V.K.JAIN
Praveen @ Parveen Kumar Jain – Appellant
Versus
Earth Infrastructures Ltd. – Respondent
V.K. Jain, Presiding Member—The complainant booked a residential flat with the opposite party in a project namely ‘Earth Copia’, which the opposite party was to develop in Sector-112 of Gurgaon. The opposite party allotted residential Unit No.404 in Tower G having super area of 1835 sq. ft. to him for a consideration of Rs.81,78,580/-. The complainants having opted for a construction linked payment plan, the aforesaid amount was payable in the following manner:—
1. At the time of booking: 10% of the BSP
(ii) Within 45 days from booking: 15% of the BSP
ii. Within 120 days from booking: 10% of the BSP plus 50% of the EDC and IDC
iv. At start of Excavation Work : 10% of the BSP
v. At start of Basement Slab : 10% of the BSP plus 50% of the EDC and IDC
vi. At start of 2nd floor work : 5% of the BSP
vii. At start of 04th floor work : 5% of the BSP
viii. At start of 07th floor work : 5% of the BSP plus 50% of 3rd and 4th floor PLC plus 50% of Park Facing PLC plus 50% of road / corner facing PLC
ix. At start of 10th floor work : 5% of the BSP
x. At start 12th floor work: 5% of BSP
xi. At the start of 14th Floor work : 5% of the BSP
xii. At start of Internal Plaster :
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.