NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION, NEW DELHI
C. Viswanath, Presiding Member and Ram Surat Ram Maurya, Member
Manoj Kawatra and Anr. – Complainants
versus
Pioneer Urban Land & Infrastructure Ltd. – Opp. Party
Consumer Case No.1442 of 2018 and Consumer Case No.1443 of 2018
Decided on 1.11.2021

Important Points

IMPORTANT POINTS
1) Opp. Party failed to prove that there was any unforeseen and unexpected event which prevented the completion of the Project within the stipulated time period.
2) Opp. Party cannot take shelter of the “Force Majeure” Clause, reasons cited by the Opp. Party for the delay appears to be delaying tactics veiled as “Force Majeure” conditions to wriggle out of its contractual obligations.

Subject

Consumer Protection - Real Estate

Act Referred

CONSUMER PROTECTION ACT : S.12(1)(a), S.21, S.58

Headnote

Consumer Protection Act, 1986 – Section 12 (1)(a) read with Section 21 [Section 58 – Consumer Protection Act, 2019] – Complaint before NCDRC – Complainants booked Unit in “Araya” by Opp, Party in Gurgaon 12.09.2012 and paid a booking amt. of Rs.40,00,000 - possession of the Unit was to be delivered by 04.03.2016, including grace period of 6 months – Complainants are consumers only - Alleging deficiency on part of the Opp. Party, Complainants filed the present Complaint before this Commission seeking 100% refund of the total amt. of Rs. 5,68,07,347/- (Rupees Five Crore Sixty Seven lakh Seven Thousand Three Hundred and Forty Four only) along with a penal interest of 18% p.a. - Findings of this Commission: No evidence of any lock-out or strike by labour at the site of the project - Opp. Party failed to prove that there was any unforeseen and unexpected event which prevented the completion of the Project within the stipulated time period Opp. Party cannot take shelter of the “Force Majeure” Clause, reasons cited by the Opp. Party for the delay appears to be delaying tactics veiled as “Force Majeure” conditions to wriggle out of its contractual obligations - Even after receiving substantial amt., Opp. Party failed to fulfil its contractual obligation of delivering possession of the Unit to the Complainant within the time stipulated in the Agreement or even within a reasonable time thereafter. (Paras 5, 8, 9 & 10)

Result: Complaint is partly allowed with direction to the Opp. Party to refund the amt. deposited by Complainants along with compensation in form of simple interest @ 9% p.a.

Advocates:
Counsel for the Parties:
For the Complainants:Mr. Aditya Parolia, Advocate
For the Opp. Party:Mr. T.V.S. Raghavendra Sreyas, Advocate

ORDER

According to the Complainants, they booked a Unit in “Araya” Project of the Opposite Party at Village Ghata, Sector 62, Gurgaon, Haryana on 12.09.2012 and paid a booking amount of Rs.40,00,000/-. Unit bearing No.B-1502 on 15th Floor of Tower B, having a super area of 5,514 sq.ft. was allotted to the Complainants, vide Allotment Letter dated 14.09.2012 issued by the Opposite Party. Subsequently, an Apartment Buyer’s Agreement was executed on 24.10.2012, wherein possession of the unit was promised within 39 months from the date of excavation, excluding an additional grace period of 6 months to complete the project. As per the Complainant, excavation of the Project started on 04.06.2012 and hence possession of the Unit was to be delivered by 04.03.2016, including grace period of 6 months. The grievance of the Complainants is that the Opposite Party, despite receiving more than 90% of the total consideration, failed to hand over possession of the Unit, within the promised time period and even possession in the near future seemed unlikely. Alleging deficiency on the part of the Opposite Party, the Complainants filed the present Complaint before this Commission under Section 21 read with Section 12 (1) (a) of the Consumer Protection Act, 1986, praying relief as under: -

“a) Direct the Opposite Party for an immediate 100% refund of the total amount of INR. 5,68,07,347/- (Rupees Five Crore Sixty Seven lakh Seven Thousand Three Hundred and Forty Four only) paid by the Complainant along with a penal interest of 18% per annum from the date of receipt of payments made to the Opposite Party for a Unit in the Project “Araya” at Village Ghata, Sector 62, Gurgaon, Haryana;

b) Direct the Opposite Party to pay compensation of Rs.10,00,000/- (Rupees Ten Lakh only) to the Complainants for mental agony, harassment, discomfort and undue hardships caused to the Complainants as a result of the above acts and omissions on part of the Opposite Party;

c) Direct the Opposite Party, jointly or severally, to pay a sum of Rs.1,50,000/- (Rupees One lakh and Fifty Thousand only) to the Complainants in the Project “Araya” towards litigation costs;

d) That any other and further relief in favour of the Complainants as the Hon’ble Commission may deem fit and proper in the fact and circumstances of the case.”

2. The Complaint was contested by the Opposite Party by filing Written Statement. Opposite Party took preliminary objection about the maintainability of the Complaint. The Complainant was an investor who booked the unit for resale purpose and making profit. The dispute between the Parties comes to the interpretation of clauses or applicability of statutory charges, which cannot be termed as “deficiency in service.” The Complaint is, therefore, not maintainable in the Consumer Forum. Opposite Party also took the ground that the Complainants failed to make timely payments. However, the Opposite Party, while admitting delay in delivering possession of the Unit, stated that the delay was purely beyond their control. Further, it was contended that the time stipulated for delivering possession of the Unit in the Apartment Buyer’s Agreement was only tentative.

3. Heard the Learned Counsels for both the Parties and carefully perused the record. The learned Counsel for the Complainants stated that the Opposite Party was casual with the construction of the project and delivery even in the near future seemed impossible. The construction status of the Project, as per the website of the Opposite Party, indicated that only the basic structure of the Project was constructed as on March, 2018. It was also contended that the Complainants had to agree to the Apartment Buyer’s Agreement in its entirety, though it contained several one-sided and unreasonable clauses. The Complainants could not negotiate on them due to continuous threat of forfeiture of earnest money, i.e. 10% of the total consideration. It was further stated by the Complainants that the services of the