NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION, NEW DELHI
D.K. Jain, President, Mrs. M. Shreesha, Member
Executive Engineer Electricity Distribution Division & Ors. —Petitioners
versus
Sindhi Sahkari Avas Samiti Ltd. —Respondent
Revision Petition No.1910 of 2015
(Against the Order dated 10/02/2015 in Appeal No. 1159/2003 of the State Commission Uttar Pradesh)
Decided on 14.9.2016

Advocates:
Counsel for the Parties:
For the Petitioners:Mr.Anurag Kishore, Advocate with Mr.Nandlal, Executive Engineer and Mr.Prem Singh, Law Officer
For the Respondent:Mr.Pawan Kr. Ray, Advocate

IMPORTANT POINT
No amount can be deposited for purpose of transformer.

Headnote:Consumer Protection Act, 1986—Sections 15, 17, 19 and 21—Electricity—Demand against additional load—State Commission found that no amount can be deposited for purpose of transformer and directed to refund amount deposited—Since Petitioner has failed to adduce any evidence in support of its demand, impugned order not suffering from jurisdictional error warranting interference in revisional jurisdiction—However, having regard to peculiar circumstances of case, award of interest in favour of Samiti on said amount is not justified—Impugned order modified. (Paras 5 to 10)

       Result: Revision Petition Partly allowed.

       

ORDER

D.K. Jain, President—Since 13.9.2016 had been declared as holiday on account of Eid in lieu of 12.9.2016, this case is being taken up today.

IA/4963/2015

2. For the reasons stated in the application, the delay in filing the Revision Petition is condoned. The application stands disposed of accordingly.

Revision Petition

3. Challenge in this Revision Petition, by the U.P. Power Corporation Ltd., Bareilly, is to the order dated 10.2.2015, passed by the State Consumer Disputes Redressal Commission, U.P. at Lucknow (for short “the State Commission”) in Appeal No.1159/2003. By the said order, the State Commission has affirmed the order dated 18.5.2002 passed by the District Consumer Disputes Redressal Forum I, Bareilly (for short “the District Forum”) in Complaint No.373/91. By the said order, the District Forum had directed the Petitioner herein to refund to the Respondent, namely, Sindhi Sahkari Awas Samiti Ltd. (for short “the Samiti”), an amount of Rs.92,080/- along with interest at the rate of 9% per annum from 9.1.1990 till the date of actual refund.

4. The occasion to file the Complaint by the said Samiti arose because of the recovery of the afore-stated additional amount by the Petitioner in terms of its letter dated 18.12.1989, as a pre-condition for energization of a 63 KVA capacity transformer. The grievance of the Samiti was that since they had already deposited the entire amount towards the cost of setting up of a transformer with capacity of 63 KVA, there was no basis for raising the said demand. The stand of the Petitioner, on the contrary, was that the said demand had been raised on account of additional load demanded by the Samiti over and in excess of 63 KVA, in terms of the Office Memorandum dated 25.11.1987. The said Memorandum stipulated that in case the load of the Samiti increases beyond 63 KVA, the cost for increase in the capacity shall be borne by the Samiti.

5. Taking into consideration the documents placed on record by both the parties, in support of the rival stands, in particular the letter dated 9.1.1990, addressed by the Samiti to the Executive Engineer, Electricity Distribution Division, Bareilly, wherein the Samiti had requested the Petitioner to furnish information about the provisions of the U.P. Electricity Act, 1910, under which they were being made liable to pay the said amount, the District Forum arrived at the conclusion that the demand of the said amount was illegal. While affirming the said finding, the State Commission has held that the Samiti was not liable to pay the said amount, observing thus :

“As far as the Appeal is concerned, the complainant got deposited Rs.92,080 under protest for the transformer with the electricity department. The electricity department has not been able to give any satisfactory reasons for getting deposited the same amount with it before the District Forum. At the stage of Appeal, copy of the order dated 14.9.1992 passed in Appeal No.403 of 1991 and Appeal No.417 of 1991 by this State Commission has been filed, which his between these parties and the said Appeals are also related to the issue of refund of the money deposited for transformers. The State Commission found that no amount can be deposited for the purpose of transformer and therefore directed to refund the amount deposited.”

Hence, the present Revision Petition.

6. On 20.7.2016, when the case had come up for consideration, we had directed the Petitioner to produce the original record wherein the Samiti’s request for release of electricity connection was dealt with, containing the estimates prepared by the Chief Zonal Engineer, determining the cost of the transformers, which was sought to be recovered from the Samiti.

7. In deference to the said order, Mr.Nandlal, Executive Engineer of the Petitioner Distribution Division, is present along with some documents. However, on repeated questioning, he has not been able to show any document, indicating the basis on which the said demand was raised for the all