KERALA STATE CONSUMER DISPUTES REDRESSAL COMMISSION
Mr. K. Chandradas Nadar, Presiding Member and Mr. V.V. Jose, Member
KERALA STATE HOUSING BOARD AND ORS. - Appellants
Versus
P. RAMACHANDRAN - Respondent
First Appeal No. 326/2013
Decided on : 14-02-2014

Important Points

The entitlement of the Kerala State Housing Board to refix the final price taking into account the increased cost of development works and amenities undertaken.

Subject

Consumer Protection - Sale of Goods

Act Referred

CONSUMER PROTECTION ACT : S.15, S.2(1)(g)

Headnote

Consumer Protection Act - Sale of Flat - 9 - 208/11 - The court discussed the provisions of Clause No. 9 of the agreement dated 26.11.1992 and the entitlement of the Kerala State Housing Board to refix the final price taking into account the increased cost of development works and amenities undertaken. The court upheld the order of the lower Forum, dismissing the appeal and directing the appellant to execute the sale deed in favor of the complainant without collecting any additional amount within two months from the date of receipt of the order.

Fact of the Case:

The complainant sought to set aside the demand notice for additional amount and to direct the opposite party to execute the sale deed in respect of the flat without collecting any additional amount.

Finding of the Court:

The court found that the appellants did not produce evidence of any development works done and agreed that there were no land acquisition cases. The court upheld the order of the lower Forum, dismissing the appeal and directing the appellant to execute the sale deed in favor of the complainant without collecting any additional amount within two months from the date of receipt of the order.

Issues: Dispute over additional cost for the allotment of a flat and refusal to execute the sale deed in favor of the complainant.

Ratio Decidendi: The court considered the lack of evidence of any development works done by the appellants and upheld the order of the lower Forum.

Final Decision: The court dismissed the appeal and directed the appellant to execute the sale deed in favor of the complainant without collecting any additional amount within two months from the date of receipt of the order.

Advocates Appeared:
Mr. Meena C.R., Advocate, for the Appellant; Mr. C. Mohanan, Advocate, for the Respondent

JUDGMENT

Mr. V.V. Jose, Member -The opposite parties in CC No. 208/11 in the file of CDRF, Kasargod are the appellants herein, who are aggrieved by the direction of the Forum to execute the sale deed in respect of flat E F 8 (a) 206 in favour of the complainant without collecting any additional amount within two months from the date of receipt of the order and cancelling the demand notice of Rs. 1,89,718 as per Ext. A(6) with future interest and penal interest.

2. The case of the complainant in the above CC is as follows: Opposite parties are claiming an additional cost of Rs. 1,89,718 vide demand notice dated 3.3.2011, alleging to be the outstanding dues (i.e. difference in cost) for the allotment of flat. Subsequent to the claim the opposite party is refusing to execute the sale deed in favour of the complainant in respect of the flat allotted. The flat in dispute was allotted for a tentative price of Rs. 2,41,000 on 8.4.1992. He was asked to remit Rs. 96,400 as initial amount by way of final allotment letter which shows the cost of flat as Rs. 2,53,053 which is in excess of Rs. 12,053. Out of Rs. 98,000 remitted by the complainant Rs. 97,021 was adjusted to the value and balance was remitted in 162 monthly instalments of Rs. 2,410 with interest of 15.5%. Possession was handed over on 2.12.2012 consequent of an agreement, in which the interest was enhanced to 16.5%. On 6.11.1999 2nd opposite party demanded Rs. 3,74,477 as Rs. 1,21,424 was the additional cost. For which the complainant sent a reply stating that the opposite parties are not entitled to ask for additional amount. Later on 3.3.2011 the 4th opposite party sent another notice demanding Rs. 1,89,718 towards the outstanding dues. Hence this complaint for setting aside the demand and to direct the opposite party to execute the sale deed in respect of the Flat No. EF 8 (a) 206 with compensation and cost.

3. The opposite parties filed version contenting that they are entitled to refix the final price taking into account the cost of development works and amenities undertaken. There were no land acquisition cases. The difference in cost is based on the actual expenditure incured by the Board and is the difference between final cost and tentative cost. Notice dated 6.11.1999 mentioned Rs. 1,21,424 including interest of Rs. 63,548 as on 31.7.1999. They would have been issued the sale deed, if paid the due as per notice. The amount was hiked to Rs. 1,89,718 as on 3.3.2011 as it was not in time. The development works are done by the board itself. The board has approved the final cost on 16.4.1998 only. The final cost is fixed by the board based on actual expenditure whereas the tentative cost is fixed based on estimated and anticipated expenditure. Instead of paying the complainant sent a lawyer notice challenging the demand.

4. Complainant filed proof affidavit and Exts. A1 to A8 were marked. Ext. B1-B4 were marked by the opposite parties. Heard both sides. Hence the Forum turned down the claim as unsustainable on the basis of facts and circumstances and based on the earlier findings of the Commission in identical cases. Hence Forum below directed to execute the sale deed in respect of the flat E F 8 (a) 206 in favour of the complainant without collecting any additional amount. Aggrieved by the said order of the Forum, opposite parties preferred this appeal.

5. In the appeal memorandum the appellants emphasised Clause No. 9 of the agreement dated 26.11.1992. They assert that they are entitled to refix the final price taking into account the increased cost of development works and amenities undertaken and repeated the contentions in the lower Forum. The price arrived on 19.6.1992 was purely tentative. The above was agreed by the complainant as per the agreement. The land value fixed at the time of allotment was only tentative. The appellant board finalised the individual accounts only in September, 1999. When intimated the same the complainant filed representation and that too wa

1
2
3
4
5
6
7
8
9