SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2011 Supreme(Guj) 18

2011 (1) GCD 402 (SC)
Hon’ble Mr. Justice P. Sathasivam &
Hon’ble Mr. Justice Dr. B.S. Chauhan
R.L. Kalathia & Co.
Versus
State of Gujarat
Civil Appeal No. 3245 of 2003—Decided on 14/01/2011

Point in Issue :
Whether plaintiff is entitled to claim for additional and altered work after acceptance of final bill and payment.

Headnote:Head Note :

       Government Contracts — Works contract — Acceptance of final bill and full payment — Subsequent claim for additional or altered works — Dismissal of claim as barred by principle of estoppel and non-suiting the plaintiff — Held, not sustainable, if the party is able to establish that it was entitled to further amount for which he has adequate material — It’s claim can not be held barred merely because, he has accepted payment of final bill by mentioning without prejudice — Court agreed with the conclusion arrived at by trial Court and held plaintiff entitled to the amount decreed by it — In the result Court restored the decree and judgment of trial Court and set aside the judgment and decree of High Court in appeal.

       Held :

       It is true that when the final bill was submitted, the plaintiff had accepted the amount as mentioned in the final bill but “under protest”. It is also the specific claim of the plaintiff that on the direction of the Department, it had performed additional work and hence entitled for additional amount/damages as per the terms of agreement. Merely because the plaintiff had accepted the final bill, it cannot be deprived of its right to claim damages if it had incurred additional amount and able to prove the same by acceptable materials. [Para 5]

       Law Laid Down :

       Even after execution of full and final discharge if the party establish that he is entitled to further amount, he is not barred from claiming such amount merely because of acceptance of payment of final bill mentioning without prejudice.

       Case Law Analysis :

       Chairman and MD, NTPC Ltd. vs. Reshmi Constructions, Builders & Contractors, (2004) 2 SSC 663 [Para 6];; Ambica Construction vs. Union of India, (2006) 13 SCC 475 [Para 7];; National Insurance Company Limited vs. Boghara Polyfab Private Ltd., (2009) 1 SCC 267 [Para 8].—Relied on

Judgment

P. Sathasivam, J.—This appeal is directed against the judgment and final order dated 07.10.2002 passed by the Division Bench of the High Court of Gujarat whereby the High Court set aside the judgment and decree dated 14.12.1982 passed by the Civil Judge, (S.D.), Jamnagar directing the State Government to pay a sum of Rs. 2,27,758/- with costs and interest and dismissed the Civil Suit as well as cross objections filed by the appellant-Firm for recovery of the aggregate amount of Rs. 3,66,538.05 on account of different counts as specified in the claim of the said suit.

2. Brief facts:

(a) The appellant-Firm, a partnership firm registered under The Indian Partnership Act, is carrying on the business of construction of roads, buildings, dams etc. mostly in Saurashtra and also in other parts of the State of Gujarat. In response to the invitation of tender by the State Government for construction of Fulzer Dam II in Jamnagar District, the appellant-Firm quoted and offered to construct the same for the quotation, specifications and design of the Dam vide covering letter dated 05.06.1970. In the said letter, the appellant-Firm also offered that they would give rebate of 3/4% provided the final bill be paid within three months from the date of completion of the work. The offer of the appellant being the lowest amongst other parties, it was accepted by the State Government with the clause that the construction work was to be completed within a period of 24 months from the works order dated 07.09.1970 which was subsequently clarified that the period of 24 months was to be commenced from the date of commencement of work i.e., 29.11.1970.

(b) During execution of the said work, the Executive Engineer, who was in-charge of the project, made certain additions, alterations and variations in respect of certain items of work and directed the appellant to carry out additional and alteration work as specified in writing from time to time. The final decision as to the alteration in respect of certain items of work and particularly, in respect of the depth of foundation which is known as cut off trenches (COT) took long time with the result that the Firm was required to attend the larger quantity of work and thus entitled for extra payment for the additional work. As per the works contract, the Firm was not paid the running bill within the specified time and, therefore, suffered loss.

(c) On 16.07.1976, the Firm lodged a consolidated statement of their claims for the additional or altered works etc. to the Executive Engineer. As there was no response, the Firm served a statutory notice dated 04.01.1977 under Section 80 of the Code of Civil Procedure (hereinafter referred to as ‘the Code’). Again, on 24.03.1977, after getting no reply, the Firm filed Civil Suit No. 30 of 1977 on the file of the Civil Judge (S.D.), Jamnagar praying for a decree of the aggregate amount of Rs. 3,66,538.05 with running interest at the rate of 9% p.a. from the date of final bill till the date of Suit and at the rate which may be awarded by the Court from the date of Suit till payment. Vide order dated 14.12.1982, the Civil Judge allowed the suit and passed a decree for a sum of Rs. 2,27,758/- with proportionate costs together with interest @ 6% p.a. from the date of suit till realization.

(d) Being aggrieved by the said judgment and decree, the State Government filed First Appeal No. 2038 of 1983 before the High Court of Gujarat at Ahmedabad. The Division Bench of the High Court, vide its order dated 07.10.2002, allowed the appeal of the State Government and dismissed the suit of the appellant-Firm and also directed that the decretal amount deposited by the State Government and as permitted to be withdrawn by the Firm should be refunded within a period of four months from the date of the judgment. Being aggrieved by the said judgment, the appellant-Firm has filed this appeal by way of special leave petition before this Court.

3. Heard Mr. Altaf Ahmed, learned senior Co

















































Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

SupremeToday

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top