2026 Supreme(Del) 878

IN THE HIGH COURTOF DELHI AT NEW DELHI
NEENA BANSAL KRISHNA, J.
Lalit Kumar - Appellant
Versus
E-Homes Infrastructure Pvt. Ltd. - Respondent
RFA 949 of 2025
Decided On : 11-05-2026

Important Points

A civil suit containing omnibus, vague pleadings and misjoined claims constitutes an abuse of process. Furthermore, litigation barred by statutory jurisdiction, the expiry of the limitation period, or the prior withdrawal of identical claims without liberty is non-maintainable and subject to rejection.

Subject

Civil Law - Property and Real Estate Litigation

Act Referred

CIVIL PROCEDURE CODE : O.21, O.23 R.1, O.7 R.11, S.35(a), S.96
SPECIFIC RELIEF ACT : S.12
UTTAR PRADESH APARTMENTS ACT : S.14(5)
ARBITRATION AND CONCILIATION ACT : S.8
RERA ACT : S.79

Headnote

(A) Civil Procedure Code, 1908 - Order VII Rule 11 - Rejection of Plaint - Grounds for - Abuse of process - Omnibus and vague pleadings - Misjoinder of causes of action - Forum shopping - Where a suit is withdrawn without seeking liberty, a fresh suit on the same cause of action is precluded by Order 23 Rule 1 - (Paras 32, 35, 37, 38).

(B) Real Estate Regulation Act - Section 79 - Bar of Jurisdiction - Civil courts are prohibited from entertaining suits or proceedings in respect of any matter which the specialized regulatory authority is competent to decide - (Para 33).

(C) Limitation Act - Recovery of money - Claims for refund arising out of purchase agreements - Action initiated beyond the statutory limitation period of three years is time-barred - (Para 34).

Facts of the case:
The appellant and several other plaintiffs filed a suit against a property developer seeking damages, mandatory injunctions, and a rendition of accounts regarding alleged project mismanagement. The claims encompassed multiple grievances including area discrepancies, financial overcharges, and membership issues. Similar complaints had previously been filed in consumer forums and civil courts, which were either dismissed or withdrawn by the plaintiffs without seeking liberty. The trial court rejected the plaint as an abuse of process, noting the lack of clear cause of action, multiplicity of suits, and jurisdictional bars.

Findings of Court:
The court found that the suit was an abuse of the legal process, characterized by the filing of omnibus, vague, and time-barred claims. It observed that the plaintiffs were engaging in forum hunting and attempting to re-litigate issues that had already been subject to judicial or regulatory adjudication.

Issues: The primary issues included whether the civil suit was maintainable given established jurisdictional bars, the bar of limitation for money recovery, the procedural consequences of withdrawing previous suits without liberty, and the validity of clubbing multiple distinct claims into an omnibus proceeding.

Ratio Decidendi: The court concluded that the lawsuit constituted an abuse of process as it failed to disclose a clear, actionable cause of action, violated procedural rules against re-litigating withdrawn matters, and attempted to circumvent the exclusive jurisdiction of specialized regulatory bodies.

Result: Appeal dismissed with costs.

Advocates Appeared:
For the Appellant :Mr. M P Sahay, Ms. Yaman Verma, Ms. Chitra Chanda, Mr. Kartik Jindal and Mr. Kartik Virmani, Advocates.
For the Respondent:Mr. Sunil Dalal (Sr. Adv.) alongwith Srinivasan Ramaswamy, Mehak Nakra, Gunjan Suyal, Ankit Rana, Shipra Bali & Sarthak Malhotra, Advocates.

Table of Content
1. nature of the appeal and procedural context. (Para 1 , 2)
2. factual allegations regarding real estate development and association formation. (Para 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12)
3. specific grievances regarding maintenance charges, services, and construction. (Para 13 , 14 , 15 , 16 , 17 , 18 , 19 , 20 , 21 , 22 , 23 , 24 , 25)
4. history of prior consumer and civil litigation. (Para 27 , 28 , 29)
5. reliefs sought by the plaintiffs in the suit. (Para 30)
6. necessity of pleading a valid cause of action. (Para 32)
7. jurisdictional bar of rera and res judicata effect. (Para 33)
8. principles of limitation, mis-joinder, and previous withdrawal. (Para 34 , 35 , 36 , 37)
9. dismissal of appeal and assessment of costs. (Para 38 , 39)

JUDGMENT :

NEENA BANSAL KRISHNA, J.

1. Regular First Appeal under Section 96 read with Order XLI CPC has been filed by the Plaintiff/Appellant whereby his Suit for Compensation/Damages, Mandatory Injunction, Declaration and for Rendition of Accounts, has been dismissed, vide Judgment dated 31.08.2024

2. The 12 Plaintiffs including the Appellant had filed Civil Suit No.220/2024 under Section 12 Specific Relief Act for Compensation/Damages/Mandatory Injunction/Declaration and for Rendition of Accounts.

3. The facts as stated in the Plaint, are that the Defendant E-Homes Infrastructure Pvt. Ltd. is a Private Limited Company engaged in the business of real estate development having its registered office at Kasturba Gandhi Marg, Delhi. The Defendant was allotted land by Noida Authority, to develop the land in various phases which included the Project the Jewel of Noida (hereinafter referred to as ‘the Project’), to develop and complete the same into a Group Housing Complex.

4. The public at large including the Plaintiffs, were lured by the representations that the Project would be a state-of-the-art Project with the best of facilities and amenities. Various advertisements in print and electronic media were taken out specifying the areas, super areas and carpet areas, maintenance aspects, quality of construction, spacious and convenient car parking etc. The Plaintiffs applied for their respective units/apartments in the said Project. Offer letters were issued broadly underlining the terms and conditions for the sale of the properties to the Plaintiffs.

5. The Plaintiffs claimed a massive shortfall and disparity in actual/carpet area vis a vis the super area, which was in total violation of the permitted loading limit of the Builder Buyer Agreement and other laws, rules and guidelines.

6. Despite the law and rule being clear on the area, super area and carpet area, maintenance charges and all other aspects, the Defendant Builder in a mala fide manner did not transfer the maintenance to the Owner’s Association, which it was bound to do. More than 60 months have elapsed since the possession was offered/taken, but till date the transfer has not happened. The Defendant Builder is obviously usurping money from the residents in the name of maintenance and profiting from the same.

7. The Defendant Builder has also been trying to create all sorts of obstacles and hindrances in formation of lawful AoA/Owner’s Association. The one which has been formed is wholly illegal and various illegalities including forgery is being committed by the Defendant Builder. The concerned residents/ Plaintiffs and others, have been pursuing criminal litigation before the jurisdictional Courts in District Gautam Budh Nagar (U.P.). The Membership has been taken @ Rs.1,000/- and the signatures had been obtained in the Register, on various dates in the first half of the year 2018, but no AoA has been formed and there are gross illegalities in its formation and functioning.

8. The Defendant has deliberately kept Units unsold, so as to create grounds for not transferring the maintenance to the Owner’s Association, clearly to negate Section 14(5) of the U.P. Apartments Act, 2010 and also Section 11 of RERA. Furthermore, one Tower