SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

HIMACHAL PRADESH STATE CONSUMER DISPUTES REDRESSAL COMMISSION
Arun Kumar Goel, President, Saroj Sharma and Chander Shekher Sharma, Members
HPSEB, KUMAR HOUSE, SHIMLA AND ORS. - Appellants
Versus
JAI RAM - Respondent
First Appeal No. 272 of 2009
Decided on : 23-02-2010

Advocates Appeared:
Mr. Shashi Bhushan Singh Chandel, Advocate, for the Appellant; Mr. Umesh Kumar, Advocate, for the Respondent

The District Forum had jurisdiction under the Consumer Protection Act, 1986, and the appellants will be entitled to claim the benefit of Section 14 of the Limitation Act, 1963 if they proceed against the responsible person for theft of electricity.

Headnote:

Electricity Bill Dispute - Consumer Protection - Electricity Act, 2003, Section 14, Limitation Act, 1963 - The court dismissed the appeal and held the appellants liable for payment of costs to the respondent. The court clarified that the order passed will not debar the appellants from proceeding against the person responsible for theft of electricity as per Annexure C-4. The court also mentioned that the appellants will be entitled to claim the benefit of Section 14 of the Limitation Act, 1963 if they approach any Court/Forum for claiming the amount from the responsible person.

Fact of the Case:

The appellants appealed against the order of the District Forum, Chamba, which directed them to issue a revised electricity bill to the respondent and compensate the respondent for sundry charges. The appellants argued that the District Forum had no jurisdiction to entertain the complaint as the remedy, if any, was available under the Electricity Act, 2003.

Finding of the Court:

The court found that the appeal deserved to be dismissed with costs, as the appellants should have initiated action against the person responsible for theft of electricity instead of filing the appeal. The court also clarified that the order passed will not debar the appellants from proceeding against the responsible person as per Annexure C-4.

Issues: Jurisdiction of the District Forum under the Consumer Protection Act, 1986 in the face of the Electricity Act, 2003.

Ratio Decidendi: The court held that the District Forum had jurisdiction under the Consumer Protection Act, 1986, as established by the Hon'ble Supreme Court in the case of Karnataka Power Transmission Corpn. Ltd. and Anr. v. Ashok Iron Works Pvt. Ltd., AIR 2009 SC 1905. The court also emphasized that the appellants will be entitled to claim the benefit of Section 14 of the Limitation Act, 1963 if they proceed against the responsible person for theft of electricity.

Final Decision: The court dismissed the appeal, held the appellants liable for payment of costs to the respondent, and clarified that the order passed will not debar the appellants from proceeding against the responsible person for theft of electricity as per Annexure C-4.

ORDER

Arun Kumar Goel, President (Oral)- Appellants are aggrieved from the order dated 22.5.2009, passed by District Forum, Chamba in Consumer Complaint No. 23/2007. While allowing this complaint, it has been ordered that the appellants will issue revised electricity bill to the respondent after deleting the sundry charges as shown in the disputed bill No. AV 3960305, Annexure C-l within 30 days after the receipt of copy of the order. Appellants have also been directed to compensate the respondent in the sum of Rs. 5,000, together with litigation cost of Rs. 2,000, hence this appeal.

2. While challenging the impugned order, Mr. Chandel, learned Counsel for the appellant forcefully urged, that District Forum below had no jurisdiction to have entertained the complaint as according to him, remedy if any available to the respondent was before authorities constituted under the Electricity Act, 2003. Further according to him the District Forum below fell into error by ignoring this vital question, therefore, on this short ground alone, the impugned order was liable to be set aside and consequently the complaint dismissed.

3. On the other hand, learned Counsel for respondent submitted that the impugned order suffers from no infirmity which may call for interference in this appeal. As according to him there is not an iota of evidence on record to suggest that the impugned bill Annexure C-l could be justified against his client. By referring to Annexure C-4, learned Counsel for the respondent submitted without in any manner admitting or conceding that the liability, if any, is that of Dr. Ashok Chowan son of his client who was living separately and independently from the respondent and it was he who was caught red handed while committing theft of electricity even by the staff of HP State Electricity Board, at Village Samrali, PO Sarol, District Chamba. He drew our attention to this stand of the appellants in their reply to the complaint, that it was Mr. Ashok Chowan who was caught red handed by the Junior Engineer of the Board, i.e. Mr. Umesh Sharma, Section In-charge of Sarol.

4. After having heard learned Counsel for the parties and having examined the record of the District Forum below, we are of the view that this appeal deserves to be dismissed with cost. Reason being that in the face of Annexure C-4 passed by none else, but the Secretary of the HP State Electricity Board-appellant No. 1, we are constrained to observe as to why the respondent has been dragged to further litigation. For ready reference contents of Annexure C-4 are extracted hereinbelow:

"In connection with the above, it is stated that the matter has been examined on the basis of record supplied and in the facts and circumstances of the case it has been decided to withdraw the demand raised and amount placed in the account of the complainant. A statement to the effect may be arranged to be made before the Ld. Forum so that the complaint is rendered in-fructuous.

Thereafter a fresh notice may be caused to be served on Dr. Ashok Chauhan and his agent namely the contractor being the defaulters calling upon them to deposit the assessed amount. In case the demand raised is not satisfied by them, appropriate proceedings for the recovery of the said amount may be arranged to be launched and instituted in the Court of competent jurisdiction in consultation with the Counsel of the Board at Chamba under intimation to this office please.

Besides you are also requested to explain the reasons and circumstances which prevented you and the field officer from lodging/registering an FIR against the accused persons on account of theft of electricity under the provisions of Electricity Act, 2003.

The matter brooks no delay please."

5. After issuance of Annexure C-4 instead of filing the appeal by the appellants action should have been initiated against Dr. Ashok Chowan.

6. So far submission of Mr. Chandel that the Foras under Consumer Protection Act, 1986 have no jurisdiction in the face of Ele

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top