SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION, NEW DELHI
Deepa Sharma, Presiding Member
Sudha and Ors. – Complainants
versus
Jaiprakash Associates Limited – Opp. Party
Consumer Case No.2804 of 2017
Decided on 29.4.2021

Advocates:
Counsel for the Parties:
For the Complainants:Mr. Nakul Singh Pathania, Advocate
For the Opp. Party:Mr. Sukumar Pattjoshi, Sr. Advocate with Mr. Sumeet Sharma, Advocate

IMPORTANT POINT
“Where after of possession is made along with occupation certificate even of there is delay in said after the allottees of flat cannot refuse to take possession.”

Headnote:

Consumer Protection Act, 1986 – Sections 21 and 2(1)(g) : [Consumer Protection Act, 2019 – Sections 58 and 2(11)] – Allotment of flat – Delivery of possession – Dispute as to – Refund to take possession – Complainants had booked one flat in Garden Isles in year 2013 which was to be completed within four years – However, before expiry of four years, they had booked the subject flat in Imperial Courts project and subsequently sought cancellation of earlier booked Garden Isles flat – And also sought transfer of money they had paid against Garden Isles flat in the account of Imperial Courts – Complainants had also raised certain objections relating to Garden Isles flat – However, no report from a qualified architect specifying defects on account of which complainants were not willing to take possession, has been filed – Where offer of possession is made along with occupation certificate even if there is a delay in the said after, the allottees cannot refuse to take the possession – There is no delay in after of possession and complainants have since failed to give any valid reason to refuse to take possession, thus such refusal to take possession and refund sought in facts and circumstances of care held not justifiable – Complainants also have failed to prove any fact on record to show that opposite party had adopted on unfair trade practice or that the agreement was biased – Relief sough by complainant cannot be granted.

Held: In the present case, mere averment that the Complainants were forced or induced are made and no specific allegation has been made by the Complainants. Rather, the facts of the case go to show that the Complainants have been acting voluntarily. During the existence of the allotment of their flat in Garden isles project, they booked another flat in Imperial Courts and finding difficult in paying installments towards Imperial Courts flat, they sought cancellation of the allotment of the flat in Garden Isles even before the period within which the possession of the said flat was to be handed over to them and requested for transfer of the money paid against the said flat in the account of Imperial Courts. The Complainants have relied on judgment of this Commission in “Ramesh Malhotra & Ors. vs. Emaar MGF Land Limited & Anr. decided on 29.06.2020 in Consumer Complaint No.438 of 2019”. The facts in that case are entirely different from the case before me. In Ramesh Malhotra’s case (supra), there was a delay of about 1 year and 2 months in offering the possession while there is no delay in the present case.

The Opposite Party on the other hand has relied on the findings of the Hon’ble Supreme Court in “Ireo Grace Realtech Pvt. Ltd. Vs. Abhishek Khanna & Ors., Civil Appeal No.5785 of 2019 decided on 11.01.2021. It is argued that the three judges bench of the Hon’ble Supreme Court in Abhishek Khanna’s case (supra) had even directed the allottees to take possession of the flat wherein the offer of possession was delayed and in this case, there was no delay in offer of possession. It has relied on para 21.1 of the said judgment which is reproduced as under:

“21.1 The issue which now arises is whether the apartment buyers are bound to accept the offer of possession made by the Developer where the Occupation Certificate has been issued, along with the payment of Delay Compensation, or are entitled to terminate the Agreement.

The factum of delay in completing the construction and making the offer of possession is an undisputed fact in this case.”

It is clear from the findings of the Hon’ble Supreme Court in Abhishek Khanna’s case (supra) that where the offer of possession is made along with Occupation Certificate, even if there is a delay in the said offer, the allottees cannot refuse to take the possession. In the present case, there is no delay in the offer of possession and the Complainants have since failed to give any valid reason and also there exists no valid reason/ground for the Complainants to refuse to take possession and terminate the contract, the refusal of take possession and refund sought in the facts and circumstances of the case is not justifiable. The Complainants have failed to prove any fact on record to show that the Opposite Party had adopted an unfair trade practice or that the agreement was biased or one sided.

