2012(2) CPR 167
MAHARASHTRA STATE CONSUMER DISPUTES REDRESSAL COMMISSION, MUMBAI
P.N. Kashalkar, Presiding Member and Dhanraj Khamatkar, Member
Sudarshan Jagannath Singh and Anr. —Complainant
versus
Sainath Enterprises —Opposite Party
Complaint Case No. CC99/263
Decided on 8.11.2011
P.N. Kashalkar, Presiding Member— This complaint is filed jointly by Shri Sudarshan Jagannath Singh and his wife Smt. Veena Sudarshan Singh. Both resident of Powai Vihar Complex, Building No.4, B-103/l04, A.S. Marg, Powai, Mumbai-400076 against M/s. Sainath Enterprise of Mulund (West), Mumbai. According to Complainants opponent was building residential flat premises. Hence, they approached opponent and at his instance booked two different flats. The opponent prepared two separate agreements, one for the Complainant No.1 and another for the Complainant No.2. Complainants agreed to purchase Flat Nos. 103B and 104B respectively in Building No.4 to be constructed in Powai Vihar Complex. Both the agreements were entered into by the Complainants with the Opponent on 12.4.1993. However, though there were two agreements and the flat numbered as two flats, the premises covered under both the agreements consisted of only one single flat admeasuring 800 and 500 sq. ft. respectively. In accordance with the two agreements, the Opponents were bound to construct one single flat admeasuring 1300 sq.ft. builtup area and possession was to be handed over to the Complainant by July, 1993. The opponent did not complete construction in time and handed over possession on 5.12.1997. The opponent constructed the flats covered under both the agreement as one single flat with main entrance door, one kitchen and provided one electric meter with Consumer No. G-11492374 and other amenities meant for one single flat. According to Complainants for delayed payments the agreement stipulated interest @12% per annum but opponent demanded interest @18% per annum for delayed payment from the Complainants. So Complainants are also entitled to claim interest @18% per annum from the Opponents for inordinate delay on their part in handing over possession of the flat. Total cost of the flat was Rs.9,10,000. The opponent agreed to hand over possession by July, 1993 but possession was given on 5.12.1997. Therefore, Complainant pleaded that they are entitled to claim interest @)18% per annum from August 1993 to November, 1997 amounting to Rs.7,09,800. Complainants further pleaded that instead of total area of the flat which would have been 1300 sq. ft., on measurement they found actual flat area of 1100 sq. ft. So area of 200 sq. ft. was found short. Therefore, opponents are bound to refund excess amount paid by the Complainants @ Rs.700 per sq.ft. amounting to Rs. 1,40,000. They also pleaded that Opponent agreed to provide teak wood doors but they provided commercial quality flush doors and difference in costs comes to Rs.35,000 for 8 doors. They demanded the said amounts from the Opponent, but opponent refused to do so and, therefore, they sent registered notice through Advocate K.N.S. Pillai on 29.3.1999 and claimed amount of Rs.8,84,000 along with Rs.1,000 as notice charges. After receipt of notice the opponent addressed letter dated 9.4.1999 and took up a contention that they had given a writing for full satisfaction of the work before taking possession of the flat. The Complainants pleaded that they were forced to record satisfaction note before handing over possession of the flat by the opponent. They pleaded that even additional lift is not provided by them though they admitted and therefore, the opponent should be directed to provide additional lift.
2. Opponent filed written version and denied the allegations made by the Complainants. According to Opponent there was no compulsion for the Complainant to enter into two different agreements, one in his name and one in his wife’s name for Flat Nos. 103B and 104B. This was done to suit convenience of Complainant. Opponent also pleaded that there was no compulsion to construct a singly flat of 1300 sq. ft. The possession of the flat was taken by the Complainants with due inspection and electric meter was installed at his request with larger capacity and amperage. The opponent pleaded that Complainants were not ent
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.