2013 Supreme(Guj) 765

IN THE HIGH COURT OF GUJARAT
Rajesh H. Shukla, J.
Indian Oil Corporation Ltd - Petitioner
Versus
Collector of Electricity Duty & Anr. - Respondents
Special Civil Application No. 5177 of 2005
Decided On : 19-07-2013

Subject

Taxation Law - Electricity Duty

Act Referred

BOMBAY ELECTRICITY DUTY ACT : S.2(bb), S.2(ee)
CONSTITUTION OF INDIA : Art.12, Art.14, Art.19(1)(g), Art.226
ELECTRICITY ACT : S.24(2)
ELECTRICITY DUTY ACT : S.2(bb)
FACTORIES ACT : S.2(k)

Headnote

Constitution of India,1950 - Articles 12, 14, 19(1)(g) & 226 - Petitioner is a Company incorporated under the Companies Act, 1956 and is a Government of India Undertaking and Petitioner Company is engaged in business of petroleum products and carry petroleum products to various parts of the country, including through pipeline - Notice for disconnection of electric supply on the ground that the petitioner cannot be treated as "Industrial Undertaking" as defined under Section 2(bb) of the Bombay Electricity Duty Act, and therefore, is liable to make the payment, which has lead to filing of the present petition - Appeal - Held, Impugned supplementary bill and notice under Section 24 of the Electricity Duty Act, 1910 and also the order passed by the Respondent No.1 dated 18.3.2005 are hereby quashed and set aside - The Respondent is restrained from disconnecting the supply for the recovery of the supplementary bill - However, it will be open for the Respondent authorities to claim the amount of energy as per the rate charged on 'Industrial Undertaking'. Rule is made absolute - After the order was pronounced, learned AGP has requested that the operation of the order may be stayed to enable him to take recourse before the higher forum. Permission as prayed for is granted - Operation of this order is stayed up to 26th August 2013 - Petition allowed.

Facts of the case:

Petitioner is a Company incorporated under the Companies Act, 1956 and is a Government of India Undertaking and Petitioner Company is engaged in business of petroleum products and carry petroleum products to various parts of the country, including through pipeline - Notice for disconnection of electric supply on the ground that the petitioner cannot be treated as "Industrial Undertaking" as defined under Section 2(bb) of the Bombay Electricity Duty Act, and therefore, is liable to make the payment, which has lead to filing of the present petition.

Findings of the case:

Impugned supplementary bill and notice under Section 24 of the Electricity Duty Act, 1910 and also the order passed by the Respondent No.1 dated 18.3.2005 are hereby quashed and set aside - The Respondent is restrained from disconnecting the supply for the recovery of the supplementary bill - However, it will be open for the Respondent authorities to claim the amount of energy as per the rate charged on 'Industrial Undertaking'. Rule is made absolute - After the order was pronounced, learned AGP has requested that the operation of the order may be stayed to enable him to take recourse before the higher forum. Permission as prayed for is granted - Operation of this order is stayed up to 26th August 2013

Result:

Petition allowed

Advocates Appeared:
For the Petitioner:Shri. M.R. Bhatt, LD. Senior Advocate With Mauna M Bhatt, Advocate
For the Respondent:Shri. Bipin Bhatt, AGP., Mr. M.D. Pandya, Advocate.

JUDGMENT :

Rajesh H. Shukla, J.

The present petition has been filed by the petitioner - Indian Oil Corporation Ltd. under Articles 12, 14, 19(1)(g) & 226 of the Constitution of India as well as under the Indian Electricity Act, 1910 and also under the Electricity Act, 2003 read with Bombay Electricity Duty Act, 1958 for the prayers:

“(A) this Hon'ble Court may be pleased to issue a Writ or Certiorari or a Writ in the nature of Certiorari or any other appropriate writ, order or direction, quashing and setting aside the supplementary bill dated 22.2.2005, notice u/s. 24 of the Indian Electricity Act, 1910 dated 15.3.2005 and the order dated 18.3.2005 passed by the respondent no.1;

(B) this Hon'ble Court may be pleased to hold and declare that the respondents are not entitled in law and on facts to issue the impugned supplementary bill by treating the petitioner’s undertaking as a “service undertaking”

(C) pending admission, hearing and final disposal of this petition, this Hon'ble Court may be pleased to restrain the respondents, their agents, subordinates from effecting any coercive recovery in respect of the supplementary bill dated 22.2.2005 and they may be restrained from dis-connecting the electricity supply to the petitioner’s pump station at Jamnagar bearing Consumer No.27125;

(D).....

(E).....”

2. The facts of the case briefly stated are that the petitioner is a Company incorporated under the Companies Act, 1956 and is a Government of India Undertaking. The Petitioner Company is engaged in business of petroleum products and carry petroleum products to various parts of the country, including through pipeline. It is stated that Salaya - Mathura Pipeline is one of such pipeline of the petitioner undertaking. It is the case of the petitioner that an agreement has been entered into between the Respondent no.2-GEB and the petitioner for supply of electrical energy of 350 KVA for the purpose of pump station at Jamnagar and as per the agreement, the petitioner is billed as per tariff schedule applicable to HTP-I. It is the case of the petitioner that though it is an “Industrial Undertaking”, the Respondent No.1 has addressed a letter for charging the electricity duty applicable to “Service Undertaking”. It is stated that the Jamnagar installation is one such boosting station of Salaya - Mathura pipeline and the crude oil is pumped from different points to Mathura refinery, and therefore, the pumping station is a part of the manufacturing unit. However, the Respondent No.2 has addressed a notice for disconnection of electric supply on the ground that the petitioner cannot be treated as “Industrial Undertaking” as defined under Section 2(bb) of the Bombay Electricity Duty Act, and therefore, is liable to make the payment, which has lead to filing of the present petition.

3. Heard learned Senior Counsel Shri. M.R. Bhatt for M/s M.R. Bhatt & Co. for the petitioner and learned AGP Shri. Bipin Bhatt for Respondent No.1 and learned Advocate Shri. M.D. Pandya for Respondent No.2.

4. Learned Senior Counsel Shri. M.R. Bhatt referred to the background of the facts and submitted that the petitioner Company has been given the bills for HTP-I, meaning thereby, as an “Industrial Undertaking”. He further submitted that the supply of the crude oil for carrying in the pipeline from Salaya to Mathura is part of the manufacturing process, and therefore, it would be an “Industrial Undertaking”. He submitted that in fact the petitioner company has been registered under the Factories Act and the license has also been issued. Similarly, he has referred to a license to import and store. He has also referred to the certificate of Gujarat Pollution Control Board, which also referred to the unit as a Industrial Plant. He has also referred to the bills issued by the Respondent No.2 for the purpose of tariff category of HTP-I. Learned Senior Counsel Shri Bhatt therefore submitted that the petitioner is a “Industrial Undertaking” and cannot be termed as “Service Undert

1
2
3
4