SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2021 Supreme(Del) 189

IN THE HIGH COURT OF DELHI AT NEW DELHI
VIBHU BAKHRU, J.
M/s Janta Associates – Petitioner
Versus
Indian Oil Foundation and Another – Respondents
O.M.P. (I) (COMM.) No. 74 of 2020
Decided On : 11-05-2021

Advocates:
Advocate Appeared:
For the Petitioners: Mr. Vineet Bhagat, Mr. Mohit Gulati.
For the Respondents: Mr. Yati Sharma, Mr. Navin Kumar, Ms. Priya Puri, Ms. Rashmeet Kaur.

Point of Law: Interim measures, etc. by courts - Ex-parte stay and Show Cause Notice - No valid ground to interdict respondents from considering show cause notice and taking an informed decision with regard to contract and on question of blacklisting petitioner.

Headnote:

Arbitration and Conciliation Act, 1996 - Section 9 - Civil Procedure Code, 1908 - Order 38 Rule 5 - Arbitration Award - Contract - Construction n work - E-bids - adverse/coercive actions - Seeking direction to Respondents to secure due amount by way of a bank guarantee or by deposit with Court during the pendency of present petition and arbitration proceedings - Whether court can grant relief under Section 9(ii)(b) of A&C Act, in nature of attachment before award except on principles as contained under Order 38 Rule 5 CPC - Petitioner claims that it had submitted it Fifth RA Bill, which was revised, for amount - However same remains unpaid - Petitioner also claims that delay in construction was caused due to various reasons attributable to respondents also despite petitioner's request for a comprehensive insurance policy, respondents had failed to accept its suggestion.

Finding of the Court:

Court finds no ground to stay show cause notice - It is not disputed that same is in terms of contract between parties. Admittedly contract has not been completed within stipulated period. According to respondents, same is on account of various reasons, which are attributable to petitioner. Reading of show cause notice also indicates that respondents are contemplating to blacklist petitioner. It is well settled that no such order can be made without affording the person proposed to be blacklisted, a fair opportunity to meet the allegations made against it. The show cause notice intends to do that - No valid ground to interdict respondents from considering show cause notice and taking an informed decision with regard to contract and on question of blacklisting the petitioner - It is seen that there is no averment in petition that respondents would not be in a position to honour award in case petitioner prevails in arbitration - Interim protection order contemplated under section 9(ii)(b) is granted by the Court to protect interest of party seeking such order until rights are finally adjudicated by the Arbitral Tribunal and to ensure that Award passed by Arbitral Tribunal is capable of enforcement.

Result: Petition dismissed.

JUDGMENT :

VIBHU BAKHRU, J.

1. The petitioner has filed the present petition under Section 9 of the Arbitration and Conciliation Act, 1996 (hereafter A&C Act), inter-alia, praying as under:

    “(a) Ex-parte stay and set aside the Show Cause Notice dated 24.02.2020 issued by the Respondents.

(b) Direct the Respondents to pay the due amount of Rs. 1,89,91,737/- (Rupees One Crore Eighty Nine Lakh Ninety One Thousand Seven Hundred and Thirty Seven Only) to the Petitioner and allow the Petitioner to continue to complete the work by providing modified dam drawings.

OR, in the alternative

Direct the Respondents to secure the due amount of Rs. 1,89,91,737/- (Rupees One Crore Eighty Nine Lakh Ninety One Thousand Seven Hundred and Thirty Seven Only) by way of a bank guarantee or by deposit with the Court during the pendency of the present petition and the arbitration proceedings.

(c) Direct the Respondents to withdraw the Termination Notices dated 06.01.2020, 13.01.2020 and 28.01.2020, and restrain the Respondents from taking any such adverse/ coercive actions against the Petitioner during the pendency of the present petition.”

2. The respondent no. 2 (hereafter ‘EIL’) had invited e-bids for “Composite Works for Development of Infrastructure Facilities at Khajekhalan Ghat, Patna Sahib, Patna” on behalf of respondent no. 1 (hereafter ‘IOF’). The petitioner had submitted its bid which was accepted by the respondents and a Letter of Acceptance was issued by EIL on 13.09.2018. Thereafter, the petitioner entered into a contract with IOF (through EIL) on 10.10.2018. The petitioner states that the work front was handed over to the petitioner on 09.02.2019, after much delay.

3. It is the petitioner's case that since the work site was on a river front, the petitioner was required to construct a cofferdam to protect the site from inflow of water. The petitioner did so as per the design provided by EIL. However, on 12.04.2019, there was heavy rainfall resulting in breach of the cofferdam. Consequently, the entire site was inundated and the petitioner had to incur substantial expenditure for clearing the site. It is the petitioner's case that it had suggested that a dam be constructed by sheet piling method. However, EIL did not accept the same and the destruction was caused due to faulty design of the cofferdam. The petitioner claims that despite the above, EIL insisted that a cofferdam be reconstructed by the petitioner. The petitioner did so but the said cofferdam was again destroyed on 04.05.2019.

4. The petitioner claims that it had submitted it Fifth RA Bill, which was revised on 27.08.2019, for a sum of Rs. 1,15,31,770/-. However, the same remains unpaid. The petitioner also claims that the delay in construction was caused due to various reasons attributable to the respondents. The petitioner also claims that despite the petitioner's request for a comprehensive insurance policy, the respondents had failed to accept its suggestion. In addition, the petitioner claims that there was substantial delay in handing over the above front. This also adversely affected the progress of the works and caused a major setback to the project. Further, the petitioner claims that the respondents had persistently delayed in making payments towards the work done and this resulted in the petitioner facing a severe liquidity crunch, which resulted in further delay in executing the works. The petitioner also claims that the pace of decision making with the respondents was extremely slow. This also made it difficult to maintain the progress of works. The petitioner applied for extension of time for completion of works, however, the same has not been granted.

5. The petitioner claims that a sum of Rs. 1,89,91,737/- is owed by the respondents to the petitioner which includes cost and losses suffered by the petitioner due to destruction of cofferdams.

6. The respondents dispute the assertions made by the petitioner. According to the respondents, the petitioner had failed to perform i

      Click Here to Read the rest of this document
      1
      2
      3
      4
      5
      6
      7
      8
      9
      10
      11
      SupremeToday Portrait Ad
      supreme today icon
      logo-black

      An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

      Please visit our Training & Support
      Center or Contact Us for assistance

      qr

      Scan Me!

      India’s Legal research and Law Firm App, Download now!

      For Daily Legal Updates, Join us on :

      whatsapp-icon Back to top