NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION, NEW DELHI
V.K. Jain, Presiding Member
Mukesh Makkar—Complainant
versus
M/s. IREO Grace Realtech Pvt. Ltd. and Ors.—Opp. Parties
Consumer Case No.752 of 2018
Decided on 30.7.2019

Important Points

IMPORTANT POINT
If a builder fails to deliver possession of the flat/plot booked with him within the time period this would constitute a defect or deficiency.

Subject

Real Estate Law - Builder-Buyer Disputes

Act Referred

CONSUMER PROTECTION ACT : .

Headnote

Consumer Protection Act, 1986—Complainant booked a residential flat with project namely ‘The Corridors’—Parties executed Apartment Buyers Agreement on 20.03.2014—Sale price for the flat was Rs.1,56,79,491.91p.—Payable in instalments-possession ought to have been offered within a period of 42 months—Possession having not been offered—Deficiency-delay in completion of the construction—One of the grounds taken in the consumer complaint while seeking refund—Opposite party pay the entire principal amount of Rs.1,44,87,344/- to the complainant—Disposed off. (Paras 2, 6, 7 and 8)

Result: Complain Disposed off.

Advocates:
Counsel for the Parties:
For the Complainant:Mr. Deepak Kr. Khushalani, Advocate
For the Opp. Parties:Mr. P. Vinay Kumar, Advocate, Ruchi Kumar, Legal Manager & Kamlesh Kumar, Advocate

ORDER

The complainant Mr.Mukesh Makkar booked a residential flat with the OPs in a project namely ‘The Corridors’ which the OP was to develop in Sector-67A of Gurgaon. Apartment No.602 in Tower C-11 of the said project was allotted to him pursuant to his application dated 06.03.2013. The parties then executed an Apartment Buyers Agreement on 20.03.2014, incorporating their respective obligations. The sale price for the flat was agreed at Rs.1,56,79,491.91p., which was payable in instalments. As per clause 13.3 of the agreement, the possession ought to have been offered within a period of 42 months from the date of approval of the building plans. Clause 13.3 reads as under:

Subject to Force Majeure, as defined herein and further subject to the allottee having complied with all its obligations under the terms and conditions of this Agreement and not having defaulted under any provision(s) of this Agreement including but not limited to the timely payment of all dues and charges including the total Sale Consideration, registration charges, stamp duty and other charges and also subject to the Allottee having complied with all formalities or documentation as prescribed by the Company, the Company proposes to offer the possession of the said Apartment to the Allottee within a period of 42 (Forty Two) months from the date of approval of the Building Plans and/or fulfillment of the preconditions imposed thereunder (“Commitment period”). The Allottee further agrees and understands that the Company shall additionally be entitled to a period of 180 days (“Grace period”), after the expiry of the said Commitment Period to allow for unforeseen delays beyond the reasonable control of the Company.

The possession having not been offered to her, the complainant is before this Commission seeking refund of the amount paid by her to the OPs alongwith compensation etc.

2. The complaint has been resisted by the OPs admittedly on the grounds which this Commission has already rejected in several other Consumer Complaints including CC No.3873 of 2017 Abhishek Khanna & Anr. Vs. M/s Ireo Grace Realtech Pvt. Ltd. decided on 28.03.2019 and CC No.1998 of 2016 Subodh Pawar Vs. M/s Ireo Grace Realtech Pvt. Ltd. & connected matters, decided on 24.09.2018 and followed in several other Consumer Complaints decided by this Commission.

3. Clauses 21.1, 21.3 & 22.1 of the Agreement read as under:

21.1 Notwithstanding anything contained in this Agreement, timely performance by the allottee of its obligations under this Agreement, including without limitation, its obligations to make timely payment of the Sale Consideration, maintenance charges and other deposits and amounts, including any interest, in accordance with this Agreement shall be of essence under this Agreement. If the Allottee neglects, omits, ignores, or fails in the timely performance of its obligations agreed or stipulated herein for any reason whatsoever or acts in any manner contrary to any undertaking assured herein or fails to exercise the options offered by the Company within the stipulated period or to pay in time to the Company any of the installments or other amounts and charges due and payable by the Allottee by respective due dates or in case of default by the Allottee as described in Clause 7.7 herein, the Company shall be entitled to cancel the allotment and terminate this Agreement in the manner described hereunder:

21.1.1 In case any failure or breach committed by the Allottee is incapable of rectification or is in the opinion of the Company unlikely to be rectified by the Allottee or where the Allottee is a repetitive defaulter or such failure or default is continuing despite the Allottee being given an opportunity to rectify the same, then this Agreement may be cancelled by the Company with immediate effect as its sole option by written notice (“Notice of Termination”) to the Allottee intimating to the Allottee the decision of the Company to terminate the Agreement and the grounds on which s

1
2
3
4
5
6
7
8
9
10
11