Gujarat High Court
Judgename :J.R.Vora, M.R.CALLA
State of Gujarat - Appellant
Versus
Vanmalibhai Kalidas Hajari - Respondent
C.A. 6593 of 1998
Decided On : 07/28/1998
On the date when the time barred Letters Patent Appeals were filed, they were not accompanied with any application for condonation of delay . Concerned Department and the officers never took the matter seriously and despite the decision taken by the concerned Secretary in March, 1998 and instructions issued by him to file appeals, the matter was taken from pillar to post in the Department. The contents of the applications seeking condonation of delay make it clear that it is a case of callous negligence and inaction on the part of the concerned officers and it is hardly a case in which it can be said that the applicants were prevented by any reasonable and sufficient cause from filing the appeals within time. Not only that, the appeals on the date when they were filed, were time barred by 171 days.
[Para 4]
( 1 ) THE learned Single Judge decided Special Civil Application Nos. 8102, 8103, 6594, 6595, 6596, 6597, 6598, 6599, 7536, 7608, 10320, 10321, 10322 and 10323 of 1995 by a common judgment and order dated 21. 10. 1997. One Dahyabhai Vestabhai, owner of land bearing survey No. 378/1 situated at village Dumas divided the said land into 48 plots. He applied for permission to sell these sub plots to make use thereof for non-agricultural purposes to the Assistant Collector, Olpad Prant, Surat under Sec. 63 of the Bombay Tenancy and Agricultural Lands Act, 1948. The concerned Assistant collector vide his order dated 29th April, 1967 granted permission to the holder of the aforesaid land with certain conditions inter alia to make use of sub-plots for non-agricultural purpose by transferring within two years from the date of the order. On 20th May, 1967, the owner of the land sold out the sub-plots to 48 persons including the petitioners in the present cases by registered sald deeds. Under the Town Planning scheme as was published on 23rd December, 1969, the land in question was put under reservation for the purpose of extension of aerodrome for civil aviation and transport. The purchasers-petitioners took certain steps for extension of time limit by the Assistant collector and also moved applications under the Bombay Land Revenue Code for non-agricultural permission. The permission was declined by the Taluka Development officer on 18th June, 1971. Appeals against this order dated 18th June, 1971 were also dismissed. The State Government vide letter dated 20th April, 1981, issued direction that the permission to sell all the sub-plots should be treated as automatically cancelled. The concerned Mamlatdar ordered for entering the names of the original owner in the revenue record in respect of the land in dispute. Though the petitioners raised grievance that this order had been passed without giving an opportunity to them while their names have been entred in the revenue records in the year 1969-70 and the entry with regard to their names continued in the revenue records, the concerned Mamlatdar ultimately passed order dated 21st October, 1993 entering the names of the original owner in the revenue records. This gave rise to the filing of the Special Civil Applications as aforesaid.
( 2 ) LEARNED Single Judge found that it was not necessary to consider the various contentions because in his opinion, the matter was required to be considered by a High power Committee of the State Government after hearing the parties concerned. Accordingly, the State of Gujarat has been directed to constitute a three member committee under the Chairmanship of the Chief Secretary to decide the controversy after hearing all the parties concerned i. e. , purchasers-petitioners, original owner of the land, surat Municipal Corporation, Surat Urban Development Authority and Airport Authority of India, New Delhi through its representative at Surat and this Committee has to decide after hearing all the parties as to whether the land in question has to be reserved for the public purpose i. e. , for extension of the aerodrome for civil aviation and transport and if at all it is decided to reserve for such purpose, necessary decision has to be taken then and there to acquire the land and to see that acquisition proceedings are completed within reasonable time, and if the Committee decides that this land is not required to be reserved for the aforesaid purpose, necssary decision is to be taken for grant of permission for construction of house by the petitioners on the land in dispute. This exercise has to be undertaken and completed within a period of nine months from the date of receipt of the order. All the parties have been directed to maintain status quo in respect of the land in dispute till the matter is decided by the Government and liberty has been granted to the petitioners for revival of the Special Civil Applications in case of difficulty and
SupremeToday
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.