SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2021 Supreme(Del) 106

IN THE HIGH COURT OF DELHI AT NEW DELHI
MANMOHAN, ASHA MENON, JJ.
Guru Gobind Singh Indraprastha University - Appellant
Versus
Engineering India Ltd - Respondent
FAO(OS) (COMM) 46 of 2021 & CM APPLs.10323-10325 of 2021 and 10760 of 2021
Decided On : 26-03-2021

Advocates Appeared:
For the Appellant :Mr. Mukul Talwar, Senior Advocate with Ms. Anita Sahani, Advocate.
For the Respondent:Mr. Uday Gupta, Advocate.

Headnote:

Arbitration and Conciliation Act, 1996 - Section 34 - Section 37 - Limitation Act, 1963 - Section 3.2.b - Section 21 - Section 11 - Learned senior counsel for Appellant submits that learned Single Judge instead of granting a similar rate of interest @ 12% per annum to Appellant, has asked it to re-agitate matter as per law despite appreciating that both Appellant and Respondent were to be treated on same footing - He points out allows this Court to correct Award atleast to extent of directing that same rate of interest shall be granted to both Respondent and Appellant - He submits that in alternate, even if learned Single Judge felt compelled to direct Appellant/Counter Claimant to re-agitate its claim for interest, then in that case, same direction ought to have been issued to Respondent as well, and amount of interest of Rs. 74 -12 lakhs ought to have been disallowed, and both parties should have been permitted to re-agitate matter before a freshly appointed arbitral tribunal – Held, It is pertinent to mention that Arbitrator had only awarded Rs.45,50,046/- against aforesaid counter-claim -judgment of Apex Court in State of Goa is inapplicable to facts of present case as said judgment deals with issue of limitation of a counter claim and not with regard to rate of interest that has to be paid on counter-claim - Further, this Court is of view that if matter is remanded to an arbitrator for fresh adjudication with regard to rate of interest, it would promote and not curtail litigation—an ‘end’ which seeks to discourage - In fact, this Court is of opinion that if argument of learned senior counsel for appellant with regard to rate of interest is accepted, it would be in consonance with one of objectives of Arbitration and Conciliation Act, 1996, namely, finality of arbitration awards - This Court is of view that if argument of learned senior counsel for appellant with regard to rate of interest is accepted, it would promote one of ‘cherished goals’ of arbitration, namely, finality of arbitration awards - Applications stand disposed of

JUDGMENT :

Manmohan, J.

1. Present appeal has been filed challenging the order dated 13th March 2020 passed by the learned Single Judge.

2. Learned senior counsel for the Appellant submits that the learned Single Judge instead of granting a similar rate of interest @ 12% per annum to the Appellant, has asked it to re-agitate the matter as per law despite appreciating that both the Appellant and the Respondent were to be treated on the same footing. He points out that Section 34 of the Arbitration and Conciliation Act, 1996 allows this Court to correct the Award atleast to the extent of directing that same rate of interest shall be granted to both the Respondent and the Appellant.

3. He submits that in the alternate, even if the learned Single Judge felt compelled to direct the Appellant/Counter Claimant to re-agitate its claim for interest, then in that case, the same direction ought to have been issued to the Respondent as well, and the amount of interest of Rs.74.12 lakhs ought to have been disallowed, and both the parties should have been permitted to re-agitate the matter before a freshly appointed arbitral tribunal.

4. Learned senior counsel for the appellant also contends that there is a calculation error in computing the external development charges by the Arbitrator inasmuch as the factum of the claimant completing only 41.9% work was not taken into account.

5. Issue notice. Mr. Uday Gutpa, Advocate accepts notice on behalf of the Respondent. He submits that as far as interference with an order made under Section 34, as per Section 37 of Arbitration and Conciliation Act is concerned, it cannot be disputed that such interference under Section 37 cannot travel beyond the restrictions laid down under Section 34. In other words, the Court cannot undertake an independent assessment of the merits of the award, and must only ascertain that the exercise of power by the Court under Section 34 has not exceeded the scope of the provision.

6. He further submits that as the counter-claim is in the nature of damages, the appellant is not entitled to any interest on the same. In the alternative, without prejudice to his rights and contentions, he would submit that if at all the appellant is held entitled to any interest then the same ought to be calculated from 26th October, 2015 when the original counter-claim was replaced with the amended counter-claim and not from 19th May, 2011. In support of his submission, he relies upon a judgment of the Supreme Court in State of Goa vs. Praveen Enterprises, AIR 2011 SC 3814 wherein it has been held as under:-

    “17. As far as counter-claims are concerned, there is no room for ambiguity in regard to the relevant date for determining the limitation. Section 3(2)(b) of the Limitation Act, 1963 provides that in regard to a counterclaim in suits, the date on which the counterclaim is made in court shall be deemed to be the date of institution of the counterclaim. As the Limitation Act, 1963 is made applicable to arbitrations, in the case of a counter-claim by a respondent in an arbitral proceeding, the date on which the counter-claim is made before the arbitrator will be the date of “institution” insofar as counterclaim is concerned. There is, therefore, no need to provide a date of “commencement” as in the case of claims of a claimant. Section 21 of the Act is therefore not relevant for counter-claims. There is however one exception. Where the respondent against whom a claim is made, had also made a claim against the claimant and sought arbitration by serving a notice to the claimant but subsequently raises that claim as a counter-claim in the arbitration proceedings initiated by the claimant, instead of filing a separate application under Section 11 of the Act, the limitation for such counter-claim should be computed, as on the date of service of notice of such claim on the claimant and not on the date of filing of the counter-claim.”

7. Having heard learned counsel for the parties, this Court is of the vi

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top