NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION, NEW DELHI
V.K. Jain, Presiding Member
Vishal Dua and Anr. —Complainants
versus
M/s. Ireo Grace Realtech Pvt. Ltd. —Opp. Party
Consumer Case No.2498 of 2017
Decided on 12.4.2019
Important Points
1. Though the parties are bound by the terms of the contract, only one sided terms are not binding on the complainant.
2. If a builder fails to deliver possession of the flat/plot booked with him, within thetime period committed for this purpose and is unable to justify the said delay, this, in myopinion, would constitute a defect or deficiency.
Subject
Real Estate Law - Builder-Buyer Disputes
Act Referred
Headnote
Held, the default in payment of the 9th installment would not dis-entitle the complainants from seeking refund of the amount paid to the builder when there has already been a delay of more than two years and three months in completion of the project and it is not known when the project would be completed and possession would be offered to the allottees. Refund along with interst 10% p.a. and cost of Rs. 25,000/- ordered.
For the Complainant:Mr. Deepak Kr. Khushalani, Advocate
For the Opp. Party:Mr. P. Vinay Kumar and Mr. Kamlesh Kumar, Advocates Ms. Ruchi Kumar, Legal Manager
V.K. Jain, Presiding Member—The complainants booked a residential flat with the OP in a project namely ‘The Corridors’ which the OP was to develop in Sector-67A of Gurgaon. Apartment No.CD-B7-07-704 of the said project was allotted to them. The parties then executed an Apartment Buyers Agreement on 14.04.2014 incorporating their respective obligations. The sale price for the flat was agreed at Rs.1,38,83,798.04p which was payable in installments.
2. The terms and conditions of the agreement, to the extent they are relied upon by the parties, read as under:—
13.3 Subject to Force Majeure, as defined herein and further subject to the allottee having complied with all its obligations under the terms and conditions of this Agreement and not having defaulted under any provision(s) of this Agreement including but not limited to the timely payment of all dues and charges including the total Sale Consideration, registration charges, stamp duty and other charges and also subject to the Allottee having complied with all formalities or documentation as prescribed by the Company, the Company proposes to offer the possession of the said Apartment to the Allottee within a period of 42 (Forty Two) months from the date of approval of the Building Plans and/or fulfillment of the preconditions imposed thereunder (“Commitment period”). The Allottee further agrees and understands that the Company shall additionally be entitled to a period of 180 days (“Grace period”), after the expiry of the said Commitment Period to allow for unforeseen delays beyond the reasonable control of the Company.
13.4 Subject to clause 13.3, if the Company fails to offer possession of the said Apartment to the Allottee by the end of the Grace Period, it shall be liable to pay to the Allottee compensation calculated at the rate of Rs.7.50/- (Rupees Seven & Half only) per sq. ft. of the Super Area (“Delay Compensation”) for every month of delay until the actual date fixed by the Company for offering possession of the said Apartment to the Allottee. The Allottee shall be entitled to payment/adjustment against such ‘Delay Compensation’ only at the time of ‘Notice of Possession’ or at the time of payment of the final installment, whichever is earlier.
13.5 Subject to Clause 13.3, in the event of delay by the Company in offering the possession of the said Apartment beyond a period of 12 months from the end of the Grace Period (such 12 month period hereinafter referred to as the ‘Extended Delay Period”), then the Allottee shall become entitled to opt for termination of the Allotment/Agreement and refund of the actual paid up installment(s) paid by it against the said Apartment after adjusting the interest on delayed payments alongwith Delay Compensation for 12 months. Such refund shall be made by the Company within 90 days of receipt of intimation to this effect from the Allottee, without any interest thereon. For the removal of doubt, it is clarified that the Delay Compensation payable to the Allottee who is validly opting for termination, shall be limited to and calculated for the fixed period of 12 months only irrespective of the date on which the Allottee actually exercised the option for termination. This option may be exercised by the Allottee only up till dispatch of the Notice of Possession by the Company to the Allottee whereupon the said option shall be deemed to have irrevocably lapsed. No other claim, whatsoever, monetary or otherwise shall lie against the Company and/or the Confirming Parties nor be raised otherwise or in any manner by the Allottee.
21.1 Notwithstanding anything contained in this Agreement, timely performance by the allottee of its obligations under this Agreement, including without limitation, its obligations to make timely payment of the Sale Consideration, maintenance charges and other deposits and amounts, including any inter