SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION, NEW DELHI
R.K. Agrawal, President and Dr. S.M. Kantikar, Member
Rajat Babbar and Anr. – Complainants
versus
Parsvanath Developers Ltd. and Anr. – Opp. Parties
Consumer Case No.2489 of 2017
Decided on 10.12.2021

Advocates:
Counsel for the Parties:
For the Complainants:Mr. M.L. Lahoty, Advocate
For the Opp. Parties:Mr. Prabhaker Tiwari, Advocate

IMPORTANT POINT
Wait indefinitely – Complainants cannot be made to wait indefinitely for possession of the booked Flat, as even till date the construction is incomplete.

Headnote:

Consumer Protection Act, 1986 – S.21(a) [Consumer Protection Act, 2019 – S.58(1)(a)] – Real Estate – Builder Buyer Agreements – Construction of the Project in question was required to be completed by the Developer within 36 months of commencement of the construction of Block B6, in which the Flat of the Complainants was located or within 24 months from the booking of the flat, whichever was later, with a grace period of six months – Alleged delay in handing over Apartment – Complaint filed – Whether delay having over apartment amounts to deficiency of Service – There in an inordinate delay of more than seven years from proposed date of handing over the possession to the Complainants by the Developer and the construction is still incomplete, Court is of the view that the Complainants are entitled for refund of the deposited amount with reasonable interest. [Para 12]

(ii) Consumer Protection Act, 1986 – S.21(a)[Consumer Protection Act, 2019 – S.58(1)(a)] – Real Estate – Builder Buyer Agreements – What rate of interestis to be paid to the Complainants on the principal amount – Computation of by National Commission – Complainants in the present case are also entitled for compensation in the form of interest @ 10 % p.a. Developer shall also pay a sum of Rs.50,000/- to the Complainants towards litigation cost. [Para 14]

Held, Hon’ble Supreme Court has been awarding lower rate of interest keeping in view the current market situation and considering the recent decline in the cost of borrowing and return on the investments made with the Banks and further keeping in mind the decisions of the Co-ordinate Benches of this Commission with respect to the same Project” Parsvnath Exotica” in Rohit Agarwal’s case and Ashwani Kapoor Vs. Parsvnath Hessa Developers Private Limited, Consumer Complaint No.2133 of 2017, decided on 14.08.2018, wherein this Commission has directed refund of the principal amount with interest @ 10 % p.a. from the respective dates of deposit.

ORDER

The present Complaint has been filed under Section 21 (a) of the Consumer Protection Act, 1986 (hereinafter referred to as “the Act”) against the Opposite Parties, namely, M/s. Parsvnath Developers Ltd. and M/s Parsvnath Hessa Developers Pvt. Ltd. (hereinafter referred to as “the Developer”) seeking the following reliefs:

a. “Direct the Opposite Parties to refund Rs.2,28,28,746.29 to the Complainants;

b. Direct the Opposite Parties to pay interest of Rs.2,80,12,963.14 (Calculated @ 18% per annum from the respective installments upto August, 2017);

c. Direct the Opposite Parties to pay a sum of Rs.25 lacs towards opportunity loss caused to Complainants due to the acts of omission/ commission on the part of the Opposite Parties;

d. Direct the Opposite Parties to pay a sum of Rs. 10 lacs towards undue hardship, injury and agony both physical and mental caused to the Complainants.

e. Direct the Opposite Parties to pay at least a sum of Rs. One Lac to the Complainants towards the cost of litigation.

f. Pass such order or further order as this Hon’ble Commission deems fit and proper in the facts and circumstances of the present case.”

2. The facts as enumerated in the Complaint are that allured by the advertisements and promises made in the Brochure, the Complainants applied for booking of a Flat in August, 2010 in the Project “Parsvnath Exotica”, to be developed by the Developer at Golf Course Road, Gurgaon, Haryana. In October, 2010 the Complainants were allotted Flat bearing No. B6-302, 3rd Floor in Tower B-6, admeasuring 3390 sq. ft. at the basic cost of Rs.2,46,62,250/- in the aforesaid Residential Project. The Complainants had opted for down payment plan and by May, 2011 they paid a total sum of Rs.2,28,28,746.29 as demanded by the Developer. It is stated that belatedly after almost 15 months of payment of substantial amount, on 29.08.2012, the Complainants were coerced to sign Unfair and One-sided standard form of Flat Buyer Agreement (hereinafter referred to as “the Agreement”) on the threat of forfeiture of huge money on account of earnest money and other charges in case the Complainants have any objection to sign the Agreement. It is alleged that most of the Clauses of the Agreement are totally one-sided, unfair and unjust and are made to suit the whims of the Developer. It is further averred in the Complaint that unfairness and one-sidedness of the Agreement can be seen from bare perusal of the Clauses 5 and 10 of the Agreement which stipulate that on the one hand, the Developer shall be liable to pay a meager compensation of Rs.10/- per Sq. Ft. per month for any delay in handing over of possession of the Flat on their part and on the other hand, the Allottees are charged an exorbitant interest @ 24% p.a. for any delay in payment of installments. According to the Complainants, as per Clause 10 (a) of the Agreement the construction of the Flat was to be completed within a period of 36 months from the date of commencement of the construction of the particular Block in which the booked flat was located or 24 months from the date of booking of the Flat, whichever is later, with a grace period of six months, i.e. by March, 2013.

3. The Complainants repeatedly visited the construction site and office of the Developer during the period from the year 2012 and 2016 to take note of the construction stage but there was no construction at the site. On 10.05.2016, the Complainants wrote a letter to the Developer expressing their serious concern and requesting the Developer to inform for definite date of handing over the possession of the Flat within six months. The Developer, vide letter dated 09.07.2016 informed the Complainants that due to some technical reasons, the construction was on hold and now construction had started in Tower B5 and B6 and the possession of the Flat is likely to be delivered by third quarter of 2017.

4. In September and December, 2016, the Complainants were shocked to see that there was no constru

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top