THE STATE CONSUMER DISPUTES
REDRESSAL COMMISSION, DELHI
Hon’ble Mr. Justice R.N. Mittal, President;
Sh. B.L. Anand, Member; Dr. (Mrs.) Avtar Pennathur, Member
R.P. BEDI—Complainant
versus
KEDAR CO-OPERATIVE GROUP
HOUSING SOCIETY LIMITED—Respondent
Case No. C-111 of 1990—Decided on 30.12.1991
COOPERATIVE HOUSING SOCIETY - DELAY IN POSSESSION OF FLAT - INTEREST ON DEPOSITED AMOUNT - CALCULATION - FACTORS TO BE CONSIDERED - HOUSING CONSTRUCTION WORK - TIME CONSUMING - ALLOWANCE OF TIME TO BUILDER - INTEREST AWARDED FROM A PARTICULAR DATE - REFUND OF AMOUNT FOR CHANGE OF MATERIAL AND ADDITIONAL AMOUNT CHARGED - DENIED - CLAIM FOR COMPENSATION FOR NOT PROVIDING SWIMMING POOL AND USING CHEAP MATERIAL - REJECTED - COMPLAINT PARTLY ALLOWED.
Fact of the Case:
The complainant, a member of the respondent cooperative housing society, claimed interest on the amount deposited by him for the purchase of a flat, due to delay in possession of the flat. He also claimed refund of certain amounts for change of material and additional amount charged by the society.
Finding of the Court:
The court found that the delay in possession of the flat was not attributable to the society, as the construction work was time-consuming and the society had taken reasonable steps to complete the project. The court also found that the complainant was aware of the change in material and the additional amount charged, and had not objected to it at the time of the annual general meeting of the society.
Issues: 1. Whether the society was liable to pay interest on the amount deposited by the complainant for the purchase of the flat, due to delay in possession of the flat? 2. Whether the complainant was entitled to refund of certain amounts for change of material and additional amount charged by the society?
Ratio Decidendi: 1. The court held that the society was not liable to pay interest on the amount deposited by the complainant for the purchase of the flat, due to delay in possession of the flat, as the delay was not attributable to the society. The court considered the fact that construction work is time-consuming and that the society had taken reasonable steps to complete the project. 2. The court held that the complainant was not entitled to refund of certain amounts for change of material and additional amount charged by the society, as he was aware of the change in material and the additional amount charged, and had not objected to it at the time of the annual general meeting of the society.
Final Decision: The complaint was partly allowed. The society was directed to pay interest to the complainant from a particular date, and the complainant's claims for refund of certain amounts were rejected.
Mr. Justice R.N. Mittal, President— The facts of the case have been given in our judgment dated 29-1-91 by which we decided a preliminary objection of the respondent. That may be deemed to be a part of the present judgment. The/Counsel for respondent appeared before us on 3-7-91 and made a statement that he wanted to withdraw from the case as the respondents were not attending his office to give instructions. He requested for one week’s adjournment to make an application for that purpose. At his request the case was adjourned to 10-7-91. The learned Counsel on the next date of hearing moved as application that he be allowed to withdraw from the suit. We allowed him to do so. No one was present on behalf of the respondents consequently they were proceeded against exparte. A notice was ordered to be issued to the respondents informing them that they had been proceeded against ex-parte as their counsel had withdrawn from the proceedings. The respondents, however, did not appear.
2. The complainant has claimed an amount of Rs. 1,24,748.10 on account of interest on the amount of Rs. 4,15,827/- from 1.1.89 to 31.8.90 @ 18% P.A. The total amount is alleged to have been deposited by him before 1.1.89. It is argued by the learned Counsel for the complainant that an assurance was given to the complainant by the respondents that the flat would be handed over to him by 31.12.88. He submits that the flat was actually delivered in September’ 90 and therefore the complainant is entitled to the interest on his amount from 1.1.89 to 1.9.90.
3. We have duly considered the arguments. It is common knowledge that the house construction work is a tedious and time consuming work. It has been seen that the house is normally not completed within the expected period. It is true, that the respondents assured the complainant that the house would be handed over to him by December’ 88. However, no fault can be found with the builder, if some more time is taken by them in completing a multi-storeyed building. We think that some allowance regarding time should be given to the respondents for completing and obtaining the completion certificate of the building. In the present case the respondents, in view of the assurance should have completed the building by the end of 1988. We allow a further period of 10 months to the respondents to complete the building. Consequently, we are of the opinion that the complainant is entitled to interest from 1.11.89 to 31.8.90.
4. Now the question arises at what rate the complainant should be awarded the interest. The Counsel for the complainant has placed reliance on M.K. Gupta v. Lucknow Development Authority (First Appeal No. 21 of 1990), decided by the National Commission, reported as 1990-91 (3) MRTP Reports 98 = I (1992) CPJ 66 (NC). In that case the complainant was allowed 16% interest on the amount deposited on account of the late delivery of possession of the house by the respondent. He also referred to a case B.L. Putney and Krishna Putney v. Delhi Development Authority (Case No. C-15/1991 decided on 24.1.91) I (1991) CPJ 345, reported as, I (1991) CPJ 345 decided by this State Commission. In that case we awarded interest @ 15% p.a. In view of the observations of the National Commission we grant interest to the complainant @ 16% P.A. The total amount of interest at the said rate, for 10 months on Rs. 4,15,000/- comes to Rs. 55,333.00.
5. The complainant has claimed refund of Rs. 15,000/- .on account of use of Dana instead of Dholpur Stone and Rs. 9,500/- charged as additional amount by the Society. In paras 5 & 6 of the complaint the complainant, however, has claimed Rs. 19,000/- only. We restrict these claims to Rs. 19,000/- In the reply to the complaint, it is stated, that the Society did not make any unjust demand! from its members and the averments in the com plaint were wrong. It is true that in letter dated 25.7.88 it is mentioned that Dholpur Stone was to be used in the outer finish of the building. In order
1. I (1992) CPJ 66 (NC)=First Appeal No. 21 of 1990. (Relied)[Para 4]
AI
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.