NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION, NEW DELHI
K.S. Chaudhari, Presiding Member and B.C. Gupta, Member
Mr. Swapan Bera —Petitioner
versus
Mr. Shyamal Sengupta & Anr. —Respondents
Revision Petition No.4114 of 2013
(From the order dated 30.04.2008 in S.C. Case No. 165/A/2007 of the West Bengal State Consumer Disputes Redressal Commission, Kolkata)
Decided on 20.2.2014
Important Points
Availment of services of builder for a house construction falls within purview of C.P. Act.
Subject
Consumer Law - Definition of Consumer
Act Referred
Headnote
For the Petitioner:Mr. Prabir Basu and Mr. Sanjoy Kumar Ghosh, Advocates.
For the Respondents: Ex-parte.
K.S. Chaudhari, Presiding Member—This revision petition has been filed by the petitioner against the order dated 30.4.2008 passed by the West Bengal State Consumer Disputes Redressal Commission, Kolkata – 700 027 (in short, ‘the State Commission’) in S.C. Case No. 165/A/2007 – Swapan Bera Vs. Shyamal Sengupta & Anr. by which, while dismissing appeal, order of District Forum dismissing complaint was upheld.
2. Brief facts of the case are that complainant/petitioner’s father entered into a joint-venture agreement dated 22.7.2002 with OP/respondents for construction of a multi-storeyed building on the said piece of land purchased by complainant’s father. OP agreed to handover 5 flats in the new building to be constructed by OP on complainant’s father’s land. Father of the complainant before his death gifted two flats out of the said five flats to the complainant. Complainant’s father died on 25.2.2006. Complainant alleged in the complaint that floor of the two flats became discoloured and due to leakage of pipeline and fittings of bath-room walls were damaged. Cracks developed in the ceilings. It was further alleged that certain works were also unfinished as per details given in the complaint. Alleging deficiency on the part of OP, complainant filed complaint and claimed Rs.3,00,000/- for repairs of two flats. OP contested complaint and submitted that father of the complainant was fully satisfied with the standard of construction and material used for construction and objections have been raised after 1½ years from the delivery of possession only for harassing and prayed for dismissal of complaint. Learned District Forum after hearing both the parties dismissed complaint. Appeal filed by the complainant was also dismissed on the ground that complainant does not fall within the purview of consumer under the C.P. Act.
3. None appeared for the respondents even after service and they were proceeded ex-parte.
4. Learned Counsel for the petitioner submitted that complainant falls within the purview of consumer as held by Apex Court, but learned State Commission has committed error in dismissing appeal on this ground; hence, revision petition be allowed and matter may be remanded back.
5. Learned State Commission while dismissing appeal observed as under in paragraph 6:
“6. xxx
It is henceforth evident that the project of construction of building was undertaken for commercial purpose. The present complaint and for that matter the Appeal is not a consumer dispute. In this context we are inclined to refer to the decision in 2006 CTJ 42 (CP) (NCDRC) wherein the Hon’ble National Commission had clearly decided that a transaction relating to the property by the owner of a land with another person for the purpose of commercial exploit shall not be the subject matter of dispute before the Consumer Forum. The said decision was again followed in 2008 CTJ 264 (CP) (NCDRC). The Hon’ble National Commission observed here that “….before getting into the purview of Section 3 of the Consumer Protection Act, 1986 one has to qualify himself to fall within the definition of the ‘Consumer’ as defined in the Consumer Protection Act, 1986. When we go through the agreement, it is clearly stated in para 1 of the Agreement that it was the respondent who was to build four floors on the stilt ‘at his own cost’. In view of this, we are of the view that in no way, the Appellant/Complainant could be said to have hired the services of the respondent developer/builder, as per definition of ‘Consumer’ laid down under Section 2(1)(d) of the CPA. The Appellant had not hired the services of the Respondent for construction of a building in the ordinary sense. In fact the arrangement was sharing the number of flats constructed on the said land”.
whereas Hon’ble Apex Court in Faqir Chand Gulati Vs. Uppal Agencies Pvt. Ltd. & Anr.1 held in paragraph 19 as under:
“19. What then is the nature of the agreement between the appellant and the first respondent? Appellant is the