NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION, NEW DELHI
R.K. Agrawal, President, Dr. S.M. Kantikar, Member and Binoy Kumar, Member
Raghbir Singh – Complainant
versus
M/s. BPTP Limited – Opp. Party
Consumer Case No.835 of 2020
Decided on 11.11.2021
Consumer Protection Act, 1986 – S.21[Consumer Protection Act, 2019 – S.58] – REAL ESTATE – Complaint filed for alleged delay in delivery of possession of flat – Contention raised that delay occurred since Complainant is a habitual defaulter in making payments and therefore there was delay in handing over possession of Unit – Developer as per terms of the Agreement, was at liberty either to charge penal interest on delayed payment or cancel the allotment of the Complainant and refund the amount deposited by him.has not cancelled the booking of the Complainant for default in making payment and refunded the deposited amount. Having not exercised the said option, the BPTP [“Developer”]now cannot take excuse that there was delay in handing over possession due to non-payment by the Complainant. Moreover, the BPTP has charged higher rate of interest for delayed payments by the Complainant. [Para 13]
(ii) Consumer Protection Act, 1986 – S.21[Consumer Protection Act, 2019 – S.58] – REAL ESTATE – Complaint filed for alleged delay in delivery of possession of flat – refund of amount sought – Failure to deliver flat if amounts to unfair trade practise – Complainant cannot be made to wait indefinitely for the delivery of possession and the act of the BPTP in relying on force majeure clause while retaining the amounts deposited by the Complainant, is not only an act of deficiency of service but also amounts to Unfair Trade Practice, especially in light of the view of the fact that the BPTP charges interest @ 18% p.a. for any delay in the payments made by the flat purchasers, but at the same time, offers compensation of Rs.10/- OR Rs.20/- OR Rs.30/-per sq. ft. per month for the delayed possession – Complainant is entitled for refund of the principal amount with reasonable interest. [Para 15]
(iii) Consumer Protection Act, 1986 – S.21[Consumer Protection Act, 2019 – S.58] – REAL ESTATE – Builder Buyer Agreement – validity of terms – on facts, Clauses are extremely unfair and one sided and fall within the definition of ‘Unfair Trade Practice’ as defined under Section 2(r) of the Act – The Appellant-Builder cannot seek to bind the Respondent with such one-sided contractual terms. [Paras 15 to 20]
ORDER
R.K. Agrawal, President.—The present Consumer Complaint has been filed under Section 21 of the Consumer Protection Act, 1986 (for short “the Act”) by Raghbir Singh (hereinafter referred to as the Complainant) against Opposite Party, M/s. BPTP Ltd. (hereinafter referred to as the “BPTP”), seeking refund of the amount deposited by him as the BPTP has failed to hand-over the possession of the residential floor booked by him in terms of the Flat Buyer Agreement.
2. It has been averred in the Complaint that the BPTP has launched a Residential Group Housing Project in the name and style of “Amstoria” located at Sector 102, Gurgaon, Haryana. On 31.08.2011, the Complainant booked a Residential Floor in the said Project. Unit No. A-134-FF on First Floor admeasuring build up area of 1999 sq. ft. was allotted to the Complainant. The Floor Buyers Agreement (hereinafter referred to as the Agreement) was executed between the Parties on 14.03.2012. The total Sales Consideration of the Floor was Rs.85,31,992/-. The Complainant had opted for Construction Linked Payment Plan and had deposited Rs.78,64,819/- on different dates as per demand of the BPTP.
3. As per Clause 5.1 of the Agreement, the possession of the Floor was to be delivered within a period of 24 months from the date of sanctioning of Building Plan or execution of the Agreement with a grace period of 180 days. In the instant case, the Agreement was executed on 14.03.2012 and allowing the grace period of 180 days, the BPTP was under an obligation to hand over the possession of the Floor latest by 13.09.2014.However, despite having received about 92% of the total Sale Consideration, the BPTP miserably failed to deliver the possession of the Floor within stipulated period. It is alleged by the Complainant that the BPTP had utilized his amount in other Projects; most of the clauses in the Agreement were one sided; Complainant was compelled to sign the Agreement which was totally in favour of the BPTP. Whenever the Complainant raised queries with the BPTP regarding the completion of the Project and exact date of handing over the possession, they neither provided any specific date for the delivery of the possession nor refunded the amount deposited by the Complainant. Consequently, the Complainant served a legal notice on BPTP on 29.07.2020 calling upon them to refund along with interest @ 18% and compensation and Costs of proceedings. However, the said notice was not responded to by the BPTP. Alleging deficiency in service and Unfair Trade Practice on the part of the BPTP, the Complainant has filed the present Consumer Complaint seeking a direction to the BPTP to refund the deposited amount with interest @ 18% p.a. and costs of complaint.
4. The BPTP filed its Written Version admitting to the booking, Allotment, Receipt of amount of Rs.78,64,819/- execution of the Agreement dated 14.03.2012 and to Clause 5.1 of the Agreement, wherein they has agreed to deliver the possession of the allotted Apartment within 24 months from the date of execution of the Agreement with six months grace period and this Clause was subject to force majeure conditions.
5. The BPTP has raised the preliminary objections that the Complainant is not a “Consumer” as defined under Section 2 (1) (d) of the Act and is speculative investors as he has invested in the present Project only to gain profits by resale of the Apartment booked by him. It is further stated that the Agreement contains Arbitration Clause and especially after the amendment in Section 8 of the Arbitration and Conciliation Act, 1996, the matter has to be referred to the Arbitrator.
6. On merits, it is also contended that at the time of signing of the Agreement, the Complainant was well aware of the terms and conditions thereof and he has duly agreed to them. The Complainant is not entitled to a reciprocal compensation for the delay in handing over the possession as alleged. In terms of Clause 6 of the Agreement, the Complainant is only entitled
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.