IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
J.B. PARDIWALA, VAIBHAVI D. NANAVATI, JJ.
Silver Touch Technologies Limited – Petitioner
Versus
Oil and Natural Gas Corporation Limited – Respondent
Special Civil Application No. 5434 of 2021
Decided On : 26-08-2021
Constitution of India,1950 – Article 12,14 and 226 - Companies Act, 1956 – Bidding - Financial bids - Writ-applicant is a company incorporated under provisions of Companies Act, 1956 and is engaged in the business of Software Services System Integration, E-Governance Solutions and Digital Transformation - It appears that respondent-O.N.G.C. invited bids for supply, installation and commissioning of seven high-end workstations with three years warranty vide Tender - It is not in dispute that upon opening of financial bids, price offered by writ-applicants was found to be lowest - However, a controversy cropped up as regards Price Bid Format - Confusion that arose was whether rates were to be submitted per unit or for all seven units - It appears that during meeting convened date on which, financial bids were opened, it was sought to be clarified on behalf of writ-applicants before O.N.G.C. that rates quoted by them were on per unit basis - A letter was addressed by O.N.G.C. awarding the contract in favor of writ-applicants for a total price - Whether they have quoted various price elements in price bid or not.
Finding of the court : It appears that the Corporation thought fit to invoke Clause of “warranty and guarantee” and decided to take necessary action to blacklist the writ-applicants - Aforesaid may empower Corporation court of view that mere delay in execution of order or non-execution of order without anything more by itself may not be sufficient to entail consequences of being blacklisted - Even in a case of delay in execution of order or non-execution of order or failure to honor commitments, Corporation as a State within the Article 12 of Constitution is obliged to consider circumstances that might have led to such delay or failure - Without considering same, it would not be proper for Corporation to straightway blacklist a Contractor – Court are taking such view in the facts of the present case - Court observations should not be construed as laying a straight-jacket formula - Thus, having regard to the aforesaid discussion, court have reached to conclusion that decision of Corporation to blacklist writ-applicants does not appear to be just, proper or reasonable, applying the doctrine of proportionality as discussed.
Result: Writ-application allowed.
JUDGMENT :
J.B. PARDIWALA, J.
1. By this writ-application under Article 226 of the Constitution of India, the writ-applicants have prayed for the following reliefs:
(B) Be pleased to issue a writ of mandamus, or a writ in the nature of mandamus or any other appropriate writ, order and/or direction quashing and setting aside the inquiry conducted against the petitioner company vide show cause notice dated 17th July 2020 (Annexure J hereto), in the interest of justice.
(C) Pending the admission, hearing and final disposal of the present petition, be pleased to grant stay over the implementation and execution of the impugned order dated 23rd November, 2020 (Annexure A hereto) passed by the Respondent, imposing a ban on the petitioner in the interest of justice.
(D) An ex-parte ad-interim relief in terms of prayer C above may kindly be granted.
(E) Be pleased to pass any other and further orders or reliefs as may be deemed fit in the facts and circumstances of the case in the interest of justice.”
2. The facts giving rise to this litigation may be summarized as under:
2.2 It appears that in August, 2019, the respondent-O.N.G.C. invited bids for the supply, installation and commissioning of seven high-end workstations with three years warranty vide the Tender No. D-31KC-19011. The period prescribed was from 23rd August, 2019 to 17th September, 2019.
2.3 It is not in dispute that upon opening of the financial bids, the price offered by the writ-applicants was found to be the lowest. However, a controversy cropped up as regards the Price Bid Format. The confusion that arose was whether the rates were to be submitted per unit or for all the seven units.
2.4 It appears that during the meeting convened on 05.11.2019 i.e. the date on which, the financial bids were opened, it was sought to be clarified on behalf of the writ-applicants before the O.N.G.C. that the rates quoted by them were on per unit basis. A letter was addressed by the O.N.G.C. dated 27.11.2019 awarding the contract in favour of the writ-applicants for a total price of Rs. 8,85,927/- [which was the unit price quoted by the writ-applicants].
2.5 The aforesaid was a rate quoted by the writ-applicants of a single unit and not the total price of the entire contract. From this point of time, the disputes arose between the parties.
2.6 It is also not in dispute that ultimately, the contract which was awarded in favour of the writ-applicants came to be cancelled and the O.N.G.C. had to issue a fresh tender notice.
2.7 The subject matter of challenge in the present writ-application is not the order cancelling or terminating the contract. The subject matter of challenge is the order passed by the O.N.G.C. blacklisting the writ-applicants for a period of six months. This period of six months has also expired. However, the writ-applicants want to pursue this litigation as according to them, if the order of blacklisting remains, then it would be a blemish on them for all times to come. In such circumstances, we are called upon to examine the legality and validity of the order passed by the O.N.G.C. blacklisting the writ-applicants.
2.8 We first start with the tender conditions. The condition no. 33.0 provides for putting the supplier on holiday on account of cancellation of the purchase order. Co
Ajay Hasia and Others vs. Khalid Mujib Sehravardi and Others
B.S.N. Joshi and Sons Ltd. vs. Nair Coal Services Ltd. and Others
Erusian Equipment and Chemicals Ltd. vs. State of West Bengal
E.P. Royappa vs. State of Tamil Nadu
G.B. Mahajan vs. Jalgaon Municipal Council
Gohil Vishvaraj Hanubhai and Others vs. State of Gujarat and Others
Indian Express Newspapers (Bombay) (P) Ltd. vs. Union of India
Joseph Vilangandan vs. The Executive Engineer, (PWD) Ernakulam and Others
M/s Southern Painters vs. Fertilizers and Chemicals Travancore Ltd. and Another
M/s. Kulja Industries Limited vs. Chief General Manager, W.T. Project, BSNL and Others
Maneka Gandhi vs. Union of India and Another
M.R.F. Ltd. vs. State of Kerala
Mohd. Hanif Quareshi vs. State of Bihar
Modern Dental College and Research Centre vs. State of M.P. (2016) 7 SCC 353
M/s Mahabir Auto Stores and Others vs. Indian Oil Corporation Ltd. (1990) 3 SCC 752
Miss Radha Krishna Agarwal and Others vs. State of Bihar and Others
Om Kumar and Others vs. Union of India
P.P. Enterprises vs. Union of India
Patel Engineering Ltd. vs. Union of India
R. vs. Ministry of Defence, Ex p Smith
Radhakrishna Agarwal and Others vs. State of Bihar and Others
R.D. Shetty vs. International Airport Authority of India and Others
Supreme Court Employees' Welfare Assn. vs. Union of India
Tata Cellular vs. Union of India
U.P. Financial Corporation vs. Gem Cap (India) (P) Ltd. (1993) 2 SCC 299
VET India Pharamaceuticals Limited vs. State of U.P. and Another
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.