NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION, NEW DELHI
R.K. Agrawal, President, Dr. S.M. Kantikar, Member and Binoy Kumar, Member
Vandana Kapila and Anr. – Complainants
versus
M/s. Ireo Pvt. Ltd. – Opp. Party
Consumer Case No.1639 of 2016
Decided on 21.12.2021
Consumer Protection Act, 1986 – S.21[Consumer Protection Act, 2019 – S.58] – Real Estate – Whether computing the 42 months commitment period plus 180 days grace period from 25.09.2013, i.e., the date of obtaining Fire NOC, there is delay in handing over possession – Computing the 42 months commitment period plus 180 days grace period from 25.09.2013, i.e., the date of obtaining Fire NOC, the OP Developer was bound to deliver the possession of the Flat to the Complainants by 25.09.2017. In the present case, admittedly the physical possession of the Flat was given to the Complainants on 14.03.2017, i.e., much before 25.09.2017. Therefore, there is no delay on the part of the OP Developer in giving the Possession of the Flat to the Complainants – Complaint dismissed.
(ii) Consumer Protection Act, 1986 – S.21[Consumer Protection Act, 2019 – S.58] – Real Estate – Whether OP Builder has illegally raised demand for Club House, Infra Augmentation Charges, Labour Cess on Project, Applicable Carrying Cost – OP Developer was justified in raising the demand vide Notice of Possession dated 06.09.2016 and the Complainants are bound to pay the same.
Held, On perusal of various clauses of the Agreement and Court finds that the demand raised by the OP Developer under the head ‘Non-Refundable Skyon Club Deposit’, Infra Augmentation Charges (IAC), Labour Cess on Project Applicable carrying cost, Interest on Delayed payment, Internal electrical charges, Service Tax Component, Recovery towards cost on account of Indirect taxes’ are in terms of the Agreement. As far as the ‘Internal Gas pipe laying & meter charges’ and ‘Administrative Charges for Registration’ are concerned, keeping in mind the safety of the Apartment owners, the OP Developer has installed Internal Gas Pipe Line to ensure that the cylinders are kept outdoors and gas is supplied to the Apartment through pipelines and meters were installed to monitor the gas usage. Since the OP Developer has hired the services of a third party for the purpose of Registration of Conveyance Deed of the Apartment, the demand for ‘Administrative Charges for Registration’ is raised.
ORDER
The present Consumer Complaint has been filed under Section 21 of the Consumer Protection Act, 1986 (for short “the Act”) by the Complainants, against the Opposite Party M/s. Ireo Private Ltd. (hereinafter referred to as the ‘Developer’), seeking compensation for delay in handing over the possession of the Flat booked by them in the Project launched by the Developer in the name and style of “SKYON” Golf Course Extension Road, Sector-60 in the revenue estate of Village Ullawas, Tehsil Sohna, District Gurgaon, Haryana, (hereinafter referred to as the Project) within stipulated period.
2. According to the Complainants, the facts of the case are that in response to the Applications invited by the Opposite Party Developer for allotment of flats in their upcoming Project, “SKYON” (hereinafter referred to as the Project) located at Golf Course Extension Road, Sector-60 in the revenue estate of Village Ullawas, Tehsil Sohna, District Gurgaon, Haryana, Mr. Shyam Sundar Sarrof and Mrs. Jyoti Sarrof (hereinafter referred to ‘original allottee’) booked an Apartment in the said Project. They were allotted provisional Apartment No. C-07-4 and an Apartment Buyer’s Agreement (hereinafter referred to as the ‘Agreement’) was executed by them on 23.11.2011. The Complainants purchased the said Apartment from original allottee and got transferred the same in their favor by the Opposite Party Developer on 16.05.2012. It is the say of the Complainants that as per Clause 13.3. of the Agreement, the possession of the Unit was to be handed over within a period of 42 months from the date of approval of the Building Plans. The OP was also entitled for additional 180 days’ grace period for giving the possession of the Unit. Clause 13.3 of the Agreement reads as under:
“Subject to Force Majeure, as defined herein and further subject to the allottee having complied with all its obligations under the terms and conditions of this Agreement and not having defaulted under any provision(s) of this Agreement including but not limited to the timely payment of all dues and charges including the total Sale Consideration, registration charges, stamp duty and other charges and also subject to the Allottee having complied with all formalities or documentation as prescribed by the Company, the Company proposes to offer the possession of the said Apartment to the Allottee within a period of 42 (Forty Two) months from the date of approval of the Building Plans and/or fulfillment of the preconditions imposed thereunder (“Commitment period”). The Allottee further agrees and understands that the Company shall additionally be entitled to a period of 180 days (“Grace period”), after the expiry of the said Commitment Period to allow for unforeseen delays beyond the reasonable control of the Company.”
3. The Complainants made payment of Rs.1,09,92,668/- (Rupees One Crore Nine Lacs Ninety Two Thousand Six Hundered Sixty Eight only), i.e., 95% of the sale consideration, on different dates upto the date of filing of the present Complaint as per demand of the Opposite Party Developer, despite that the Opposite Party Developer failed to deliver the possession of the Unit within stipulated period, i.e., by 22.09.2015. The OP Developer issued Notice of Possession on 06.09.2016 in which false/illegal demand of Rs.15,45,244/- under following distinct heads, was raised:-
| a. Non-Refundable Skyon Club Deposit | Rs.5,00,000/- |
| b. Infra Augmentation Charges (IAC) | Rs.16,459/- |
| c. Labour Cess on Project | Rs.66,995/- |
| d. Applicable carrying cost | Rs.87,386/- |
| e. Interest on Delayed payment, if any | Rs.1,97,030/- |
| f. Internal Gas pipe laying & meter charges | Rs.19,878/- |
| g. Internal electrical charges | Rs.28,270/- |
| h. Service Tax Component, where applicable | Rs.4,99,024/- |
| i. Recovery towards cost on account of Indirect taxes | Rs. |
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.