2020 Supreme(Guj) 524

IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
Vikram Nath, Ashutosh J. Shastri, JJ.
Jitf Water Infrastructure Limited – Appellant
Versus
Msme Commissionerate – Respondent
R/Letters Patent Appeal No. 1667 of 2019 In R/Special Civil Application No. 11169 of 2018 With Civil Application (For Stay) No. 1 of 2019
Decided On : 24-07-2020

Advocates:
Advocate Appeared:
For the Appellant :Mr H M Parikh, Senior Advocate Assisted By Mr Rasesh H Parikh, Mr Hemang H Parikh
For the Respondent: Mr G M Amin, Mr Mitul Shelat With Mr Rutul P Desai, Mr Akash Chhaya, AGP

Point of Law:
Single Bench is perverse, it shall not disturb the same. Merely because another view or a better view is possible, there should be no interference with or disturbance of the order passed by the Single Judge, unless both sides agree for a fairer approach on relief.

Headnote:

Letters Patent Appeal – Clause 15 – Companies Act, 1956 – Micro, Small and Medium Enterprises Development Act, 2006 – Section 18(1) – Arbitration and Conciliation Act, 1996 – Section 76 – Contract and Specific Relief – Termination of Contract and Termination of conciliation – Seeking to quashing and setting aside the impugned order passed by the Respondent No.1 and pleased to grant stay of operation, execution and implementation of the impugned order – According to petitioner, JV delayed the execution and work which was duly intimated to it by the petitioner by dozens of communications right from 29.03.2017 till 22.12.2017 – When despite such notices the JV failed to rectify and to maintain the pace of work as required under work order, petitioner vide notice (sent by email) exercising the rights available under the contract, terminated the contract – Held, There is one more reason for dismissing the appeal i.e. Section 16 of the 1996 Act – Above provision gives ample power to the Arbitrator to decide all objections, including objections relating to its own jurisdiction. Law as by now is well settled and we need not further burden this order by referring to the case laws – Management of Narendra & Company Private Limited (supra) it has been clearly laid down that the appellant Bench may not interfere with the findings of learned Single Judge where the learned Single Judge has dealt with in detail the arguments advanced by counsel for the parties and also recorded finding which cannot be said to be perverse, appellate Bench will refrain its hands from interfering with the judgment of learned Single Judge – Council would not have any option left but to refer it to the institution or center providing alternate dispute resolution services for carrying out matter further in accordance with provisions of 1996 Act – We also find that the learned Single Judge in above backdrop rightly dismissed writ petition – We may also record that the finding recorded by learned Single Judge can be held to be clearly a possible view – Nothing has been shown to even remotely indicate that finding recorded by the learned Single Judge is either perverse in any manner or that it cannot be sustained in law – Appeal dismissed.(Paras 32, 33 and 34)

Facts of the case:

Petitioner company entered into an agreement with M/s. Aquafil - Wintech JV [hereinafter referred to as `the JV’], a joint venture of M/s. Acquafil Polymers Company Private Limited (Respondent No.2) and M/s. Wintech Engineering Private Ltd. in respect of the work order on turnkey basis. The work related to procurement of Design, Supply, Installation and Commissioning of Intake Facilities, Transmission Mains, Water Treatment Plant and Reservoir for North Zone including 5 years of operation and Maintenance of JICA funded Guwahati Water Supply Project – Completion period of the contract for the work other than Operation and Maintenance service was 28 months from date of commencement and thereafter JV was obliged to render Operation and Maintenance service for 5 years – Total contract value was Rs.79.47 Crores for E.P.C. and Operation and Maintenance – According to petitioner, JV delayed the execution and work which was duly intimated to it by the petitioner by dozens of communications right from 29.03.2017 till 22.12.2017 – When despite such notices the JV failed to rectify and to maintain the pace of work as required under work order, petitioner vide notice (sent by email on 09.01.2018) exercising the rights available under the contract, terminated the contract.

