SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

Supreme Court of India
Shivaraj V. Patil & D.M. Dharmadhikari, JJ.
KANPUR DEVELOPMENT AUTHORITY—Appellant
versus
SHEELA DEVI & ORS. ETC.—Respondents
Civil Appeal Nos. 913-914 of 1998 from Judgment and Order dated 21.5.1997 of Allahabad
H.C. in C.M.W.P. Nos. 303 and 9478 of 1995—Decided on 28.11.2003

Counsel for the Parties :
For the Appellant :Mr. Vikas Singh, Ms. Amrita Narayan, Advocates for Mr. L.R. Singh, Advocate.
For the Respondents:Mr. Ranjeet Kumar, Senior Advocate with Ms. Bina Gupta, Ms. Rakhi Ray and Ms. Sreedevi Raja, Advocates.

The determination of cost of house/flat or escalation of cost cannot be arbitrary or erratic. The authority has to broadly satisfy by placing material on record to justify the escalation of cost of a house/flat. Whether the delay was caused by the allottee or the authority itself is also a factor which has bearing in determination of the cost of house/flat.

Headnote:

KDA - Housing Allotment Dispute - [HUDCO Act, Section 4(1)(a); Indian Penal Code, Sections 193, 196, 199, 200, 463, 464, 465, 467, 468, 471 read with Section 120-B; Code of Criminal Procedure, Section 340 read with Section 195] - The court discussed the terms and conditions of the housing scheme, the delay in allotment, and the arbitrary increase in house prices by KDA. The court found that the delay in allotment was caused by KDA's own actions and that the increase in house prices was unjustified and contrary to the terms of the brochure. The court dismissed the appeals, upholding the High Court's decision to quash the increase in house prices and directed KDA to deliver possession of the houses at the cost fixed in the brochure.

Fact of the Case:

Kanpur Development Authority (KDA) appealed against a High Court order in a housing allotment dispute. KDA delayed allotment and increased house prices, leading to litigation by affected applicants. The High Court found fault with KDA and directed it to deliver possession of houses at the cost fixed in the brochure.

Finding of the Court:

The court found that KDA's delay in allotment and arbitrary increase in house prices were unjustified and contrary to the terms of the brochure. The High Court's decision to quash the increase in house prices and direct KDA to deliver possession of the houses at the cost fixed in the brochure was upheld.

Issues: Delay in housing allotment, arbitrary increase in house prices, compliance with terms of the housing scheme brochure.

Ratio Decidendi: The delay in allotment was caused by KDA's own actions, and the increase in house prices was unjustified and contrary to the terms of the brochure. KDA was directed to deliver possession of the houses at the cost fixed in the brochure.

Final Decision: The appeals were dismissed, upholding the High Court's decision to quash the increase in house prices and direct KDA to deliver possession of the houses at the cost fixed in the brochure.

JUDGMENT

Shivaraj V. Patil, J.—Kanpur Development Authority (KDA) has filed these appeals challenging the correctness and validity of the common order dated 21.5.1997 made by the Division Bench of the High Court in Writ Petitions.

2. Three schemes were floated by KDA in September, 1978 with financial support of ‘HUDCO’ “on no profit no loss basis”. The three Schemes were: (1) For Economically Weaker Section; (2) For Lower Income Group and (3) Middle Income Group. Applications were invited in the prescribed form fixing the last date as 29.9.1978. The applications were to be made in the prescribed form alongwith the earnest money for each category. A brochure was issued showing the cost of each house and terms and conditions of the Schemes. In these cases, we are not concerned with the houses constructed in two other schemes which were allotted to the applicants on the basis of lottery on 25.10.1980 and cost specified in the brochure and the possession of the houses was delivered to them. However, the applicants (respondents herein) in the Middle Income Group were not allotted the houses and their applications were kept pending for more than 18 years for no fault of them.

3. As per the terms and conditions mentioned in the brochure in the MIG Category, the applications were to be made alongwith the earnest money by 29.9.1978. The estimated cost of each house was specified in the brochure as Rs. 48,000/-. The persons whose income was between Rs. 601/- to Rs. 1,500/- per month were eligible for Middle Income Group Houses. The houses were to be allotted among the valid applicants by lottery. After the lottery was drawn and on receipt of letter of information of allotment, the applicants had to deposit balance of the 1/4th of the cost of the house. Thereafter, physical possession of the houses was to be delivered to the allottees and the remaining 3/4th of the cost of the house i.e. Rs. 36,000/- was to be paid by the allottees in 48 quarterly instalments in 12 years with 11.5% interest as per the brochure. Since there were only 108 valid applications altogether for 111 MIG houses, all the applicants could have been allotted MIG houses when 1/4th cost of the house was deposited by the applicants as on 31.3.1979, what remained was only to draw a lottery among the 108 valid applicants for the specific houses to each one of the applicants. And thereafter the possession of specified house was to be delivered to each allottee as the constructions of 111 MIG houses were completed in 1980.

4. However, KDA chose to include names of some more applicants after the last date i.e. 29.9.1978, which gave rise to disputes. Some affected applicants filed suits in 1981/1982. None of these respondents were parties in those suits.

5. The Court finding fault with the KDA decreed the suit and directed it to allot the houses to 108 valid applicants keeping 8 houses reserved for the persons who are plaintiffs in those two suits. The appeals filed by the KDA against the decree passed by the Trial Court were also dismissed. Instead of complying with the decree, KDA increased the cost of each house from Rs. 48,000/- to Rs. 2,08,000/- by the Notification dated 24.12.1994 stating that each applicant had to deposit a further sum of Rs. 40,000/- and in case of default the name of the applicant would not be included in the list of lottery for allotment of houses. In these circumstances, some of the respondents were compelled to file writ petitions.

6. The writ petitions were admitted and interim orders were issued to include the names of 85 general category applicants in the lottery. In spite of the interim order dated 4.1.1995, KDA again issued a notification on 10.1.1995 stating that the date of lottery had been extended to 17.1.1995.

7. The lottery was drawn among the 108 valid applications, keeping 8 houses reserved to the plaintiffs in the two suits. In February, 1995, information of allotment was issued to all the allottees along with demand for Rs. 24,000/- from e




















































































































Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top