SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION, NEW DELHI
J.M. Malik, Presiding Member, Dr. S.M. Kantikar, Member
Dr. K.D. Suchak & Mrs Geeta K.Suchak —Appellant
versus
HI - Life Developers Pvt. Ltd. & Ors. —Respondents
First Appeal No. 91 of 2011
(Against the Order dated 16/11/2010 in Complaint No. 238/2001 of the State Commission Maharashtra)
Decided on 22.4.2015

Counsel for the Parties:
For the Appellant:Mr. Vivek Sharma, Advocate with Mr. Yatin Gujrati, Ms. Mamta Gautam, Advocates with Appellant No.1
For the Respondent Nos.1 & 3:Mr. Nagaraj V. Hoskeri, Advocate
For the Respondent Nos. 2, 4 & 5: Nemo
For the Respondent No.6:Mr. Shankar Narayanan, Advocate

IMPORTANT POINT
Justice delayed is not only justice denied, it is also justice circumvented, justice mocked and system of justice undermined.

Headnote:Consumer Protection Act, 1986—Sections 17, 19 and 21—Real estate—Scheme for construction of farm house—Denial of possession—Had OPs been bonafide, they would have refunded amount the moment complaint was filed or written versions were submitted before State Commission—However, OPs themselves insisted that they were ready to give farm house within a period of 9 months when they were owners of no land—Even after lapse of 9 months, they did not hand over plot to complainants—This case is pending for last 25 years when cheques were given—Justice delayed is not only justice denied, it is also justice circumvented, justice mocked and system of justice undermined—Consumers are exasperated by senseless delay—Rs.1,19,43,750/- directed be paid to complainants after deducting amount paid in Execution Proceedings. (Paras 15 to 18)

       Result: Appeal disposed of.

       

ORDER

J. M. Malik, Presiding Member—There was a delay of 26 days in filing this appeal, which was condoned vide order passed by our predecessor Bench on 05.05.2011. The facts germane to the present case are these. Hi-Life Developers Pvt. Ltd. –OP-1, Mr. Dhiraj P. Shah-OP-2, Mr. Chaitanya N Parekh- OP-3, Mr. Chirag V Shah-OP-4, Mr. Vinayak C. Shah –OP-5, issued a brochure in the year 2001 with the Scheme of construction of farm house measuring half Acre agriculture land and construction of 1250 sq.ft. in Village Ovale, District Thane. Complainants Dr.K.D. Suchak and Mrs. Geeta K. Suchak booked one half Acre farm house by paying Rs.4,50,000/- by cheques and Rs.50,000/- in cash. OP-3 issued an allotment letter dated 23.08.1991. The total consideration was agreed at Rs.6,00,000/- for the said farm house. The said project was known as “COSMOS”.

2. Thereafter, several letters of request were sent to the OPs to hand over the possession of the farm house but these efforts made by the complainants did not ring the bell. Ultimately, the complaint was filed before the State Commission on 01.12.2001, wherein the following prayers were made:-

“(a) that the opposite parties be jointly and severally directed to refund the amount of Rs.5,00,000/- (Rupees Five Lakhs only) paid by the complainants;

(b) that on the aforesaid amount of Rs.5 lakhs, the opposite parties be jointly and severally directed to pay interest at the rate of 18 per cent per annum from the dates of payment till the date of refund/realization;

(c) that the opposite parties be jointly and severally directed to pay a compensation of Rs.1 lakhs or such other amount as this Hon’ble Commission may deem fit and proper, for the harassment caused to the complainants;

(d) that the opposite parties be jointly and severally directed to pay costs of this litigation; and

(e) for such further and other reliefs and/or directions as this Hon’ble Commission may deem fit and proper.

Dated at Mumbai, this 15th day of June 2001.”

3. It is note-worthy that in their written version filed by OPs- 1 & 3, they promised that they would hand over the possession within 9 months. It is also note-worthy that the OPs did not agree to refund the amount instantaneously but insisted that farm house would be given within a period of 9 months. They explained that OPs are ready and willing to provide the constructed plot to the complainant as per terms of the allotment letter, hence the question of refunding money together with interest and compensation, as alleged, demanded by the complainant in the instant complaint, did not arise.

4. The complainants moved another application dated 13.06.2003 wherein they stated that even after the lapse of 9 months i.e., till July 1992, the respondents had failed to hand over the possession and the complainant signified their interest in possession of the said farm house. The OPs further averred that they had submitted a plan to the Municipal Corporation but the same was rejected by the Corporation on technical grounds. It was contended that the complainants were aware of that. The OPs denied having received Rs.50,000/- in cash.

5. Thereafter, the amendment application was moved on 11.10.2005 seeking relief of the possession as well. It may be mentioned here that vide order dated 24.02.2006, the State Commission was pleased to note that the complainants had filed an application for amendment of complaint with the relief in regard to delivery of possession of plot. Before the amendment could be allowed by the State Commission, the land in question was sold in favour of Mr. Suraj P. Parmar, who was subsequently, arrayed as OP-6 in this case.

6. The State Commission heard the parties and passed the following order on 16.01.2010:-

“1. Complaint is partly allowed.

2. O.P.Nos.1 to 3, jointly and severally, do pay Rs.4,50,000/- (Rupees Four Lakhs Fifty Thousand only) to the complainant along with interest @ 18% p.a. from the date of their respective payments till their realization.

3.
























Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

SupremeToday

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top