Findings of the court:

There is one more reason for dismissing the appeal i.e. Section 16 of the 1996 Act – Above provision gives ample power to the Arbitrator to decide all objections, including objections relating to its own jurisdiction. Law as by now is well settled and we need not further burden this order by referring to the case laws – Management of Narendra & Company Private Limited (supra) it has been clearly laid down that the appellant Bench may not interfere with the findings of learned Single Judge where the learned Single Judge has dealt with in detail the arguments advanced by counsel for the parties and also recorded finding which cannot be said to be perverse, appellate Bench will refrain its hands from interfering with the judgment of learned Single Judge – Council would not have any option left but to refer it to the institution or center providing alternate dispute resolution services for carrying out matter further in accordance with provisions of 1996 Act – We also find that the learned Single Judge in above backdrop rightly dismissed writ petition – We may also record that the finding recorded by learned Single Judge can be held to be clearly a possible view – Nothing has been shown to even remotely indicate that finding recorded by the learned Single Judge is either perverse in any manner or that it cannot be sustained in law.

Result: Appeal dismissed

JUDGMENT :

VIKRAM NATH, J.

1. The present appeal under clause 15 of the Letters Patent has been preferred assailing the correctness of the judgment and order dated 09.09.2019 passed by the learned Single Judge in Special Civil Application No.11169 of 2018 whereby the writ petition filed by the present appellant has been dismissed.

2. The present appellant viz. JITF Water Infrastructure Ltd., a company incorporated under the Companies Act, 1956, filed Special Civil Application No.11169 of 2018 praying for the following reliefs:-

“[A] Admit this writ petition;

[B] Allow this writ petition by quashing and setting aside the impugned order dated 30.06.2018 passed by the Respondent No.1 (Annexure `A’);

[C] Pending admission hearing and till final disposal of the present writ petition, Your Lordships may be pleased to grant stay of operation, execution and implementation of the impugned order dated 30.06.2018;”

3. Before proceedings to deal with the matter on its merits, basic facts relevant for the purpose are stated hereunder :-

3.1 The petitioner company entered into an agreement with M/s. Aquafil - Wintech JV [hereinafter referred to as `the JV’], a joint venture of M/s. Acquafil Polymers Company Private Limited (Respondent No.2) and M/s. Wintech Engineering Private Ltd. in respect of the work order dated 08.08.2014 on turnkey basis. The work related to procurement of Design, Supply, Installation and Commissioning of Intake Facilities, Transmission Mains, Water Treatment Plant and Reservoir for North Zone including 5 years of operation and Maintenance of JICA funded Guwahati Water Supply Project. The completion period of the contract for the work other than Operation and Maintenance service was 28 months from the date of commencement and thereafter the JV was obliged to render Operation and Maintenance service for 5 years. The total contract value was Rs.79.47 Crores for E.P.C. and Operation and Maintenance. According to the petitioner, the JV delayed the execution and work which was duly intimated to it by the petitioner by dozens of communications right from 29.03.2017 till 22.12.2017. When despite such notices the JV failed to rectify and to maintain the pace of work as required under the work order, the petitioner vide notice dated 08.01.2018 (sent by email on 09.01.2018) exercising the rights available under the contract, terminated the contract.

3.2 The JV thereafter vide communication dated 08.02.2018 invoked the arbitration clause as per terms of the contract contained in clause 20.3 and proposed the name of the Arbitrator also as the Sole Arbitrator to adjudicate the dispute.

3.3 In response to the invocation of the arbitration clause by the JV, the petitioner vide communication dated 14.02.2018 refuted all the alleged contentions. It also stated in the above communication that, the authority to appoint the arbitrator vested in the petitioner and not the JV. Later on, the petitioner vide letter dated 26.02.2018 appointed Justice A.K. Patnaik as the Sole Arbitrator to adjudicate the dispute. The learned Arbitrator Justice A.K. Patnaik, appointed by the petitioner, vide notice dated 12.03.2018, directed the parties to appear on 30.03.2018 for preliminary hearing.

3.4 On 24.03.2018 before the first date of hearing fixed by the Arbitrator Justice Patnaik, the JV informed the petitioner that it would approach the MSME Commissionerate with respect to its claims as per the mandate of The Micro, Small and Medium Enterprises Development Act, 2006 [hereinafter referred to as, `2006 Act’]. In response, the petitioner vide letter dated 30.03.2018 refuted the contentions of JV on several grounds, including the ground that as the JV is not registered as a Micro or Small or Medium Enterprise, as such it could not invoke the provisions of 2006 Act.

3.5 The MSME Commissionerate vide notice dated 10.04.2018 communicated to the petitioner to submit reply within 15 days to the application filed by M/s. Acquafil Polymers Company Pvt. Ltd. (respondent N