SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION, NEW DELHI
Ram Surat Ram Maurya, Presiding Member
Subrato Bandhu and Anr. – Complainants
versus
Millennia Realtors Private
Limited and Ors. – Opp. Parties
Consumer Case No.3141 of 2017
Decided on 25.1.2022

Counsel for the Parties:
For the Complainants:Mr. Aditya Parolia, Mr. Nithin Chandran, Mr. Sumbul Ismail, Mr. Adithya Ramani and Ms. Parul Singh, Advocates
For the Opp. Party No.1:Ms. Pallavi Sengupta, Advocate
For the Opp. Party Nos.2 and 3: Nemo

Headnote:

Consumer Protection Act, 1986 – S.21(a)[Consumer Protection Act, 2019 – S.58(1)(a)(i)] – Real Estate – Services – Complaints have been filed for alleged delay in possession of flat – Delay due to the reasons beyond the control of the builder and covered under force majeure clause – Whether deficiency of Service can be fastened on builder – There was no deficiency in service on the part of the builder. Whatever delay was caused, it was due to the reasons beyond the control of the builder and covered under force majeure clause. The builder is entitled for extension of that period under the agreement. As such the relieves as claimed in the complaint cannot be granted – Therefore, complaint is disposed of with direction to the builder to supply fresh statement of account to the complainants within one month from the judgment, after adjusting ‘delayed compensation’ giving six weeks further time to the complainants, for taking possession, in accordance with the terms of the agreement. [Para 9].

Held: A combined reading of clauses-9 (a) and 10 (b) of the agreement, it is clear that subject to force majeure, possession had to be delivered till December, 2014 with a grace period of six months. The builder has filed various papers showing that Assistant Executive Engineer, Kodigehalli Sub-Division, Bruhath Bangalore Mahanagara Palike, had illegally stopped the constructions vide notice dated 04.12.2014 and the construction could be resumed only after the order of High Court dated 10.03.2016. Including grace period of six months, the construction was completed in November, 2016 and the builder applied for issue of “Occupation Certificate’ on 16.11.2016 before the competent authority, which was issued on 17.03.2017. The complainants were offered possession, vide letter dated 22.03.2017. In the statement of account supplied along with letter dated 22.03.2017, the builder had adjusted ‘delayed compensation’, according to the agreement.

Result: Complaint disposed of.

ORDER

Ram Surat Ram Maurya, Presiding Member.—Heard Mr. Aditya Parolia, Advocate, for the complainants and Ms. Pallavi Sengupta, for the opposite party-1.

2. Opposite Party-1 has filed IA/3475/2020, on 09.03.2020, for leave to file additional documentary evidence, which is allowed. The documents attached with the application are taken on record.

3. The complainants have filed the aforementioned complaint for directing the opposite parties (hereinafter referred to as the builder) (i) to refund their principal amount of Rs.11900000/- along with interest @18% per annum, from the date of respective deposits till the day of its payment, (ii) to pay Rs.20/- lacs as the compensation, for mental agony and harassment, (iii) Rs.2/- lacs as the cost of the litigation and (iv) any other relief, which is deemed fit and proper in the facts and circumstances of the case.

4. The facts, as stated in the complaint and emerged from the documents attached with it, are that the builder was a company and engaged in business of development and construction of residential and commercial buildings and selling its unit to the prospective buyers. In the year 2012, the builder launched a project of group housing in the name of “RMZ Latitude” at village Hebbal, Kasaba Hobli, Bangalore North Taluka, Karnataka. On coming to know about this project, the complainants booked a 4BHK flat on 30.04.2014 and gave a cheque of Rs.25/- lacs. The builder allotted Unit No. A-702, [tentative super area 3895 sq.ft. + 3 car parking spaces, basic sale price Rs.3.97/- crores, (total sale price of Rs.40931815/-)], Tower No.-A, in the project “RMZ Latitude”. Along with Booking Form, “Payment Plan” was supplied, under which Rs.25/- lacs had to be given at the time of booking, Rs.94.10 lacs at the time of the agreement and remaining amount on completion of construction. The complainants were asked to deposit Rs.94.10 lacs, which was deposited by them on 27.05.2014. However, Agreement to Sell was executed on 09.01.2015. As per clause-9 of the agreement, expected date of possession was 31.12.2014, subject to force majeure clause. Time to time, the complainants inquired about the possession of the flat and the builder gave some assurance for delivery of possession as early as possible. The complainants received a letter of the builder dated 08.06.2015, extending date of delivery of possession till 31.12.2015. The complainants made query about the status of construction. The builder, vide email dated 30.11.2015, informed the position of the construction and that fit out possession would be given from September, 2016. The builder, vide letter dated 31.03.2016, informed that due to restraint order of Assistant Executive Engineer, the construction was stopped for 253 days and now that order had been set aside by High Court and they had resumed the work and it would likely be completed till the end of December, 2016 to March, 2017. The builder again vide emails dated 19.04.2016 and 02.05.2016, informed that they would be able to give fit out possession till the end of December, 2016 to March, 2017. The complainants, vide emails dated 31.08.2016 and 07.09.2016, requested for return of their money. The builder did not respond. The complainants then gave legal notice dated 01.10.2016, terminating the agreement and demanding refund along with interest, damages etc. Then a meeting was held between the complainants and the officers of the builder. In that meeting, the complainants were informed that the construction had been completed and the builder had applied for “Occupation Certificate” and they were assured that after receiving “Occupation Certificate”, the builder would arrange a new buyer of the flat and the money would be returned to the complainants. The builder obtained “Occupation Certificate” on 17.03.2017 and vide letter dated 22.03.2017, offered possession to the complainants. The complainants, vide application dated 11.06.2017, referred the dispute to District Legal Services A

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top