2022 Supreme(Del) 475

IN THE HIGH COURT OF DELHI AT NEW DELHI
Vibhu Bakhru, J.
NTPC Vidyut Vyapar Nigam Ltd. – Petitioner
Vs.
Newton Solar Pvt. Ltd. – Respondent
O.M.P. (Comm.) Nos. 271, 375 of 2020, I.A. Nos. 1559, 2369 of 2020
Decided On : 06-07-2022

Advocates:
Advocate Appeared:
For the Petitioners: Mr. Bharat Sangal, Mr. R.R. Kumar, Ms. Babita Kushwaha.
For the Respondents: Mr. Deepak Khurana, Mr. Vineet Tayal, Ms. Nishtha Wadhwa.

The main legal point established in the judgment is the determination of the date of commissioning of the Power Project and the liability for liquidated damages. The court interpreted the relevant provisions of the Agreement and applied legal principles to decide the dispute.

Headnote:

Liquidated Damages - Delay in Commissioning of Solar Power Project - Arbitration and Conciliation Act, 1996 - Section 34 - Summary of Acts and Sections: Arbitration and Conciliation Act, 1996 - Section 34 - The judgment discusses the controversy regarding delay in commissioning the solar power project and the consequent decision regarding levy of liquidated damages. The court analyzed the relevant provisions of the Agreement and the legal principles established in previous cases to determine the date of commissioning and the liability for liquidated damages. The court found that the date of commissioning was the date on which the power was generated and injected into the grid, and held that NSPPL was liable to pay compensation for the delay in commissioning the Power Project. The court also rejected NVVNL's claim for compensation for shortfall in supply of power, finding that the shortfall was not solely attributable to NSPPL.

Fact of the Case:

The parties filed petitions under Section 34 of the Arbitration and Conciliation Act, 1996, impugning an arbitral award regarding disputes arising from a Power Purchase Agreement. The controversy related to delay in commissioning the solar power project, liability for liquidated damages, and compensation for shortfall in supply of solar power. Both parties were aggrieved by the findings of the Arbitral Tribunal.

Finding of the Court:

The court found that NSPPL was liable to pay liquidated damages for the delay in commissioning the Power Project and rejected NVVNL's claim for compensation for shortfall in supply of power. The court analyzed the relevant provisions of the Agreement and previous legal principles to reach its decision.

Issues: The issues involved the determination of the date of commissioning of the Power Project, liability for liquidated damages, and the responsibility for the shortfall in supply of power.

Ratio Decidendi: The court held that the date of commissioning was the date on which the power was generated and injected into the grid. It found that NSPPL was liable to pay compensation for the delay in commissioning the Power Project and rejected NVVNL's claim for compensation for shortfall in supply of power, as the shortfall was not solely attributable to NSPPL.

Final Decision: NSPPL's petition under Section 34 of the A&C Act was rejected, and NVVNL's challenge to the impugned award succeeded to a limited extent. The court set aside the finding of the Arbitral Tribunal regarding the delay in commissioning the Power Project and allowed the parties to agitate the dispute afresh.

JUDGMENT :

Vibhu Bakhru, J.

INTRODUCTION

1. The parties have filed the present petitions under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter ‘the A&C Act’) impugning an arbitral award dated 21.10.2019 (hereinafter ‘the impugned award’) delivered by an Arbitral Tribunal comprising of Justice (Retd.) G.N. Ray, Justice (Retd.) Usha Mehra, and Justice (Retd.) G.B. Patnaik as the Presiding Arbitrator (hereinafter ‘the Arbitral Tribunal’).

2. The impugned award was rendered in the context of disputes that have arisen between the parties in connection with a Power Purchase Agreement dated 08.01.2011(hereinafter ‘the Agreement’).

THE CONTROVERSY

3. The controversy in the present petition relates to the question whether there was any delay on the part of Newton Solar Power Private Limited (hereinafter ‘NSPPL’) in complying with its obligations under the Agreement and whether it was liable to pay liquidated damages for the said delay, if any. In addition, NTPC Vidyut Vyapar Nigam Limited (hereinafter ‘NVVNL’) had also claimed compensation for shortfall in supply of solar power, which was disputed by NSPPL.

4. The Arbitral Tribunal found that there was a delay of four days in commissioning the solar project and NSPPL was liable to pay liquidated damages quantified at 20% of the aggregate amount of the performance bank guarantees. The Arbitral Tribunal further found that NSPPL was not liable to pay any compensation for any shortfall in supply of energy.

5. Both the parties are aggrieved by the finding of the Arbitral Tribunal regarding the delay in commissioning of the solar power project and the consequent decision regarding levy of liquidated damages. According to NVVNL, the delay is in excess of one month and NSPPL is liable to pay an additional 40% of the aggregate amount of the Performance Bank Guarantees as liquidated damages. According to NSPPL, there is no delay in commissioning the solar project in question and therefore, it is also aggrieved by the impugned award. In addition, NVVNL is aggrieved by the decision of the Arbitral Tribunal in absolving NSPPL of any liability on account of shortfall in supply of solar power. Thus, both the parties have assailed the impugned award to the extent that they are aggrieved.

FACTUAL CONTEXT

6. In the month of July 2010, the Ministry of New & Renewable Energy, Government of India (hereinafter ‘MNRE’) issued certain guidelines for the selection of new grid connected solar power projects. NVVNL was selected as a nodal agency for arranging and purchasing solar power from Solar Power Developers (hereinafter ‘SPD’ in singular and ‘SPDs’ in plural).

7. On 18.08.2010, NVVNL issued a request for selection (hereafter ‘RFS’), which was followed by a request for proposal (hereafter ‘RFP’) on 29.10.2010.

8. Pursuant to the said RFP, NSPPL (a SPD) submitted its bid for establishing a solar power project and supplying power. NSPPL’s bid was accepted and NVVNL issued a Letter of Intent dated 11.12.2010 (hereinafter ‘the LoI’) accepting NSPPL’s proposal to set up the power project at Village Askandra, Tehsil Nachna in District Jaisalmer, Rajasthan.

9. Thereafter, on 08.01.2011, the parties entered into the Agreement. In terms of the Agreement, NSPPL agreed to set up a “Solar Power Project based on Advanced Technology of 5 MW capacity” (hereinafter ‘the Power Project’) and supply power for a period of twenty-five years commencing from the Commercial Operation Date (hereinafter ‘COD’) of the Power Project.

10. In terms of the Agreement, the Scheduled Commissioning Date (hereinafter ‘SCD’) was stipulated as 07.01.2012.

11. The Agreement also required NSPPL to furnish Performance Bank Guarantees (hereinafter also referred to as ‘the PBG’). It was further agreed that in the event there was a failure on the part of NSPPL to commission the Power Project by the SCD (that is, on or before 07.01.2012), NVVNL would have the right to levy liquidated damages in a phased manner and recover the damages by invokin

                Click Here to Read the rest of this document
                1
                2
                3
                4
                5
                6
                7
                8
                9
                10
                11
                SupremeToday Portrait Ad
                supreme today icon
                logo-black

                An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

                Please visit our Training & Support
                Center or Contact Us for assistance

                qr

                Scan Me!

                India’s Legal research and Law Firm App, Download now!

                For Daily Legal Updates, Join us on :

                whatsapp-icon Back to top