IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
J.C. Doshi, J.
Dakshin Gujarat Vij Company Limited Thru Its Executive Engineer - Appellant
Versus
Garrison Polysacks Pvt.Ltd. – Defendant
R/First Appeal No. 2938 of 2004 With R/First Appeal No. 2939 of 2004
Decided On : 23-06-2026

Important Points

Disputes regarding the correctness of an electricity meter and subsequent estimations of consumption fall under the exclusive jurisdiction of the statutory electrical authority. Furthermore, courts must strictly adhere to the parties' pleadings and cannot grant reliefs not specifically sought, as doing so violates procedural fairness.

Subject

Electricity Law - Meter Disputes and Procedural Law

Act Referred

CIVIL PROCEDURE CODE : O.7 R.11(a), S.96
ELECTRICITY ACT : S.26(6)

Headnote

(A) Electricity Act, 1910 - Section 26(6) - Meter dispute - Exclusive jurisdiction of Electrical Inspector - Quantification of energy loss and determination of meter status rest solely with the statutory authority - Electricity company acted unilaterally in issuing a supplementary bill without adhering to the mandatory reference mechanism for determining meter accuracy, thereby failing to establish a valid claim for recovery of charges. (Paras 13, 14, 15)

(B) Civil Procedure Code - Order 7 Rule 11 - Scope of relief - Doctrine of pleadings - Relief not specifically prayed for in the plaint cannot be granted by the Court - Granting a declaratory decree in a suit for perpetual injunction without an amendment to the pleadings constitutes a miscarriage of justice and violates the rights of the respondent to effectively resist such claims. (Paras 9, 10, 11, 12)

Facts of the case:
An electricity supply company discovered a discrepancy in a consumer's meter, alleging it ran slow, and subsequently issued a supplementary bill. The consumer filed a suit seeking a perpetual injunction to prevent disconnection. The supplier filed a separate suit for recovery of the alleged under-charged amount. The trial court decided both suits through a common judgment, dismissing the recovery suit and decreeing the consumer’s suit, granting a declaration that the supplementary bill was illegal, despite such relief never being prayed for. The trial court also rejected requests by the supplier to involve the statutory expert authority for meter testing.

Findings of Court:
It was held that the trial court committed a manifest error by failing to refer the meter dispute to the designated statutory authority as required by law. Furthermore, the trial court bypassed procedural fairness by granting extensive relief that was not sought in the initial pleadings. The adjudication of the meter’s accuracy and subsequent billing without the statutory authority's determination is procedurally flawed.

Issues: Whether the trial court erred in granting relief beyond the pleadings and whether the assessment of meter inaccuracy and final billing can be performed by the supplier without an expert determination by the statutory authority.

Ratio Decidendi: Disputes concerning the functionality of electricity meters must be resolve by the designated statutory electrical expert to ensure impartiality and technical accuracy. Additionally, a court must confine its relief to the issues and prayers raised in the pleadings to ensure that no party is prejudiced by a lack of opportunity to defend against un-pleaded claims.

Result: Appeals allowed; trial court judgment set aside; cases remanded back for fresh consideration in accordance with law.

Advocates Appeared:
For the Appellant : Mr Chinmay M Gandhi, Ms Rumi M Gandhi
For the Defendant : Mr Chaitanya S Joshi

Table of Content
1. factual history of the electricity meter dispute and the initial trial court's common judgment. (Para 1 , 3 , 4)
2. parties' contentions regarding the scope of section 26(6) of the indian electricity act vs. authority of the licensee. (Para 6 , 7)
3. the court's analysis on granting relief exceeding the scope of the original pleadings. (Para 9 , 10 , 11 , 12)
4. application of section 26(6) jurisdiction concerning meter slowness and the necessity of referring disputes to an electrical inspector. (Para 13 , 14 , 15 , 16)
5. court's decision to remand for trial due to inconsistent prior findings and procedural errors. (Para 17 , 18 , 19)

JUDGMENT: 

J. C. DOSHI, J.

1. The learned 3rd Senior Civil Judge, Bharuch by its impugned judgment and decree dated 18.11.2003 decided Special Civil Suit No.150 of 1997 filed by erstwhile Gujarat Electricity Board (for short, ‘G.E.B’) and now Dakshin Gujarat Vij Company Limited (for short, ‘DGVCL’) and Special Civil Suit No.195 of 1994 filed by M/s. Garrison Polysacks Private Limited (for short, ‘the Company’) by common judgment and decree, whereby the former suit was dismissed and latter was decreed. The supplementary bill issued by the DGVCL in tune of Rs.8,37,153.14/- is declared arbitrarily illegal and void and the suit for recovery of the said supplementary bill is dismissed.

2. The aforesaid captioned appeals have been preferred by DGVCL under Section 96 of the Code of Civil Procedure, 1908 (for short, ‘CPC’) to question the legality and merit of the impugned judgment and decree. In view of that, I propose to decide the captioned appeals by this common judgment.

3. Facts of the case are as follow:

3.1 M/s. Garrison Polysacks Private Limited (for short, ‘the Company’) urged DGVCL to release the electricity connection. Consequently, the DGVCL (erstwhile ‘G.E.B’) released the electricity connection in favour of the complainant on 1st January, 1992 for customer no.1039. This electricity connection was listed under the rules and regulations of the erstwhile G.E.B and on 21st April, 1994, the surveillance squad of G.E.B had made surprise checking at the Company’s electrical installation and tested the electricity meter installed at the Company’s premises with trivkometer and subsequent thereto prepared a checking report E-0405 and E-0443. The electricity company found that the electricity meter installed at the Company’s premises was running slow. Thus, the L.T. meter was installed on 4th July, 1994 to check the slowness of the meter. Then, subsequently on 7th July, 1994, HT and LT installations were checked by the checking squad and found that the electricity meter installed at the premises of the Company was running slow by 48.56%. Pursuant to which a Rojkam was prepared on the spot whereby, according to G.E.B - DGVCL, the authorized officer of the company refused to sign.

3.2 G.E.B – DGVCL, after preparing the aforesaid Rojkam and a report, issued a supplementary bill for the period commencing from January 1993 to June 1994 on 29.09.1994 in tune of Rs.8,37,153.14/- for a recovery of the electricity loss which was not recorded in the electricity meter, due to slowness of meter to the tune of 48.56%.

3.3 The Company having received this supplementary bill filed Special Civil Suit No.195 of 1994 against the G.E.B - DGVCL in the Court of Senior Civil Judge, Bharuch for the relief of permanent injunction restraining the G.E.B - DGVCL from disconnecting the electricity connection. An application for interim injunction was moved whereby the learned Civil Judge, Senior Division directed the Company to deposit 45% amount of supplementary bill and upon fulfilling such condition, restrained the G.E.B - DGVCL from disconnecting the electricity connection. The Company in three installments totallys deposited Rs.3,76,723/-, which was given set off by the G.E.B - DGVCL and thereafter, G.E.B - DGVCL filed Civil Suit No.150 of 1997 for recovery of the remaining amount of Rs.4,60,430.14/- with interest.