NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION, NEW DELHI
R.K. Agrawal, President and Dr. S.M. Kantikar, Member
Nishant Saini and Anr. – Complainants
versus
SS Group Private Limited and Ors. – Opp. Parties
Consumer Case No.1306 of 2016
Decided on 18.3.2021
Consumer Protection Act, 1986 – Sections 21 and 2(1)(g) : [Consumer Protection Act, 2019 – Sections 58 and 2(11)] – Allotment of Flat – Delay in delivery of possession – Refund of amount – Scope – Complainants booked a flat on 5.6.2012 as developed by opposite parties – Possession was to be delivered to the complainants on or before 15.9.2015 – Opposite parties had failed to deliver the possession as committed despite receiving the amount of Rs. 1,11,32,379, out of total compensation of Rs. 1,26,72,000/- – Therefore, complainants found entitled to refund of amount deposited – Therefore, opposite parties directed to refund the entire principal amount received from the complainants alongwith compensation in the form of simple interest @ 9% p.a. – Further directions also issued.
Held: I have given a thoughtful consideration to the arguments advanced by the learned counsel for the parties and examined the record. The admitted fact is that the possession was due on 30.5.2015 and the occupancy certificate has been obtained on 17.10.2018. Clearly, there is a huge delay in the project. Letter of offer of possession was issued on 22.11.2018. The complainants have not accepted offer of possession as the complainants have already given a notice for cancelling the agreement as per clause 8.3 (b) of the agreement. Now, the question arises as to when the opposite parties have agreed to have a clause like 8.3(b) in the agreement and if the complainants have acted in accordance with this clause, the opposite parties should also have acted in compliance of this clause. Even this Clause 8.3 (b) seems one sided because the complainants’ money is already blocked and if the same is not returned till the unit in question is sold to a third party, this is clearly prejudicial to the interest of the consumer. The interest @ 15% is only payable when the flat is sold to a third party and the money is not refunded within 90 days from that sale. All these conditions are totally one sided and they are the result of the dominant position of the builder at the time of signing the builder-buyer agreement because by that time lot of money of the complainants is already blocked with the builder.
The main reason for delay in completion of the project has been told to be due to delay in obtaining environmental clearance for the project. Though, this may not be directly within the control of the opposite parties to get the clearance, however, the clear procedures are laid down and it depends on the management of the builder company how efficiently and meticulously they pursue the environmental clearance with the competent authority. Thus, this cannot be considered as force majeure, therefore, the delay on account of this factor cannot be excluded from the total delay in the project. Hon’ble Supreme Court in Civil Appeal No.12238 of 2018 titled as “Pioneer Urban Land & Infrastructure Ltd. versus Govindan Raghavan” has upheld the order of this Commission.
It is submitted by the learned Counsel appearing for the Complainants that the order passed by the Co-ordinate Bench of this Commission has not been challenged by the Opposite Parties in Appeal before the Hon’ble Supreme Court and as such it has attained finality. Accordingly, following the decision rendered by a Coordinate Bench of this Commission in the aforesaid case, we dispose of both the Complaints and direct the Opposite Parties to refund the entire principal amount received from the Complainants alongwith compensation in the form of simple interest @ 9% p.a as awarded by the Coordinate Bench in the aforesaid case, from the respective dates of deposit till the actual date of payment together with costs of Rs.25,000/- to the Complainants in both the cases. The aforesaid directions shall be complied with within a period of eight weeks from the date of receipt of a copy of this order failing which the amount shall carry interest @ 11% p.a. for the same period. (Paras 12 to 15)
Result: Complaint Allowed.
ORDER
R.K. Agrawal, President.—The present Consumer Complaints have been filed under Section 21(a)(i) of the Consumer Protection Act, 1986 (for short “the Act”) by the Complainants, the allottees of Residential Flat in the luxury residential Group Housing Complex, namely, “The Coralwood & Almeria” (hereinafter to be referred to as “the Project”) to be developed and constructed by the Opposite Parties at Village Sihi, Sector 84, Gurgaon, against Opposite Party No.1, North Star Apartments Pvt. Ltd. (amalgamated in S.S. Group Pvt. Ltd. and now known as S.S. Group Pvt. Ltd) and Opposite Party Nos.2 and No.3, Directors of Opposite Party No.1, inter alia, alleging deficiency in service in not handing over the possession till today and seeking refund of the amount deposited by them with the Opposite Parties along with reasonable interest and compensation.
2. In both the Complaints, Complainants have entered into identical “Flat Buyer’s Agreement” with the Opposite Parties; the facts and question of law involved in their cases are similar, inasmuch as physical possession of the allotted Flats, has not been handed over within the committed period and almost similar reliefs have been prayed for in both the Complaints.
3. For the sake of convenience, the material facts, enumerated hereinafter, are taken from the Consumer Complaint No. 1306 of 2016 titled as Nishant Saini & Anr. Vs. S.S. Group Private Limited and Ors.
4. Factual matrix as culminating from the Consumer Complaint is that on 10.04.2012, the Complainants, husband and wife, had applied for booking of a residential Flat in the Group Housing Complex, i.e, “The Coralwood & Almeria” in Sector 84, Gurgaon by paying the booking amount of Rs.13,09,684/-. Vide Allotment Letter, dated 17.05.2012, Complainants were allotted Unit No. 17A on the ground floor admeasuring super area of 2,000 sq. ft. in the Building No. 17A in Almeria Residential Complex for a total consideration of Rs.1,26,72,000/- including Preferential Location Charges of Rs.300/- per sq. ft., External Development Charges of Rs.271/- per sq. ft. and Infrastructural Development Charges of Rs.35/- per sq. ft.. The Flat Buyer’s Agreement (for short, the “”Agreement”) was executed between the parties on 05.06.2012. As per Clause 8 of the Agreement, the construction of the allotted Flat to be completed and possession was to be handed over by the Opposite Parties within 36 months from the date of execution of the Agreement. The Opposite Parties were also entitled for a grace period of 90 days after the expiry of 36 months for applying and obtaining the Occupation Certificate in respect of the Group Housing Complex, meaning thereby that the possession should have been handed over to the Complainants on or before 05.09.2015. The Complainants have also obtained a home loan of Rs.1,02,20,145/- from the Indiabulls Housing Finance Ltd. (for short, the “IHFL”) for which a Tripartite Agreement was executed between the Complainants, Opposite Parties and IHFL on 23.06.2012. The Complainants were also liable to pay pre-EMI interest of Rs.75,006/- to IHFL on the amount disbursed to them. It is averred that all the payments as demanded by the Opposite Parties were made by the Complainants without any default. According to the Complainants, they have paid a sum of Rs.1,11,32,379/- to the Opposite Parties till 06.06.2014.
5. In June, 2016, the Complainant No.1 visited the Project Site and was utterly shocked and surprised to see the progress of the construction at the site. The construction of the Project was stopped and was far away from completion in the near future. Even the structure of the building was not complete and the rear courtyard attached to the allotted Unit was reduced to less than 600 sq. ft. from 900 sq. ft. It is stated in the Complaint that the Opposite Parties, despite having received the complete due amount, have miserably failed to construct the said Project and hand over the possession of the Flat, complete in all respe
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.