GAUHATI HIGH COURT
A.K.Goel,Amitava Roy, JJ.
Subodh Chintey -Appellant
Versus
State of Assam & Ors. -Resopndent
Writ Appeal No. 127 of 2009
Decided On : 23-09-2011
Constitution of India – 1950 - Employment - Jurisdiction - Executive Engineer North Water Resource Division North as Member Secretary of Selection Committee requested District Employment Officer to send names and particulars of candidates for post - Receipt of list of such candidates as requested call letters were issued to them including parties in fray fixing written test - Call letter inter alia mentioned that written test would comprise of General English General Knowledge and Mathematics for marks with duration of hours - Written test was to be followed by interview and typewriting test – Held, Unlikely that writ petitioner respondent was aware letter of departmental Minister at all relevant times and particularly at time of institution of writ petition - His omission to mention about same in his pleadings that point of time thus cannot non-suit him on this ground - Decision of this Court in Das supra is also of no avail appellant - It is no longer res that candidate participating selection process is not debarred thereafter to question validity thereof if same suffers from apparent illegalities rendering it non - Plea against writ petitioner respondent does not appeal - Appeal dismissed
The appellant is aggrieved by the judgment and order dated 08.04.2009 rendered in WP (C) No. 2906/2008 setting aside his appointment to the post of Lower Division Assistant (for short, hereinafter referred to as 'LDA') in the office of the Executive Engineer, Water Resource Department, North Lakhimpur. The annulment was as a consequence of a challenge to the selection process by the respondent No. 7 herein. The appellant was arrayed as respondent No. 7 in the writ proceeding.
2. We have heard Mr. R.C. Saikia, learned counsel for the appellant; Mr. B. Goswami, learned Standing Counsel, Water Resource Department, Govt. of Assam; Mr. P.S. Deka, learned State counsel and Mr. M. Bhuyan, learned counsel for the respondent No.7.
3. The process of filling up the aforementioned post was initiated pursuant to the Office Order bearing Memo No. A/10(C)/05-06/621-26 dated 27.2.2008 of the Executive Engineer, North Lakhimpur Water Resource Division, North Lakhimpur. A four member Selection Committee was also constituted thereby to administer the selection which was to be on the basis of a written test, viva-voce and typewriting test. The post was reserved for the Scheduled Tribe (P) candidates only. In this connection, the Executive Engineer, North Lkhirnrnr Water Resource Division, North Lakhimpur as the Member Secretary of the Selection Committee requested the District Employment Officer, Lakhimpur to send the names and particulars of 20 candidates for the post. On receipt of the list of such candidates as requested, call letters were issued to them including the parties in the fray fixing 18.5.2008 for written test etc. The call letter inter alia mentioned that the written test would comprise of General English, General Knowledge and Mathematics for 50 marks with the duration of 1½ hours. The written test was to be followed by interview and typewriting test.
4. In course of the written test it transpired that the same was for 100 marks instead of 50 marks as indicated in the call letter. However, on the completion of the written test, on the very same day, viva-voce as well as typewriting test was held. The results of the selection were also announced on the same day and the appellant was shown to have been selected for appointment.
5. Situated thus, the respondent No.7 in the above factual backdrop initiated the writ proceeding assailing the selection process and the resultant appointment of the appellant inter alia on the ground that the same had been conducted in violation of the prescribed guidelines and was in reality a sham exercise in order to favour the appellant on extraneous considerations. That the written test was held for 100 marks instead of 50 marks and that the model of the question paper demonstrated total non-application of mind for securing the appointment of the appellant herein was also underlined.
6. This Court while issuing notice by the order dated 28.5.2008, in the interim, observed that any appointment on the basis of the impugned selection would be subject to further orders. Contending that in view of the above observation, he though appointed meanwhile tentatively, the same had not been regularized, the appellant filed an application seeking modification and/or vacation of the order dated 28.5.2008. In the said interim application registered as M.C. No. 34937 2008, the appellant pleaded the validity of the selection process and urged that as on a comparative assessment of the performance of the participating candidates he had been appointed having been adjudged to be the best, no interference as sought for therewith was warranted.
7. The respondent No.5 in the writ proceeding i.e. the Executive Engineer, North Lakhimpur Water Resource Division, North Lakhimpur in his counter did not dispute that in terms of the decision taken by the Selection Committee the written test was to be held for 50 marks with a duration of 1½ hours. The answering respondent stated that as per the decisi
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.