NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION, NEW DELHI
J.M. Malik, Presiding Member and Vinay Kumar, Member
Hanshmukh Patel & Ors. —Petitioners
versus
Dr. Sunil Kumar Majhi & Ors. —Respondents
Revision Petition No. 3745 of 2012
(Against the order dated 18.05.2012 in Appeal No. FA/399/2010 of the West Bengal State Consumer Disputes Redressal Commission, Kolkata)
Decided on 18.10.2012

Important Points

IMPORTANT POINT
Non-providing of facilities constitutes continuous cause of action.

Subject

Consumer Law - Real Estate

Act Referred

CONSUMER PROTECTION ACT : S.15, S.17, S.19, S.21

Headnote

Consumer Protection Act, 1986—Sections 15, 17, 19 and 21—Real estate—Apartment—Shortcomings—District Forum allowed complaint with costs of Rs.15,000/- and directed opposite parties to provide community hall and underground reservoir and further directed to demolish wall causing hindrance in main entrance leading to lift—This is a continuous cause of action and complaint was not barred by time—Agreement to sell specifies some terms and conditions—Parties are bound by agreement—District Forum also appointed Advocate Commissioner—His report fortifies case of complainants—Revision petition dismissed. (Paras 2, 5 to 10)

       Result: Revision petition dismissed.

       

Advocates:
Counsel for the Parties:
For the Petitioner:Mr. Sunil Jha, Advocate with Ms. Pamela Saha, Advocate.

ORDER

J.M. Malik, Presiding Member—The complainants, namely, Dr. Sunil Kumar Majhi, Dilip Kumar Mukherjee, Shabbir Alam Khan purchased flats at Deepkiran Apartment against payment of entire consideration amount from the opposite parties, namely, Hanshmukh Patel, Kishore Patel and Keshab Lal Patel. They have got the following grievances against the opposite parties.

“(a) The Community hall as proposed in the agreement as well as sanctioned plan has been completed into flats without their consent.

(b) No underground reservoir has been provided in the apartment though it has been mentioned in the agreement.

(c) Two residential flats were let out to Barasad Co-operative Bank on length for commercial use and no maintenance charge has been paid by the bank or the shop owner in the said building.

(d) Flats are mortgaged with the said co-operative Bank.

(e) Ops have blocked the main entrance to lift compelling the Complainants to use the lift over the safety tank which is very risky and dangerous.

(f) The buildings are not ensured as per building rules.

(g) The promoter has not yet handed over the documents of title, relating to the property on which building stood. The promoter by constructing office and toilet on the car parking space by violating the Municipal Building Rules.”

2. The complainants filed a complaint before the District Forum. The District Forum allowed the complaint with costs in the sum of Rs.15,000/- payable by the opposite parties to the complainants and directed the opposite parties to provide community hall and the underground reservoir as per schedule ‘C” of the deed of conveyance. The opposite parties were further directed to demolish the wall causing hindrance in the main entrance leading to the lift and to complete the aforesaid work within six months from the date of judgment delivered by the District Forum. It was further ordered that in case of non-compliance of any portion of the order by the opposite parties, the complainants would be at liberty to put the decree as per provisions of law.

3. Aggrieved by the order of the District Forum, the opposite parties filed appeal before the State Commission. The State Commission dismissed the appeal.

4. We have heard the learned counsel for the petitioner-opposite parties. He contended that the present case is barred by time. The flats were transferred in favour of the complainants in the years 2002 and 2003. The complaint was filed by the complainants on 9.10.2007 which clearly goes to show that the instant complaint was barred by time.

5. We find no force in this argument. This is a continuous cause of action. This Commission in the case of Juliet V. Quadros v. M/s Mrs. Malthi Kumar1 was pleased to hold that ‘cause of action remains continuous till allotment of site or till refusal’. Same ratio will apply in this case as well.

6. Same view was taken in Lata Construction & Ors. v. Dr. Rameshchandra Ramniklal Shah and another.2 Consequently, it cannot be said that the case is barred by time.

7. The second contention raised by learned counsel for the petitioners was that the learned Additional District Judge, Barrackpore vide its order dated 1.4.2008 modified the order to the extent that parties to the suit shall maintain status quo in respect of community hall (in ‘C’ schedule) till the disposal of the injunction petition by the court below.

8. The pleadings filed by the petitioner go to show that the application for injunction was filed before the Hon’ble High Court and ad-interim order of status quo was passed for a period of six weeks by Hon’ble High Court of Kolkata in civil order No. 2836 of 2008 filed by M/s Rathtala Deepkiran Residents’ Welfare Association, represented by its Secretary, Dilip Kumar Mukhopadhyay v. Shri Keshablal B. Patel and Ors. It further reveals that on 24.2.2009, the status quo granted on 22.09.2008 was not extended by his Lordship Hon’ble Mr. Justice Sadhan Kumar Gupta. These facts do not establish a clear picture. It is not underst