The relief claimed qua Garden Isles flat is naturally time barred, but the Complainant’s claim is unwarranted.

In view of the above discussion, it is apparent that the relief sought by the Complainants cannot be granted. The Complaint stands disposed of in these terms. (Paras 13 to 17)

Result: Complaint Disposed of.

ORDER

Deepa Sharma, Presiding Member.—This Complaint has been filed on 20.09.2017.

2. The brief facts as alleged in the Complaint are that on 27.01.2013, the Complainant no.3 Sh. Naren Nath Sarvaria booked a unit no. GDI 143304 in Garden Isels project of the Opposite Party and the possession was to be handed over within 42 months, i.e., three and a half year. The Complainant no.3 took a home loan for the said unit on 21.04.2015 and paid EMI of approximately Rs.35,000/- per month and paid total amount of Rs.59,48,479.86/- towards the said unit. He also had to pay the late payment of installment @12% p.a. It is alleged that the Complainant No.3 was again duped for the second time by the Opposite Party in June-July 2015. When he had went to the office of the Opposite Party complaining about the delay in construction of the Garden Isels, it was suggested by the Opposite Party that the Complainant no.3 should buy another flat. Thereafter, the flat in the project Imperial Courts was booked by all the Complainants on 12.06.2015. It was a four bedroom flat measuring 3724.68 sq. ft. as covered area with the super area of 3724.68 sq. ft. with four car parking. The cost of one car parking was Rs.5,00,000/- which was double the cost of the car parking offered in the previous unit. At the time of booking of the flat, a 4% discount on the consolidated final figure of the sale consideration was given to the Complainant. On 11.07.2015 an allotment letter was issued and the Opposite Party promised to hand over the possession within 24 months. It is contended that in the month of October 2015, the Complainant as per the plan and advice of the Opposite Party sought cancellation of the purchased unit in Garden Isels and requested for the transfer of the amount in the account of Imperial Courts flat. In March, 2016 the Opposite Party transferred the said amount in the account of Imperial Courts flat. It is submitted that due to the said transfer, the Complainants have lost home loan monthly EMI of Rs.35,000/- paid for over 25 months, 5% deduction on cancellation of the unit and the late payment amount of Rs.2 to 4 Lakhs calculated @ 12% p.a. on the late payment of the installments and this amount comes to approximately Rs.14 to 16 Lakhs and it is recoverable from the Opposite Party along with compensation for harassment and mental agony.

3. On 24.10.2016, the Complainant received a possession letter from the Opposite Party indicating the total sale consideration of Rs.2,98,13,862.30/-. By 31.12.2016, the Opposite Party had received a sum of Rs.28,825,436/-. It is submitted that the total consideration amount stood paid to the Opposite Party on 31.12.2016 and as per the possession letter, the flat was to be handed over within 45 days, i.e., by 15th February 2017. However, series of unfortunate and exploitative events took place after the entire consideration amount was paid by the Complainants. It is submitted that the Opposite Party informed the Complainants about the shortage of material and therefore, informed them that it would take a long time for them to install 7 ACs, one Jacuzzi, well-furnished modular kitchen and wardrobes in all four bedrooms. On the advice of the Opposite Party, the Complainants under duress decided to give up all the materials like installation 7 ACs, one Jacuzzi, well-furnished modular kitchen and wardrobes in all four bedrooms and for that purpose, the Opposite Party had given a discount of Rs.4,72,900/-, while the actual cost of all those articles were more than Rs.15 Lakhs. The work which was left to be done was final finishing like putting of window panels and glasses, painting/whitewash, bathroom fittings and kitchen fitting, putting granite slabs etc. and bedroom wooden flooring, electricity and pluming. It is submitted that as per the assurance of the Opposite Party, the flooring was to be done with imported

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top