V.K.JAIN
Swapnil Builders and Developers – Appellant
Versus
Iila Banerjee – Respondent


Advocates:
Counsel for the Parties:
For the Petitioner:Mohd. Anis-Ur-Rehman, Advocate
For the Respondent:Mr. B.S. Sharma, Advocate

ORDER (ORAL)

V.K. Jain, Presiding Member—The complainant/respondent booked a residential flat with the petitioner in a project namely ‘Rajmahal Green Town’, which the petitioner was to develop in Bhilai. Initially, the complainants had booked a two BHK residential apartment with the petitioner on 06.04.2013 and the possession was agreed to be delivered within two years. Thereafter, the parties executed another agreement whereby a three BHK flat was agreed to be delivered to the complainants within two years of the subsequent agreement dated 06.04.2015, for a consideration of Rs.16,50,000/-. The possession of the flat having not been given to them, the complainants approached the concerned District Forum by way of a Consumer Complaint instituted on 21.03.2016 seeking refund of the amount which they had paid to the petitioner alongwith interest, compensation etc.

2. The complaint was resisted by the petitioner which inter-alia stated in its written version that the construction work was in progress and the complainant had not made payment as per the agreement between the parties. It was also stated in the written version that the petitioner was ready to give the flat on receiving the

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top