WEST BENGAL STATE CONSUMER DISPUTES
REDRESSAL COMMISSION, CALCUTTA
Hon’ble Mr. Justice Mr. A.K. Bhattacharjee, President;
Prof. Sunil Kanti Kar & Mrs. S. Dutta, Members
CESC LTD.—Complainant
versus
RAM PRASAD DAS & OTHERS—Opp. Parties
S.C. Case No. 243/A of 1994—Decided on 16.8.1994

An applicant for a new electric connection is a consumer within the meaning of the Consumer Protection Act, 1986.

Headnote:

CONSUMER PROTECTION ACT, 1986 - ELECTRICITY CONNECTION - APPLICANT FOR NEW CONNECTION - WHETHER A CONSUMER - INTERPRETATION OF SECTION 2(1)(D)(II) - HELD, AN APPLICANT FOR NEW ELECTRIC CONNECTION IS A CONSUMER WITHIN THE MEANING OF THE ACT.

Fact of the Case:

The appellants, C.E.S.C. Ltd., refused to grant electric connections and install new meters to a group of complainants on the ground that they were beneficiaries of previous meter holders who were in arrears of electricity charges. The complainants filed complaints with the Calcutta District Forum (C.D.F.) alleging deficiency in service.

Finding of the Court:

The C.D.F. rejected the contentions of the C.E.S.C. Ltd. and held that the complainants were consumers under the Consumer Protection Act, 1986 and that they were not liable for the arrears due from previous consumers. The C.E.S.C. Ltd. appealed the decision of the C.D.F.

Issues: 1. Whether an applicant for a new electric connection is a consumer within the meaning of the Consumer Protection Act, 1986? 2. Whether the complainants were liable for the arrears due from previous consumers?

Ratio Decidendi: 1. The court held that an applicant for a new electric connection is a consumer within the meaning of the Consumer Protection Act, 1986. The court interpreted Section 2(1)(d)(ii) of the Act, which defines a consumer as a person who hires any service for consideration, to include an applicant for a new electric connection. The court reasoned that an applicant for a new connection has to pay the necessary charges after the connection is given and therefore he is a person who has hired the services of the O.P. for consideration which is promised. 2. The court held that the complainants were not liable for the arrears due from previous consumers. The court found that there was no evidence to suggest that the complainants were beneficiaries of the old consumers.

Final Decision: The court dismissed the appeal and confirmed the order of the C.D.F.

ORDER

Mr. Justice A.K. Bhattacharjee, President—This is an apeal against an order dated 12.4.94 passed by the Calcutta District Forum in C.D.F. Cases Nos. 3436 to 3457 of 93 and 3486 to 3487 of 93. In the aforesaid cases a group of complainants at different premises filed complaints that although they had applied for electric connection to the C.E.S.C. Ltd. the said Co. did not agree to grant any electric connection and to instal new meters on certain grounds. In short the complainant’s objection to the grant of electric connection to the complainants was that the complainants were actually beneficiaries of the previous meter holders who were in arrear of charges for electricity to the tune of Rs. 81,605.13 P. The C.E.S.C. Ltd. further contended that the complainants were liable to clear up the arrears in respect of the previous meters and that unless this was done they were not entitled to new electric meters. The C.E.S.C. also contended that the appellants were not consumers within the meaning of the Consumer Protection Act, 1986 and that the C.D.F. could not grant any relief under the said Act. On a consideration of the cases put forth by both the parties, C.D.F. had rejected the contentions of the C.E.S.C. Ltd. and held that the complainants were consumers under the Act and that they were not liable for the arrears due from previous consumers. Accordingly the District Forum ordered that the C.E.S.C. should provide a new meter to each of the complainants within one month after observing all necessary formalities.”

2. The C.E.S.C. Ltd. is the appellant here. They have reiterated the contentions which were raised before the C.D.F. and have stated in their Memo of Appeal that the points raised by them were not properly decided by the District Forum. They have also stated that they should be given an opportunity to establish that the applicants for new meters were beneficiaries of the old consumers who were in arrear of a huge amount of electric charges.

3. The main point of argument on behalf of the applicant is that the O.P.-complainants were not the consumers. In this respect they have relied on a decision of the Karnataka State Consumers Disputes Redressal Commission reported in II (1991) CPJ 455 (Ahmed Ul-Haq v. Asst. Engineer, K.E.B. Chamarajannagar & Ors.). In the aforesaid case the complainants had filed a registration fee of Rs. 50/- and had deposited a sum of Rs. 12,470/- being three months minimum deposit. The Karnataka State Commission held that the aforesaid deposit of money could not be treated as consideration for hiring the services of the Karnataka Electricity Board. Accordingly it was held that complainant was not a consumer and accordingly the complaint was dismissed.

4. Another case of the Tamilnadu State Commission reported in II (1992) CPJ 761 (Consumer Protection Council, Tamilnadu v. The Chairman, Electricity Board & Anr.) had also been brought to our notice. In this case the Tamilnadu State Commission had held an opposite view. The view of the Commission in the said case was that the complainant therein was a potential user. Under Section 2(1)(d)(ii) of the Consumer Protection Act a person is a consumer who hires any service for consideration which has been paid or promised or partly paid or partly promised. On the basis of this definition it was held by the Tamilnadu State Commission that a person who applies for electric connection has to pay the necessary charges after the connection is given and therefore he is a person who has hired the services of the O.P. for consideration which is promised. In the instant appeal the complainants had prayed for new meters separately to the C.E.S.C. Ltd. The Company conducted inspection at site and gave offer to the complainants for depositing the initial cost of Rs. 60/- each. But ultimately connection was refused on the ground that arrears left by the previous consumers have not been paid by the complainants.

5. We have considered the views of the two different State





Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top