UNION TERRITORY CONSUMER DISPUTES
REDRESSAL COMMISSION, CHANDIGARH
Honble Mr. Justice J.B. Garg, President;
Mr. Sada Nand & Mrs. P. Ojha, Members
SAB INDUSTRIES LTD.—Complainant
versus
THE INDIAN OVERSEAS BANK—Respondent
Complaint Case No. 432 of 1993—Decided on 20.12.1996
BANK GUARANTEE - VALIDITY - SECTION 126 OF THE INDIAN CONTRACT ACT, 1872 - THE COURT HELD THAT THE COMPLAINANT COULD NOT INVOKE THE JURISDICTION OF THE CONSUMER PROTECTION ACT, 1986 BECAUSE HE WAS NOT A 'CONSUMER'.
Fact of the Case:
THE COMPLAINANT ENTERED INTO AN AGREEMENT FOR CONSTRUCTION OF UNDERGROUND WORKS OF GAJ HYDEL PROJECT AT CHARRI IN TEHSIL DHARAMSALA (H.P.). M/S. KROPINIK CABLEWAYS PRIVATE LIMITED WERE TO ACT AS SUB-CONTRACTOR. THE COMPLAINANT AGREED TO MAKE AN ADVANCE PAYMENT TO THE EXTENT OF RS. 2.50 LACS TO AFORESAID SUB-CONTRACTOR AND IN THIS REGARD THE AFORESAID SUB-CONTRACTOR FURNISHED A BANK GUARANTEE ON 5.5.89 WHICH WAS VALID TILL 4.5.90 FOR A PERIOD OF ONE YEAR.
Finding of the Court:
THE COURT HELD THAT THE COMPLAINANT COULD NOT INVOKE THE JURISDICTION OF THE CONSUMER PROTECTION ACT, 1986 BECAUSE HE WAS NOT A 'CONSUMER'.
Issues: WHETHER THE COMPLAINANT COULD INVOKE THE JURISDICTION OF THE CONSUMER PROTECTION ACT, 1986.
Ratio Decidendi: THE COURT HELD THAT THE COMPLAINANT COULD NOT INVOKE THE JURISDICTION OF THE CONSUMER PROTECTION ACT, 1986 BECAUSE HE WAS NOT A 'CONSUMER'.
Final Decision: COMPLAINT DISMISSED.
Mr. Sada Nand, Member—This judgment shall dispose of Complaints No. 432 and 435 of 1993 wherein the date of execution of the Bank guarantee was 5.5.89 and also Complaints No. 433 and 434 of 1993 wherein the date of execution of the Bank guarantees was 21.3.89 and for the reason that the facts in question and the parties relating to these complaints happen to be the same.
2. Briefly the complainant entered into an agreement for construction of under ground works of Gaj Hydel Project at Charri in Tehsil Dharamsala (H.P.). M/s. Kropivnik Cableways Private Limited were to act as sub-contractor. The complainant agreed to make an advance payment to the extent of Rs. 2.50 lacs to aforesaid sub-contractor and in this regard the aforesaid sub-contractor furnished a Bank guarantee on 5.5.89 which was valid till 4.5.90 for a period of one year. The respondent Bank had undertaken to pay to the complainant on demand all the amounts which were payable by the sub-contractor alongwith any amount upto the maximum sum of Rs. 2.50 lakhs. There was an agreement that if there was any loss suffered by the Company, it was to be of the Company itself which would be final and binding on the Bank. It asked the complainant by means of a letter dated 17.3.90 not to release any payment directly to the sub-contractor as their liability under guarantee had to be reduced in proportion to the work done by the sub-contractor. The respondent was again informed on 2.5.90 and 3.5.90 before the expiry of the Bank guarantee on 4.5.90 that M/s. Kropivnik Cableways Private Limited the said sub-contractor had committed a breach of the terns and conditions of the agreement executed with complainant and the respondent Bank was required to make the payment of the sum of Rs. 2,50,000/-to the complainant. The complainant again wrote to the respondent on 11.5.90, but of no avail. The reliefs claimed by the complainant are briefly as under:
(i) A sum of Rs. 2.50 lacs on account of the deficiency on the part of the respondent;
(ii) Rs. 1.00 lack on account of damages together with Rs. 15,000/as expenses of litigation and interest @ 25% per annum.
The Indian Overseas Bank, the respondent filed a reply wherein it has been averred that M/s. Kropivnik Cableways Pvt. Ltd., the sub-contractor was a necessary party and without impleading it the dispute could not be decided. There was also a plea that it was barred by limitation inasmuch as cause of action arose to the complainant on 5.5.90. The other pleas are that the complainant himself violated Clauses 2 and 3 by making payments directly to the sub-contractor instead of routing the payments through the respondent Bank. The complaint has been instituted in violation of Clause No. 5 of the Bank guarantee. The complainant was not the sole Judge to assess the losses occurred by virtue of Clauses 2 and 3 of the guarantee. It has further been averred that since the complainant himself violated the guarantee, the respondent Bank was not liable. It was denied that respondent Bank did not reply to the communication received from the complainant and on the contrary the respondent Bank had been informing the complainant by means of letter dated 17.3.90 that the complainant is violating the agreement by making direct payments to the sub-contractor. The letter dated 21.3.90 was a routine letter asking the complainant to surrender the papers after the expiring of the guarantee. The other pleas were that the respondent Bank rightly turned down as illegal, wrong and frivolous demands of the complainant that this Commission had no jurisdiction to try such complicated matters where several issues were involved and the complainant could at the most approach the Civil Court.
3. In this case an important plea raised on behalf of the respondent is that the work pertaining to construction of underground of Gaj Hydel Project was entrusted to M/s. S.A. Builders Ltd., at the same time the requisite equipment, financial resources and personnel and kn
AI
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.