SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION, NEW DELHI
Deepa Sharma, Presiding Member
Harish Jain and Ors. – Complainants
versus
M/s. Ramprastha Promoters and Developers Pvt. Ltd. and Anr. – Opp. Parties
Consumer Case No.2089 of 2016, Consumer Case No.2090 of 2016, Consumer Case No.2091 of 2016, Consumer Case No.2092 of 2016 and Consumer Case No.2093 of 2016
Decided on 19.3.2021

Advocates:
Counsel for the Parties:
For the Complainants:Mr. Sushil Kaushik, Advocate

IMPORTANT POINT
“Since the possession of subject flats were not delivered within the stipulated time, allottee held entitled for refund of amount deposited with interest.”

Headnote:

Consumer Protection Act, 1986 – Sections 21 and 2(1)(c) : [Consumer Protection Act, 2019 – Sections 58 and 2(6)] – Allotment of flat – Non-delivery of possession – Refund of amount deposited – Scope – Complainants had booked subject-flats in question – However, opposite parties had failed to deliver possession within the 36 months from execution of Builder-Buyer Agreements – Payments towards costs of flat had already been deposited – Opposite parties were bound under aforesaid agreement to handover the possession of the unit by September 2015, extendable to four months – Plea of pecuniary jurisdiction also ruled out – Since the possession was not delivered within the stipulated time, allottee held entitled for refund of the amount along with reasonable interest – Complainants therefore held entitled for refund of their respective amounts deposited – Further directions issued. (Paras 8 to 22)

Result: Complaints Allowed.

ORDER

Deepa Sharma, Presiding Member.—This order shall dispose of the Consumer Complaints No.2089, 2090, 2091, 2092 and 2093 of 2016 since all the Complaints are against the same Opposite Parties and relate to the same project and the facts in all the cases are similar. Facts are being taken from Consumer Complaint No.2089 of 2016.

2. In brief, the facts of the case are that the Complainants had booked a flat in the project “RISE” of the Opposite Parties in RP City, Sector 37 D, Gurgaon, Haryana. The details are as under:

Complaint No.

Date of booking

Total amount paid

Proposed date

Date of execution of Builder Buyer Agreement

2089 of 2016

26.03.2012

Rs.67,77,234/-

30.09.2015

28.08.2012

2090 of 2016

09.12.2011

Rs.62,09,154/-

30.09.2015

02.11.2012

2091 of 2016

22.11.2011

Rs.62,87,222/-

30.09.2015

15.12.2012

2092 of 2016

02.04.2012

Rs.66,20,645/-

30.09.2015

14.09.2012

2093 of 2016

02.04.2012

Rs.68,58,904/-

30.09.2015

20.07.2012

3. The case of the Complainants is that the Opposite Parties had promised to hand over the possession of the subject flats within 36 months from the date of execution of the Builder Buyer Agreement but they have miserably failed to do so. At the time of signing the Builder Buyer Agreement, the same was not shown to the Complainants. It is submitted that the Builder Buyer Agreement is one sided and is in favour of the Opposite Parties, violating the rights and interest of the Complainants. It is submitted that since the Opposite Parties have failed to hand over the possession of the flats within the stipulated period, the Opposite Parties be directed to refund their deposited amount along with service tax, compound interest @ 18% p.a. from the date of deposit and also to pay a sum of Rs.5 lakhs towards the mental agony and harassment and the cost of litigation.

4. In the written statement filed by the Opposite Party No.1, it is submitted that there is no deficiency in service and no unfair trade practice has been adopted by them. It is submitted that the delay in handing over the possession has been caused due to the reasons which were beyond the control of the Opposite Party. It is submitted that as per the terms and conditions of the Builder Buyer Agreement, the parties had agreed for extension of time for handing over of the possession in such contingencies. It is further contended that the time was not the essence as per the clause 13(a) of the Builder Buyer Agreement and the time was the essence only in relation to the allottees obligation to pay. It is further contended that the compound interest which has been sought by the Complainants is on the higher side and is in violation of the order of the Hon’ble Supreme Court in “Bharathi Knitting Company vs. DHL Worldwide Express Courier division of Airfreight Ltd. AIR 1996 SC 2508”. It is submitted that in the said order, the Hon’ble Supreme Court has clearly observed that the stipulations in the contract have to be adhered by and cannot be neglected. He has also relied on “Secretary, Bhubaneswar Development Authority vs. Susanta Kumar Mishra, V (2009) SLT 242” and has submitted that the parties are bound by the unchallenged terms of the contract. Reliance is also placed on “PUDA (Chief Administrator) and Another vs. Mrs. Shabnam Virk, II (2006) CPJ 1 (SC)”. It is submitted that in the said case, the Hon’ble Supreme Court has held that the allottee would be bound by the terms and conditions contained in the allotment letter agreed by him. It is submitted that in view of these judgments, the Complainants cannot claim the compensation or interest beyond the amount of compensation provided in the agreement. It is submitted that the Builder Buyer Agreement clearly specifies the amount of compensation the Complainants are entitled to in the case of delay. Reliance is also placed

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top