DELHI HIGH COURT
PRATHIBA M.SINGH
Leighton India Contractors Private Ltd. – Appellant
Versus
DLF Ltd. – Respondent


JUDGMENT

1. The present petition under Section 9 of the Arbitration and Conciliation Act, 1996 has been filed by M/s Leighton India Contractors Pvt. Ltd ("Petitioner") against DLF Ltd. ("DLF") and M/s Axis Bank Ltd. (the "Bank") seeking the following reliefs:

    (a) Restraining Respondent No.1, its agents, officers, employees etc. from invoking and/or encashing Bank Guarantee(s) as detailed Paragraph No. [73] herein above issued by Respondent No.2 during pendency of the present Petition till conclusion of arbitration proceeding; and/or;

    (b) Restraining Respondent No.2, its agents, officers, employees etc. from making any payment to Respondent No.1 under Bank Guarantee(s) as detailed Paragraph No. [73] herein above during pendency of the present Petition till conclusion of arbitration proceeding; and/or;

    Or

    In alternative, if amount is already released by the Respondent no.2 in favour of the Respondent no.1 under Bank Guarantee(s) as detailed Paragraph No. [73],

    (c) Direct the Respondent No.1, its agents, officers, employees etc. to pay to and deposit the complete amount received under Bank Guarantee(s) as detailed Paragraph No. [73] with the Petitioner during pendency of the pres

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top