NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION, NEW DELHI
V.K. Jain, Presiding Member
Jivitesh Nayal and Anr. —Complainants
versus
M/s. Emaar Mgf Land
Limited and Anr. —Opp. Parties
Consumer Case Nos.34, 40, 664, 665, 668, 671, 673, 741, 1194 and 1471 of 2015 and Consumer Case No.42 of 2016
Decided on 2.11.2017

Important Points

IMPORTANT POINT
National Commission does possess requisite pecuniary jurisdiction to entertain complaints where agreed sale consideration and compensation in form of interest comes to more than Rupees one crore.

Subject

Consumer Dispute - Real Estate

Act Referred

CONSUMER PROTECTION ACT : S.21, S.14(1)(d)

Headnote

(A) Consumer Protection Act, 1986—Section 21—Real estate—Allotment of residential flats in a project—Denial of possession despite payment—National Commission does possess requisite pecuniary jurisdiction to entertain complaints since agreed sale consideration and compensation in form of interest comes to more than Rupees one crore—A highly exaggerated, fanciful or inflated claim cannot be considered to be a genuine claim and cannot be determinative of pecuniary jurisdiction—However, considering that not only National Commission, but Supreme Court has awarded compensation in form of 18% interest, compensation in form of interest calculated @ 18% per annum would not be taken as a highly inflated or exaggerated claim so as to warrant outright rejection of complaint even though Court / Forum may award a lesser compensation. (Paras 5 and 6)

       (B) Consumer Protection Act, 1986—Section 14(1)(d)—Real estate—In terms of Section 14 (1)(d) of Act National Commission is also required to pass an order directing opposite party to pay compensation to complainants for any loss or injury suffered by them due to negligence of opposite party—If builder whose services are engaged by a buyer for construction of a residential house for him fails to complete construction and deliver its possession on or before date committed by him for the purpose, such an act on part of builder would be an act of negligence causing loss or injury to flat buyer. (Para 8)

       Result: Complaints allowed.

       

Counsel for the Parties:
For the Complainants:Mr. Sushil Kaushik and Ms. Himanshi Singh, Advocates
For the Opp. Party in CC/34/2015 & CC/40/2015: For the Opp. Party:Mr. Aditya Narain, Mr. Kshitij Parashar and Mr. Arjun Jain, Advocates
For the Opp. Party in CC/664/2015, CC/665/2015, CC/668/2015, CC/673/2015 and CC/671/2015:Mr. Aditya Narain and Mr. Shashank Sharma, Advocates
For the Opp. Party in CC/741/2015:Mr. A.S. Chadhiok, Sr. Advocate Mr. Aditya Narain, Mr. Arjun Jain, Ms. Anushree Narain, Ms. Sweta Kakkad, Mr. Mishra Raj Shekhar and Mr. Gaurav Sharma, Advocates
For the Opp. Party in CC/1194/2015, CC/1471/2015 and CC/42/2016:Mr. Aditya Narain, Mr. Arjun Jain and Ms. Anushree Narain, Advocates

ORDER

V.K. Jain, Presiding Member—The complainants in these matters are allottees of residential flats in a project namely “Emerald Floors” at Emerald Hills, which the opposite party was to construct on the land comprised in Village Maidawas, Sector 65 of Gurgaon. The following are the particulars of the bookings made by the complainants, the flats allotted to them, the date on which Builder Buyer Agreements were executed, the sale consideration agreed between the parties and the payment made so far to the opposite party:

Sl. No.

CC No.

Apartment Details

Booking date

Date of execution of BBA

Agreed sale consideration

Amt. paid

1.

34/2015

EHF-350-C-SF-002

17.6.2009

12.10.2009

6108600

5778600

2.

40/2015

EHF-350-I-FF-134

6.9.2009

28.12.2009

7065000

5771122

3.

664/2015

EFP-II-54-0001

17.5.2010

16.09.2010

11718000

9280006

4.

665/2015

EFP-12A-0202

29.9.2009

02.9.2010

7080100

6204003

 

 

 

Resale

 

 

 

5.

668/2015

EFP-II-54-0101

17.5.2010

16.9.2010

10039250

7381846

6.

673/2015

EFP-10-0301

25.9.2009

28.12.2009

6251163

5919596

7.

741/2015

EHF-350-I-FF-114

09.7.2009

28.12.2009

7335000

7242786

 

 

 

Resale

 

 

 

8.

1194/2015

EFP-06-0002

10.11.2009

02.1.2010

8255642

7499725

9.

1471/2015

EFP-24-0501

24.01.2010

04.9.2010

9417900

8395955

 

 

 

Resale

 

 

 

10.

42/2016

EFP-27-0402

20.01.2010

30.4.2010

8477248

8209461

11.

671/2015

EFP-09-0001

25.9.2009

28.12.2009

7946350

7158578

2. As per Clause 13(a) of the BBA, the opposite party proposed to hand over possession within 27 months from the execution of the said agreement though it was entitled to a grace period of three months for the limited purpose of applying and obtaining the occupancy certificate. The grievance of the complainants is that the possession of the flat / floor has not been offered to them despite they having paid major part of the sale consideration to the opposite party. However, in two cases, CC/40/2015 and CC/741/2015, the possession has been delivered during pendency of the complaints. The complainants have therefore approached this Commission by way of these separate complaints, seeking possession of their respective flats complete in all respects or in the alternative, ready-to-move-in, independent flats of identical size in a similar locality. The second alternative prayer made by the complainants is for payment of a sum calculated at Rs.9,500/- per sq. ft. of the area of their respective flats, which according to them is the current market price of such residential flats / floor. They are also seeking compensation under several heads including rental value, interest @ 24% per annum and compensation for the physical and mental torture and agony suffered by them.

3. The complaint has been resisted by the opposite party which has taken a preliminary objection that since the agreed consideration was less than Rupees One crore, this Commission lacks pecuniary jurisdiction to entertain the complaint. On merits, the allotment made to the complainant as well as the execution of the Builder Buyer Agreements with them, has been admitted. The payments made by the complainants have also not been disputed. It is claimed that in view of Clause 15 of the Builder Buyer Agreement, in the event of delay, the complainants are entitled only to compensation calculated at Rs.10/- per sq. ft. per month. The construction, according to the opposite party, is in full swing. It is alleged that all possible efforts are being made to complete the construction and deliver possession to the complainants.

4. In terms of Section 21 of the Consumer Protection Act, this Commission possesses the requisite pecuniary jurisdiction to en