UNIT TRUST OF INDIA—Appellant
versus
K.S. BADWAL—Respondent
Appeal Case No. 224 of 2002—Decided on 7.1.2003

Advocates:
Counsels for the Parties :
For the Appellant :Mr. B.J. Singh, Advocate.
For the Respondent: None.

Condonation of delay may be allowed if the reasons for delay are deemed bona fide by the court.

Headnote:

Condonation of Delay - Appeal Filing - The court allowed the condonation of delay in filing the appeal due to bona fide reasons related to office shifting and restructuring, and listed the appeal for hearing.

Fact of the Case:

The appellant sought condonation of delay in filing the appeal against the order passed by the District Consumer Disputes Redressal Forum-II, U.T., Chandigarh.

Finding of the Court:

The court allowed the application seeking condonation of delay and listed the appeal for hearing on 30.1.2003.

Issues: Delay in filing the appeal, reasons for delay, respondent's objection, and listing of the appeal for hearing.

Ratio Decidendi: The delay in filing the appeal was condoned based on the appellant's reasons related to office shifting and restructuring, deemed as bona fide.

Final Decision: The application seeking condonation of delay was allowed, and the delay in filing the appeal was condoned. The appeal was listed for hearing on 30.1.2003.

ORDER

Mr. Justice K.K. Srivastava, President—The appellant seeks condonation of delay in filing the appeal against the order passed by the District Consumer Disputes Redressal Forum-II, U.T., Chandigarh (for short hereinafter referred to as the District Forum) on 26.6.2002. The certified copy of the order was prepared on 12.6.2002 and sent to the parties including the appellant by post free of charge. It has been alleged that the copy was received by the Chandigarh Office of the appellant on 15.7.2002 and the appeal was to be filed by 14.8.2002. It has, however, been filed on 3.9.2002.

2. There is delay of 20 days in filing the appeal. According to the case of the appellant, the delay occurred due to the fact that the dealing office at Mumbai received the communication from the Chandigarh Office for permission to file the appeal on or about 21.7.2002 when the entire office was under process of shifting including restructuring and placement of staff from Mumbai Main Branch to Branch Office at Belapur, New Mumbai. The opinion of the Solicitors were sought and the papers were sent to the Delhi Office which is the concerned office with advice to take steps to file the appeal against the impugned order. The Delhi Office of the appellant received advice from its Mumbai Office on or about 11.8.2002 and incidentally the Delhi Office of the appellant was under process of shifting from Herald House, II Floor, 5-A, Bahadur Shah Zafar Marg, New Delhi and it took some time to connect the papers and refer. The papers were then transmitted to Chandigarh Office for filing the appeal which was eventually filed on 3.9.2002. It is alleged that there is bona fide delay of 20 days in filing the appeal and the same is due to the factors mentioned above.

3. Notice of application was sent to the respondent who sent written reply to the application seeking condonation of delay. It was contended that the Branch Manager could have filed the appeal in time. It was further contended that even if Chandigarh Branch Manager is not competent to file the appeal directly then why he had filed his affidavit under his signatures and seal.

The objection raised in the written reply which was received on 23.10.2002 are to be read along with another written letter received from the respondent which is dated 11.12.2002 wherein, in para No. 3, it was averred as under :

“3. Please decide the appeal on basis of my written arguments and merits of the case. UTI cannot get all the pardons for its delay in payments and delay in appeal even.”

4. The appellant has given reasons for delay in filing the appeal and these reasons, as mentioned above, comprise of the communication being sent to the Mumbai Office which was under process of shifting from one place to another and then at the Delhi Office, where under somewhat similar circumstances, the office was being in the process of shifting and the appeal was filed on 3.9.2002 in which delay of 20 days took place. The reasons mentioned by the appellant appear to be sufficient where the delay occurred due to bona fide reasons and the same is liable to be condoned.

5. Resultantly, the application seeking condonation of delay is allowed and the delay in filing the appeal is condoned. The appeal be listed for hearing on 30.1.2003. The respondent be informed about this order. He has already filed written reply to the memo of appeal as well. The respondent may be informed that in case he wants to put in appearance in appeal for submission of arguments personally, he should appear before the Commission on 30.1.2003. The record of the complaint case be summoned in triplicate from the District Forum-II, U.T., Chandigarh.

6. Vide our detailed order of the even date recorded separately, the application seeking condonation of delay has been allowed and the delay in filing the appeal has been condoned. The parties are directed to appear before this Commission on 30.1.2003 for hearing of appeal on merit.

Application allowed.

––