Important Points
If a builder fails to deliver possession of flat/plot booked with him, within time period committed for this purpose and is unable to justify the said delay, this would constitute defect or deficiency in services rendered by him to buyer.
Subject
Real Estate Law - Builder-Buyer Disputes
Act Referred
Headnote
Result: Complaints allowed.
For the Complainants:Mr. A.R. Takkar, Mr. Amarjeet Kumar, Mr. Ajay Bansal and Ms. Shriya Takkar, Advocates
For the Opp. Party:Mr. P. Vinay Kumar and Ms. Manisha Gupta, Advocates, Ms. Ruchi Kumar, Legal Manager (IREO)
V.K. Jain, Presiding Member—The complainant in CC/189/2017, namely, Pradeep Kumar Gupta booked a residential flat with the OP in a project namely ‘The Corridors’, which the OP was to develop in Sector-67A of Gurgaon. Apartment No. A1-06-601 in Tower A1 of the aforesaid project was allotted to him for a consideration of Rs.19920649/- and he executed a Buyers Agreement with the OP on 21.10.2014. The grievance of the complainant is that the possession of the flat has not been offered to him despite he having already paid a sum of Rs.6122733/- to the OP.
The complainants in CC/217/2017 also booked a residential flat with the opposite party in the said project and flat No. A2-11-1102 in Tower A2 was allotted to them for a consideration of Rs.20186365/- and they executed a Buyers Agreement with the OP on 2.6.2014. The grievance of the complainants is that the possession of the flat has not been offered to them despite they having already paid a sum of Rs.6205441/- to the OP.
The complainants in CC/218/2017 also booked a residential flat with the opposite party in the said project and flat No. A1-08-802 in Tower A1 was allotted to them for a consideration of Rs.19920649/- and they executed a Buyers Agreement with the OP on 3.9.2014. The complainants claim to have already made the payment of Rs.6122738/-to the opposite party but the possession of the flat has not been offered to them.
The complainant in CC/219/2017, namely, Shailaditya Gangopadhyay also booked a residential flat with the opposite party in the above-said project and flat No. A1-04-401 in Tower A1 was allotted to him for a consideration of Rs.20271389.78/- and he executed a Buyers Agreement with the OP on 10.7.2014. The grievance of the complainant is that the possession of the flat has not been offered to him despite he having already paid a sum of Rs.6209828/- to the OP.
The complainants in CC/520/2017, also booked a residential flat with the opposite party in the said project and flat No. A2-03-302 in Tower A2 was allotted to them for a consideration of Rs.20186365/- and they executed a Buyers Agreement with the OP on 28.5.2014. Their grievance is that the possession of the flat has not been offered to them despite they having already paid a sum of Rs.6205440/- to the OP.
The complainants in CC/521/2017 also booked a residential flat with the opposite party in the above-said project and flat No. A1-12-1201 in Tower A1 was allotted to the complainants for a consideration of Rs.20292883/- and they executed a Buyers Agreement with the OP on 25.3.2014. They also have a similar grievance that the possession of the flat has not been offered to them despite they having already paid a sum of Rs.6238594/- to the OP.
The complainant in CC/522/2017, namely, Raman Narula also booked a residential flat with the opposite party in the above-said project and flat No. A2-09-903 in Tower A2 was allotted to him for a consideration of Rs.18941277/- and he executed a Buyers Agreement with the OP on 28.4.2014. Their grievance also is that the possession of the flat has not been offered to him despite he having already paid a sum of Rs.5855695/- to the OP.
The complainant in CC/523/2017, namely, Priyanka Gupta also booked a residential flat with the opposite party in the above-said project and flat No. A2-05-501 in Tower A2 was allotted to her for a consideration of Rs.18406981/- and she executed a Buyers Agreement with the OP on 27.8.2014. Her grievance is that the possession of the flat has not been offered to her despite she having already paid a sum of Rs.5688308/- to the OP.
The complainant in CC/524/2017, namely, Raj Sethi also booked a residential flat with the opposite party in the above-said project and flat No. A2-03-303 in Tower A2 was allotted to him for a consideration of Rs.18941277/- and he executed a Buyers Agreement with the OP on 25.3.2014. The grievance of the complainant is that the possession of the flat has not been offered to him despite he having already paid a