NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION, NEW DELHI
Prem Narain, Presiding Member
EMAAR MGF Land Ltd. and Ors. —Appellant
versus
Sudesh Kumari Mahajan —Respondent
First Appeal No.375 of 2016
(Against the Order dated 18/01/2016 in Complaint No. 170/2014 of the State Commission Punjab)
Decided on 31.10.2019
Important Points
There is no justification for awarding separate compensation when interest is also in shape of compensation.
Subject
Consumer Dispute - REAL_ESTATE
Act Referred
Headnote
Consumer Protection Act, 1986 – Section 14(1)(d) – Real estate – Purchase of residential flat – Denial of possession despite substantial payment – There is a provision in agreement which mentions that timely payment of instalments is essence of agreement and allotment of plot – Once builder/promoter has accepted that time is essence of contract, then he cannot take plea that time is not essence of contract as this is a contract in respect of immovable property – If time is essence of contract for payment to be made by complainant, builder cannot take liberty of completing project beyond time agreed in builder–buyer agreement as he is also bound by the same (time is the essence of the contract) – Provision in agreement forfeiture of earnest money does not entitle opposite party to deduct earnest money unless opposite party has suffered a loss and loss is proved – Opposite parties have not filed any proof for any loss suffered by opposite parties – Appellants are not entitled to deduct earnest money in present case – Moreover, no breach of agreement has been occasioned by complainant before due date of possession as per agreement – Clause relating to deduction of earnest money cannot become applicable in facts of present case – There is no justification for awarding separate compensation of Rs.1,50,000/- to complainant because interest is also in shape of compensation only – Order of State Commission modified to the extent that order of State Commission in respect of award of compensation of Rs.1,50,000/- set aside. (Paras 22, 30, 31, 33, 34 and 35)
Result: Appeal Partly allowed.
For the Appellant:Mr. Aditya Narain, Advocate with Mr. Gaurav Sharma, Mr. Mishra Raj Shekhar, Advocates
For the Respondent:Ms. Vibha Mahajan Seth, Advocate with Ms. Niharika Beri, Advocate
ORDER
This appeal has been filed by the appellant Emaar MGF Land Ltd. & Ors. against the order dated 18.01.2016 of the State Consumer Disputes Redressal Commission, Punjab, (in short ‘the State Commission’) passed in complaint No.170 of 2014.
2. Brief facts of the case are that the complainant/respondent purchased a residential plot, in Sector 108, SAS Nagar Mohali from the appellants/opposite parties. She purchased plot No.380 of 300 Sq.yards. The plot was earlier allowed to one Mr. Rajeev Kumar Jain. Thereafter it was endorsed, with the allotment letter, to the complainant dated 8.8.2008. Total consideration of the flat was Rs.40,28,499. Total payment made by the complainant was Rs.41,78,501/-. Opposite parties promised to deliver the possession to the complainant within 3 years, maximum subject to force majeure as per the Builder –Buyer agreement (BBA). Till date of filing of the complainant, possession was not offered to the complainant. Thereafter, when complainant demanded refund of money, opposite parties flatly refused it after lingering on the matter on some or the other pretext. Aggrieved, the complainant filed a consumer complaint bearing CC No.170 of 2014 before the State Commission.
3. The complaint was resisted by the opposite parties by filing written reply. Opposite parties pleaded that she bought the plot from open market at her own will. Possession will be offered shortly with compensation for delay to the complainant as per the terms of the agreement. On 18.01.2016, the State Commission passed the following order:-
“11. In the result, the complaint is allowed and the following directions are issued to the opposite parties:-
i) to refund the amount of Rs.41,78,501/-, along with interest at the rate of 12% per annum from 29.6.2010 till the date of payment of that amount;
ii) to pay Rs.1,50,000/- as compensation for the physical and mental harassment suffered by her; and
iii) to pay Rs.22,000/- as litigation expenses.
The compliance of this order shall be made by the opposite parties within a period of one month from the date of receipt of the certified copy of this order.”
4. Hence the present appeal.
5. Heard the learned counsel for the parties and perused the record. The learned counsel for the appellants/opposite parties stated that they have filed along with their evidence the copy of the intimation of possession letter dated 7th Feb-2015 after establishing all amenities in terms of the Buyer’s agreement. Copy of the intimation of possession letter alongwith dispatch receipt was annexed hereto. It is not out of place to mention here that in case of any delay in handing over possession beyond the proposed period of 3 years, there are sufficient safeguards in the agreement to protect the interest of the consumer and the opposite parties are committed to honour the same. Yet further, as per agreed terms, in case of the allottee seeking refund, the same shall be governed by clause 2(f) of the Buyer’s Agreement which provides for forfeiture of earnest money.
6. Learned counsel for the appellants stated that the offer of possession was sent on 07.02.2015 whereas the complaint was already filed on 14.10.2014. This offer was given before filing the written statement by the opposite parties. The learned counsel mentioned that complaint was filed for delay in possession. It was further argued that the complainant is a subsequent purchaser and the first purchaser Mr. Rajiv Kumar Jain entered into the buyer agreement on 30.6.2006. The plot was transferred in the name of the complainant and the endorsement was made on 08.08.2008. Learned counsel stated that as per Clause 8 of the agreement, a tentative time for possession was given from two years to three years. Para 8 of the Plot Buyer’s Agreement reads as under:-
“8. Subject to Force Majeure conditions and reasons beyond the control of the Company, the Company shall endeavour to deliver possession of the Plot of the Allotte within a period of 2 (Two) years from the date