent levelling parallel allegations against the petitioner.

                    12. It appears that, the petitioner and the respondent exchanged communications, terminating the MoU and the sub-contracts.

                    13. The disputes between the parties related to alleged liabilities, by one towards the other, under the MoU/sub-contracts.

                    14. The arbitration clauses, in the MoU and the two sub-contracts, are alike and i

                                    Click Here to Read the rest of this document
                                    1
                                    2
                                    3
                                    4
                                    5
                                    6
                                    7
                                    8
                                    9
                                    10
                                    11
                                    SupremeToday Portrait Ad
                                    supreme today icon
                                    logo-black

                                    An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

                                    Please visit our Training & Support
                                    Center or Contact Us for assistance

                                    qr

                                    Scan Me!

                                    India’s Legal research and Law Firm App, Download now!

                                    For Daily Legal Updates, Join us on :

                                    whatsapp-icon telegram-icon
                                    whatsapp-icon Back to top