2011 Supreme(Gau) 44

IN THE HIGH COURT OF GAUHATI
Biplab Kumar Sharma, J.
Deba Kumar Dutta and Ors. - Appellants
Vs.
State of Assam and Ors. - Respondent
WP (C) Nos. 3773, 4137 of 2010, 1897 and 4790 of 2009
Decided On: 18.01.2011

Advocates Appeared:
For Appellant/Petitioner/Plaintiff: U.K. Nair, B. Sarma, D.K. Das and R.S. Choudhury, Advs.
For Respondents/Defendant: A.K. Bhattacharrya, D.K. Mishra, Sr. Advs., G. Goswami, SC, L.P. Sarma and S. Dutta, Advs.

Headnote:

Constitution of India,1950 - Article 16(4)(A) - Assam Engineering (Flood Control Department) Services Rules 1981 - Assam Scheduled Castes and Scheduled Tribes (Reservation of Vacancies in Services and Posts) Act, 1978 - Assam Scheduled Castes and Scheduled Tribes (Reservation of Vacancies in Services and Posts) Rules, 1983 - Rules for filling up backlog vacancies for Scheduled Castes - Exceed the percentage of reservation - Noticing of carrying - Setting aside and quashing recommendation - Four writ petitions involved in writ petition are aggrieved by recommendation of the selection committee recommending Respondent No. 4 and 5 for promotion to post of Addl. Chief Engineer - Cadre strength of the Addl. Chief Engineer is and promotion to said cadre is governed - Rules called Assam Engineering (Flood Control Department) Services Rules, 1981 - In seniority list of feeder cadre published names of Petitioners appeared at serial and of Respondent Nos. 4 and 5 at serial Nos. 14 and 15 respectively - Assam Scheduled Castes and Scheduled Tribes Act, 1978 – Held, Percentage of reservation as noted is not only applicable for the vacancies to be filled up by direct recruitment Section 4 of Act, 1978 - Percentage of reservation is also applicable for vacancies to be filled up by promotion - Although a separate 20 point roster is given in Schedule to Act to be maintained, but as has been held by Apex Court - When a percentage of reservation is fixed in respect of a particular cadre and the roster indicates reservation points - Posts shown on reserved points are to be filled amongst reserved categories - Operation of roster will have to be in reference to prescribed percentage of reservation - Prescription being operation of roster till the required percentage is achieved, in absence of any quota on the basis of prescribed percentage there is No question of operating roster to achieve impermissible percentage of reservation - Writ petitions being W.P.(C) No. and W.P.(C) No. are allowed by setting aside and quashing recommendation of the selection committee - Writ petitions are answered

ORDER

B.K. Sharma, J.

1. All the writ petitions pertaining to the same issue, i.e. the promotion and seniority in the post of Addl. Chief Engineer in the Water Resources Department, Government of Assam, have been heard together and are being disposed of by this common judgment and order.

2. At the very outset, upon hearing the learned Counsel for the parties, although it was pointed that all the cases are governed by the earlier decisions of this Court reported in 2007 (4) GLT 587: Khaninder Nath Choudhury v. State of Assam and Ors. and 2010 (3) GLT 377: Bhogeswari Saikia v. State of Assam and Ors., it was argued by the contesting counsel that their being distinctive features involved in the writ petitions, it is possible to take a different view of the matter.

3. The brief leading to the filing of the writ petitions are as follows:

W.P.(C) No. 3773/2010

4. The four writ petitions involved in this writ petition are aggrieved by the recommendation of the selection committee dated 20.05.2010 recommending the Respondent No. 4 and 5 for promotion to the post of Addl. Chief Engineer. The cadre strength of the Addl. Chief Engineer is 7(seven) and the promotion to the said cadre is governed by the Rules called the Assam Engineering (Flood Control Department) Services Rules, 1981. In the seniority list of feeder cadre published on 11.03.2010, the names of the Petitioners appeared at serial No. 4, 5, 6, and 7 and that of the Respondent Nos. 4 and 5 at serial Nos. 14 and 15 respectively. As per the provisions of the Assam Scheduled Castes and Scheduled Tribes (Reservation of Vacancies in Services and Posts) Act, 1978 and the Assam Scheduled Castes and Scheduled Tribes (Reservation of Vacancies in Services and Posts) Rules, 1983, there is reservation for reserved category candidates both for direct recruitment and promotion to the extent as follows:

i) Scheduled Castes - 7%

ii) Scheduled Tribes (P) - 10%

iii) Scheduled Tribes (H) - 5%

5. Based on the aforesaid percentage of reservation, the Petitioners have calculated the number of posts that can be reserved for reserved category candidates in the cadre of Addl. Chief Engineer comprising of 7 posts, which are as follows:

i) Scheduled Castes - 7% -0.49

ii) Scheduled Tribes (P)- 10% - 0.7

iii) Scheduled Tribes (H)- 5% - 0.35

6. On the basis of the aforesaid calculations, the Petitioners have contended that there can be No. reservation for any category inasmuch as in case of providing reservation in the cadre of Addl. Chief Engineer comprising of 7 posts, same would exceed the percentage of reservation earmarked in the aforesaid Act and Rules.

7. The Petitioners have also placed reliance on the Annexure-3 office memorandum dated 14.07.2004 on the subject of implementation of the aforesaid Act and the Rules for filling up backlog vacancies for Scheduled Castes and Scheduled Tribes thereof in which the fact of noticing of carrying forward the backlog as well as the current vacancies even to the extent beyond the permissible entitled quota for Scheduled Tribes (P), Scheduled Tribes (H) and Scheduled Castes which have shown exaggerated figures for reserved categories, was conveyed. By the said office memorandum, the appointing authorities were requested to carry out a review for correct assessment of backlog/current vacancies in respect of said reserved category candidates both for direct recruitment and promotion.

8. By Annexure-4 representation dated 26.05.2010 made by the Assam Engineering Services Association to the Chief Secretary of the State bringing on records the aforesaid facts, it was contended that No. candidates belonging to reserved categories is entitled to be considered for promotion on the basis of the reservation as the percentage of reservation did not permit them to be so considered.

W.P.(C) No. 4137/2010

9. This writ petition has also been filed by the four writ Petitioners involved in the first writ petition. In this writ petition, they have challenged the Annexure-4 select list dated 12.07


















































Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top