2026 Supreme(Guj) 392

IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
Niral R. Mehta, J.
Pandya Naresh Chandra Through Poa Gaurang Bhavsar – Petitioner
Versus
Shalin Infrastructure & Ors. – Respondents
R/Special Civil Application No. 558 of 2026
Decided On : 22-06-2026

Important Points

Rejection of a claim by an arbitral tribunal solely for the failure to produce a document of authority is an erroneous, hyper-technical exercise of power, as such procedural lapses are curable and the tribunal must prioritize the adjudication of disputes on their substantive merits.

Subject

Arbitration Law - Arbitral Procedure

Act Referred

CONSTITUTION OF INDIA : Art.226, Art.227
ARBITRATION AND CONCILIATION ACT : S.25, S.25(a), S.25(b), S.25(c), S.32, S.32(2)(a), S.32(b), S.32(c)
Arbitration Centre Domestic and International High Court of Gujarat Rules : R.48

Headnote

(A) Arbitration and Conciliation Act, 1996 - Sections 25 and 32 - Termination of arbitral proceedings - Rejection of statement of claim solely for non-production of document of authority - Whether curable procedural defect - Statutory mandate under Section 32 allows termination only upon specific contingencies - Non-production of document does not justify summary rejection of claim as it is a procedural lapse susceptible to rectification. (Paras 13, 14, 14.1)

(B) Procedural Law - Document of authority - Nature of defect - Deficiencies in representation or authority are procedural in nature and curable - Tribunals must adopt a pragmatic approach to facilitate adjudication on substantive merits instead of relying on hyper-technical formalisms that defeat justice. (Paras 14.1, 14.2)

Facts of the case:
A claimant, residing abroad, initiated proceedings through an authorized representative. Following a request for the production of the physical document confirming such authority, the claimant failed to produce it within the specified timeframe. Consequently, the tribunal rejected the entire statement of claim and terminated the proceedings.

Findings of Court:
The tribunal exceeded its statutory jurisdiction. The Act provides exhaustive grounds for termination under Sections 25 and 32. The failure to produce a procedural document does not fall within the enumerated grounds for termination, nor does it affect the core jurisdiction to decide the matter. Therefore, the tribunal acted in a manner inconsistent with the legislative intent to provide speedy, fair, and substantive justice.

Issues: Whether the rejection of a claim for the absence of a document of authority constitutes a valid termination of proceedings under the Act and whether such a defect is an incurable jurisdictional deficiency.

Ratio Decidendi: The court held that tribunals must prioritize the adjudication of disputes on their merits over rigid procedural insistence. Since the power to terminate proceedings is limited by the statute, using procedural non-compliance as a ground for summary rejection is legally unsustainable and represents an improperly technical application of the law.

Result: Petition allowed; impugned order set aside; proceedings restored for adjudication.

Advocates Appeared:
For the Petitioner: Mr. A H Mohapatra
For the Respondent: Mr. Yashkumar S Pandya

Table of Content
1. consolidation of facts and procedural history of the case. (Para 1 , 3 , 4 , 5 , 8 , 10)
2. arbitration proceedings prioritising adjudication over hyper-technicality. (Para 9 , 11 , 12 , 15)
3. termination of proceedings confined strictly to statutory grounds. (Para 13 , 14)
4. restoration of proceedings to ensure substantive justice. (Para 16 , 17)

JUDGMENT :

Niral R. Mehta, J.

1. By way of the present petition under Articles 226 and 227 of the Constitution of India, the petitioner–claimant has invoked the extraordinary jurisdiction of this Court challenging the legality and validity of the order dated 08th October, 2025 passed by the learned Arbitral Tribunal in Arbitration Case No.6 of 2025, whereby the statement of claim came to be rejected on the ground that the petitioner had failed to produce the Power of Attorney along with the statement of claim within the time extended by the learned Tribunal.

FACTUAL BACKGROUND:

2.1 The petitioner is a senior citizen aged about 87 years and is presently residing in London. Respondent No.1 is a partnership firm registered under the provisions of the Partnership Act, 1932, and is engaged, inter alia, in the business of real estate development and construction of residential and commercial projects. Respondent Nos.2 and 3 are partners of respondent No.1 and are responsible for managing its day-to-day affairs.

2.2 The respondents executed three separate Agreements to Sell in favour of the petitioner and his wife in respect of three residential flats situated in the project known as Shalin Heights. Pursuant to the said agreements, the petitioner paid an aggregate sum of Rs.61,00,500/- on different dates. The respondents were obliged to execute the sale deeds and hand over possession of the said flats within a period of twelve months. However, despite receipt of the consideration amount, the respondents neither handed over possession of the flats nor refunded the amounts paid by the petitioner.

2.3 Consequently, by notice dated 21st November, 2023, the petitioner invoked the arbitration clause contained in Clause 11 of the Agreements to Sell. Thereafter, the petitioner was constrained to approach this Court by filing Arbitration Petition No.15 of 2024, wherein, by order dated 10th January, 2025, this Court appointed Mr. I.R. Dave (Retd.), District Judge, as the sole Arbitrator to adjudicate the disputes between the parties.

2.4 Pursuant thereto, the Arbitration Centre initiated the arbitral proceedings and directed the petitioner to file the statement of claim on or before 24th February, 2025. The communication in that regard was dispatched to the petitioner’s address in the United Kingdom and came to his knowledge only on 02nd March, 2025. Immediately thereafter, by an e-mail dated 03rd March, 2025, the petitioner’s advocate informed the Arbitration Centre about the delayed receipt of the notice and sought extension of time for filing the statement of claim.

2.5 Owing to his advanced age and inability to travel to India, the petitioner executed a Power of Attorney in favour of Mr.Gaurang Bhavsar to represent him in the arbitral proceedings. The original Power of Attorney was dispatched for filing before the Tribunal. However, the same could not be delivered in time. Meanwhile, by an e-mail dated 08th April, 2025, the Arbitration Centre informed the petitioner’s advocate that if the statement of claim was not filed by 15th April, 2025, the opportunity to do so would stand closed.

2.6 As the original Power of Attorney had not yet been received and the deadline for filing the statement of claim was imminent, the petitioner’s advocate submitted the statement of claim before the Arbitration Centre on 15th April, 2025 without enclosing the Power of Attorney. On the very same day, the learned Tribunal sought clarification regarding the absence of the Power of Attorney.

2.7 By communication dated 16th April, 2025, the learned Tribunal was informed that the original Power of Attorney had not