2026 Supreme(Guj) 487

IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
SUNITA AGARWAL, C.J., D.N. RAY, J.
Chief Engineer (NH) And Additional Secretary & Anr. - Appellants
Versus 
Kunal Structure (India) Pvt. Ltd. – Defendant
R/First Appeal No. 2066 of 2026 [Reasoned Order dated 15/06/2026 in R/FA/2066/2026] With Civil Application (For Stay) No. 1 of 2026 In R/First Appeal No. 2066 of 2026
Decided On : 15-06-2026

Act Referred

ARBITRATION AND CONCILIATION ACT : S.28(3), S.34, S.34(2)(a), S.34(2)(b), S.37
CONTRACT ACT : S.73

Advocates Appeared:
For the Appellants : Mr. Shalin Mehta, Senior Counsel With Arpit R. Singhvi.
For the Defendant : Mr. Saurabh Soparkar, Senior Counsel With Mr. Devang Nanavati, Senior Counsel, Mr. Dhaval Vyas, Senior Counsel, Mr. Vishwas Shah, Mr. Masoom Shah, Ms. Priyanshi Trivedi, Ms. Aashvi P. Shah With Ms Bhavna V. Shah.

JUDGMENT :

SUNITA AGARWAL, C.J.

1. This appeal under Section 37 of the Arbitration and Conciliation Act’ 1996 (for short, “the Act’ 1996”) has been filed challenging the judgment and order dated 30.12.2025 passed by the Judge, Commercial Court, City Civil and Sessions Court, Ahmedabad rejecting the application under Section 34 of the Act’ 1996 seeking for setting aside of the arbitral award dated 26.06.2018 on various grounds qua the claims towards loss of profit and overhead on the ground that the claim awarded by the Arbitral Tribunal was without any legal basis or evidence of proof or demonstrable actual loss.

2. It was the case of the appellant before the Court under Section 34 that the Arbitral Tribunal decided these claims merely on presumptions and assumptions and that in view of the decisions of the Apex Court, noted therein, the loss of profit was required to be proved by tendering cogent evidence.

3. It was urged that the Arbitral Tribunal has committed error in relying upon the Standard Data Book of Ministry of Road, Transport and Highways (MoRTH) and that the standard practice followed by the State PWDs cannot be a legal ground to award the loss of profit and overhead.

4. It was argued before the Court under Section 34 that loss of profit and loss of profitability are quite different and the Arbitral Tribunal has committed a patent illegality in ignoring the same and deciding the question about the loss of profitability in the category of “loss of profit”.

5. There was an another challenge to claim No. ‘3’ about the rental of machinery calculated @ 20% of the final bill amount, which was agitated to have been awarded without any legal basis or supporting evidence. It was urged before the Court under Section 34 that the claimant’s witness had admitted that no payments had been made towards the rent of plants and machinery and, therefore, without the proof of actual damage or actual machinery rental expenses, the said claim has been awarded falsely, that too when the Arbitral Tribunal had ignored that the machineries were owned by the claimant itself.

6. On claim No. ‘4’, i.e. difference in costs for delay, the challenge was on the ground that the difference amount had been awarded without any legal basis or supporting evidence. The contention of the appellant in the proceedings under Section 34 was that there is a fundamental illegality in the award, where the Arbitral Tribunal has ignored that the claimant had already received the amount of Rs.4 crores and odd as per clause ‘47’ and all the conditions of the contract dealing with price adjustment as per the formula had been satisfied. Further claims of additional escalation based on the market price, contract terms, etc. was not entertainable, inasmuch as, it is settled law that the Arbitral Tribunal cannot award anything outside the bounds of the contract.

7. It was urged that when the contract provides certain specific formula to deal with price adjustment, the Arbitral Tribunal cannot award escalation. The submission, thus, is that the award made by the Arbitral Tribunal amounts to rewriting the contract, which is not permissible in view of the law laid down by the Apex Court. Further, when the final bills were fully paid and the liability under the contract was fully discharged, no further claims could be raised by the original claimants / respondent herein.

8. Dealing with the contentions of the learned counsels for the parties on the issues raised therein, as noted herein, the learned Commercial Court in Section 34 proceedings has assigned the following reasonings to uphold the Arbitral award:-

“8. First of all, before entering into the merits and de-merits of the case, it is to be seen for what purpose the A&C Act has been enacted. An aim of A&C Act is to have expeditious and effective resolution of dispute between the parties by their nominated or chosen or appointed arbitrators as judge and by keeping as much as far the intervention of the Courts.

9. Further, as per