2007 Supreme(Gau) 765

IN THE HIGH COURT OF GAUHATI
Jasti Chelameswar and Ashok Potsangbam, JJ.
Kula Prasad Gogoi
Vs.
State of Assam and Ors.
Decided On : 23.11.2007

The main legal point established in the judgment is that unauthorized construction, in deviation of prescribed norms and provisions, is liable for demolition.

Headnote:

Unauthorized Construction - Guwahati Municipal Corporation - GMC Act, 1971, Section 328; Building Byelaws - The court discussed the provisions of the GMC Act, 1971, Section 328, and the Building Byelaws in relation to unauthorized construction and deemed permissions. The court emphasized the necessity of adhering to the prescribed norms and provisions and highlighted the extent of deviation and violation of the building byelaws in reaching its decision.

Fact of the Case:

The petitioner sought to quash an order passed by the Commissioner, Guwahati Municipal Corporation, regarding unauthorized construction of a residential building. The petitioner claimed to have applied for permission for construction and alleged that the building was in conformity with the Building Byelaws, Master Plan, and Zoning Regulations.

Finding of the Court:

The court found that the petitioner's building was unauthorized and in deviation of the prescribed norms and provisions, as evidenced by a report prepared by the Corporation's engineers. The court ordered the demolition of the deviated part/portion of the building.

Issues: The issues before the court included whether the entire building should be considered illegal due to lack of necessary approval, and whether only the deviated part/portion should be demolished.

Ratio Decidendi: The court held that the construction of the petitioner's building, without necessary approval and in deviation of the prescribed norms, constituted unauthorized construction and was liable for demolition.

Final Decision: The court disposed of the writ petition, upholding the impugned order and directing the demolition of the deviated part/portion of the petitioner's building.

JUDGMENT

Asok Potsangbam, J.

1. Heard Mr. A. Sarma, learned Counsel appearing for the petitioner. Also heard Mr. U.C. Nath, learned Counsel, Mr. S. Chamaria, Standing Counsel, GMC and Mr. G.N. Sahewalla, learned senior Counsel for the G.M.C.

2. This is the second round of litigation. By the instant writ petition, the petitioner is seeking to quash the order dated 22.6.2007 passed by the Commissioner, Guwahati Municipal Corporation, disposing of the representation dated 10.4.2007, which was filed by the petitioner pursuant to judgment and order dated 26.3.2007 passed by this Court in the first round of litigation i.e. W.P. (C) No. 1340/2007. The Commissioner, Guwahati Municipal Corporation, disposed of the aforesaid representation by holding that the building constructed by the petitioner was unauthorized and without necessary approval of the authority and, consequently, GMC was directed to take necessary action against the unauthorized construction of the petitioner as per GMC Act and Building Byelaws framed thereunder.

3. The case of the petitioner is that on 11.3.1998, he applied for permission, as required under Section 328 of the GMC Act, for construction of his residential building over a plot of land at Uzanbazar, Guwahati and as the permission was not forthcoming even after waiting for 60 days, he went on with the construction of his residential building. The further case of the petitioner is that after completion of first floor, he applied for assessment of his residential building and GMC, after due assessment, allotted Holding No. 95 to the writ petitioner. The petitioner also annexed few receipts showing payment of, Municipal Taxes, Urban Taxes etc. in respect of Holding No. 95 i.e. residential building of the petitioner.

4. The case of Respondents No. 2 and 3 i.e. Guwahati Municipal Corporation, is that a complaint dated 6.2.2006 was received by the office of the GMC from the proforma Respondents No. 7 and 8 who claim to be the persons residing on the western side of the petitioner's building, alleging therein that the construction of the petitioner's residential building is without necessary permission from the GMC and without approval of any building plan etc. and that the aerial projection of the building of the petitioner had encroached upon the land of the Respondents No. 7 and 8 etc.

5. In order to ascertain the allegations made in the aforesaid complaint, GMC caused a site inspection by its engineers to enquire into the allegations and in that, it was found that the consumption in question did not maintain setbacks and other norms prescribed by the GMC Act and Building Byelaws and this led the GMC to issue a notice dated 2.3.2006 asking the petitioner to stop further construction and to produce the approved plan and NOC issued to him in connection with the construction of his building. A photocopy of the NOC dated 12.10.2004 was submitted by the petitioner and on verification from records, GMC found the aforesaid NOC a forged one and, as a consequence thereof, an FIR was lodged and Latasil Police Station Case No. 3232 of 2007 under r Sections 420/468/471 I.P.C. was registered.

6. On 15.3.2007, GMC issued another notice under Section 337 of the GMC Act, 1971, directing the petitioner to discontinue with further construction of his building and submit a show cause reply within seven days as to why the unauthorized construction/deviation should not be demolished. The petitioner, instead of replying to the notice mentioned above, chose to challenge the notice dated 15.3.2007 before this Court by filing a writ petition being W.P. (C) No. 1340 of 2007 and this Court was pleased to dispose of the said writ petition by an order dated 26.3.2007 directing the petitioner to file a detailed representation to the Corporation by highlighting all his grievances within 15 days and the Corporation was also directed to dispose of the representation by passing a speaking order within a period of one month. The representation so submi













































































Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top