NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION, NEW DELHI
J.M. Malik, Presiding Member
Lucknow Development Authority, Through Its Secretary —Petitioner
versus
Anoop Kumar —Respondent
Revision Petition No. 273 of 2015
(Against the Order dated 25/04/2013 in Appeal No. 2771/1998 of the State Commission Uttar Pradesh)
Decided on 12.2.2015

Advocates:
Counsel for the Parties:
For the Petitioner:Mr. Parvaz Dabas, Advocate

IMPORTANT POINT
A time-barred revision petition cannot be entertained.

Headnote:Consumer Protection Act, 1986—Sections 15, 17, 19 and 21—Revision—Delay—Condonation—Delay of 554 days in filing of Revision Petition—There is huge delay in filing present revision petition—Name of panel lawyer was not disclosed—His affidavit also did not see light of day—It is duty of petitioner to go to office of Advocate and get next date of hearing—It shows negligence, inaction and passivity on part of petitioner—State Commission dismissed appeal filed by OP-Since this is an admitted fact that fittings were not complete, no material irregularity or impropriety in order passed by Fora below—Revision petition dismissed as barred by limitation as well as on merits. (Paras 3, 7 to 10)

       Result: Revision Petition dismissed.

       

ORDER

J.M. Malik, Presiding Member—Learned counsel for the petitioner present.

2. There is delay of 554 days in filing this revision petition. The petitioner has moved an application for condonation of delay in filing the revision petition. The delay has been explained in paras 4, 5 and 6 of the application which are reproduced as under:

“4. That the panel lawyer of the petitioner authority did not inform the petitioner authority about the dismissal of the case. Thereafter the respondent moved a letter on 09.01.2014 to the petitioner authority for execution of registry of the suit properly only then the petitioner came to know about the dismissal of the appeal before the State Commission.

5. That thereafter the legal advise was sought for filing the revision petition before the Hon’ble N.C.D.R.C. The counsel at New Delhi advised to file revision.

6. That thereafter in the end of month of January, 2014, the case file was sent to counsel at Delhi for filing the revision petition.”

3. There is huge delay in filing the present revision petition. The name of the panel lawyer was not disclosed. His affidavit also did not see the light of the day. It is the duty of the petitioner to go to the office of the advocate and get the next date of hearing. It shows negligence, inaction and passivity on the part of the petitioner.

4. The Apex Court in a recent case i.e. Sanjay Sidgonda Patil vs. Branch Manager, National Insu. Co. Ltd. & Anr., Special Leave to Appeal (Civil) No. 37183 of 2013 decided on 17.12.2013, confirmed the order of the National Commission and refused to condone the delay of 13 days. Likewise, delay of 78 days was not condoned by the Apex Court in the case of M/s Ambadi Enterprise Ltd. vs. Smt. Rajalakshmi Subramanian in SLP No. 19896 of 2013 decided on 12.7.2013. Again delay of 77 days was not condoned in case of Chief Off. Nagpur Hous. & Area Dev. Boa & Anr. vs. Gopinath Kawadu Bhagat, SLP No. 33792 of 2013 decided on 19.11.2013.

5. This view neatly dovetails with the Supreme Court authorities reported in Anshul Aggarwal v. New Okhla Industrial Development Authority, IV (2011) CPJ 63 (SC) R.B. Ramlingam v. R.B. Bhavaneshwari; 2013(4) CPR 785 (SC): I (2009) CLT 188 (SC): I (2009) SLT 701: 2009 (2) Scale 108 Ram Lal and Others v. Rewa Coalfields Ltd., AIR 1962 Supreme Court 361 and Bikram Dass Vs. Financial Commissioner and others, AIR 1977 Supreme Court 1221 and Office of the Chief Post Master General & Ors. Vs. Living Media India Ltd. & Anr. 2013(3) CPR 622 (SC): 2012 STPL(Web) 132 (SC).

6. This case is barred by limitation.

7. Let us turn to the merits of this case. Shri Anoop Kumar, the complainant applied for allotment of a house with Lucknow Development Authority. The opposite party allotted a house in favour of the complainant on 12.8.1992. The complainant has paid the entire costs of the house in the sum of Rs.3,24,000/-. The possession letter was issued on 19.11.1995. The complainant alleged that there were many defects and the house was not fit for habitation.

8. At this stage, learned counsel for the petitioner submits that there were no defects at all and this is a false allegation. However, he admits that the electric fittings and other fittings were not yet fixed. It is thus clear that the house was not fit for use. Nobody could have lived there in absence of those fittings. However, the complainant took over the possession on 29.5.1998. The complainant filed a complaint with the District Forum. The District Forum allowed the complaint allowing 18% p.a. interest on the total amount deposited by the complainant, for the period from 1.2.1996 to 28.5.1998 and Rs.2,000/- towards the costs of the case.

9. The State Commission dismissed the appeal filed by the OP. Since this is an admitted fact that the fittings were not complete, I see no material irregularity or improprietory in the order passed by the fora below.

10. The revision petition is without merits. Therefore, the same is dismissed as barred by limitation as



Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

SupremeToday

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top