VIKAS MAHAJAN
Electrosteel Castings Limited – Appellant
Versus
Union of India – Respondent
JUDGMENT
Vikas Mahajan, J.
CM APPL. 30822/2023 (Application for interim relief)
1. Aggrieved by the inaction of respondents no.1 and 2 in determining the compensation which is due and payable to the Petitioner towards its land and mine infrastructure in respect of the Parbatpur Coal Block, the petitioner has filed the present writ petition seeking the following reliefs:
"(a) Declare that the Respondent No. 2's decision to not classify `Pits' as Mine Infrastructure is ultra vires the Act and accordingly declare that the `Pit' is Mine Infrastructure in terms of Section 3(1)(j) of the Act.
(b) Declare that 'Coal Washery' is Mine Infrastructure in terms of Section 3(1)(j) of the Act.
(c) Declare that all costs (apart from the costs for statutory consents/permits) which form part of the entry of "Mine Planning and Design expenses" in the audited balance sheet of the Petitioner are to be compensated as Mine Infrastructure in terms of Section 3(1)(j) of the Act.
(d) Declare that the decision of Respondent No. 2 to not classify `movable' assets that are meant for mining operations as Mine Infrastructure is ultra vires the Act.
(e) Declare that the list of assets, which form part of Annexure 28as
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.