SupremeToday Landscape Ad
Back
Next
Headnote Court Copy Facts Arguments Court observation Judicial Analysis Case Map Category Hierarchy Table of Content
Listen Article Pause Article
judgment-img

2014 Supreme(Gau) 429

IN THE GAUHATI HIGH COURT (The High Court of Assam, Nagaland, Mizoram and Arunachal Pradesh)
N. CHAUDHURY, J.
ASSAM AGRICULTURAL UNIVERSITY AND ORS
VS
MANJIT KUMAR BHATTACHARYA
RFA 35 of 2004
Decided on: 13.6.2014

Subject

Contract Law - FORMATION OF CONTRACT

Act Referred

CIVIL PROCEDURE CODE : S.80
CONTRACT ACT : S.4, S.2(b), S.3, S.2, S.7(1)

Headnote

Evidence Act – Section 60 – D.A.F.P. Rules, 1988 – Rule 13 – Indian Limitation Act, 1963 – Section 3 – Payment of earnest money – Whether communication of acceptance containing counter offer without there being a formal contract preceded by payment of earnest money constitutes a concluded contract, is the central question in the present first appeal – By challenging the judgment and decree passed by the learned Civil Judge (Senior Division), Jorhat in Money Suit, the appellant has raised this question. – According to the appellant, there was no concluded contract with the respondent/plaintiff and in that view of the matter the impugned judgment and decree for realization of Rs. 9,49,526/- (Rupees nine lakh forty nine thousand five hundred and twenty six), being compensationed, is untenable and is liable to be set aside in cost. – Held, Under Section 3 of the Indian Limitation Act, 1963, it becomes a duty on the court to see as to whether a particular claim is time barred or not irrespective of whether an objection of limitation is taken by the defendants in the written statement. – Be that as it may, even without the bar of limitation, the plaintiff has miserably failed to show that he is entitled to any compensation not to speak of the amount decreed by the learned trial court. – To prove the liability of the defendants to pay compensation, concluded contract between the parties is a must as otherwise it cannot be said that the defendants were bound to indemnify the plaintiff for their failure to proceed with the contract work. – First point for determination assumes importance for this reason only as legally there was no binding contract between the parties. – Issuance of Ext. 11 asking the plaintiff to proceed with the work was nothing but a measure to ensure that it can be completed within 12 (twelve) months. – Plaintiff was not under any obligation to place orders with the suppliers before a formal contract was executed between the parties. – Claim of the plaintiff that he had demolished previous structures, that he made labour shed and that there were building materials at site could not be proved by cogent and credible oral evidence as required under Section 60 of the Evidence Act. – On consideration of totality of these circumstances, the defendants/appellants cannot be held to be liable to compensate the plaintiff for the claims made by him. –Appeal Allowed

Advocates Appeared:
For the Appellants :Mr. P Kataki Advocate
For the Respondent:Mr. BD Goswami Advocate

JUDGMENT AND ORDER (CAV)

Whether communication of acceptance containing counter offer without there being a formal contract preceded by payment of earnest money constitutes a concluded contract, is the central question in the present first appeal. By challenging the judgment and decree dated 07.07.2003 passed by the learned Civil Judge (Senior Division), Jorhat in Money Suit No. 34/1998, the appellant has raised this question. According to the appellant, there was no concluded contract with the respondent/plaintiff and in that view of the matter the impugned judgment and decree for realization of Rs. 9,49,526/- (Rupees nine lakh forty nine thousand five hundred and twenty six), being compensationed, is untenable and is liable to be set aside in cost.

2. The respondent, as plaintiff, instituted Money Suit No. 34/1998 in the Court of learned Civil Judge (Sr. Divn.), Jorhat stating that pursuant to Notice Inviting Tender (hereinafter referred to as ‘the NIT’) dated 25.02.1992 for construction of first floor of vertical extension of the laboratory building at Regional Research Station, Diphu, the plaintiff submitted tender along with 8 (eight) others quoting Rs. 24,52,060/- (Rupees twenty four lakh fifty two thousand and sixty) under Rule 13 Schedule III of the D.A.F.P. Rules, 1988 of the Assam Agricultural University Act. The Director, Physical plant of the appellant university informed the respondent on 07.08.1992 that works had been allotted to the plaintiff at the quoted rate of 20% above the A.P.W.D. Schedule of rates (building) for 1990-91 and 89% above the APWD Schedule of rates (Sanitary & Water Supply) for 1981-82 at the total tender value of Rs. 24,52,060/- (Rupees twenty four lakh fifty two thousand and sixty) and thereby directed the plaintiff to deposit an earnest money of Rs. 49,050/- (Rupees forty nine thousand and fifty) within 15 days for signing the formal tender agreement of work. Plaintiff claimed to have deposited a Bank Guarantee of the aforesaid amount and thereupon an agreement was signed on 18.08.1992. According to the plaintiff, even prior to signing of the agreement dated 18.08.1992, the defendant No. 3 issued final Work Order to him asking him to start the work in consultation with Executive Engineer-II, Director Physical Plant (DPP), Assam Agricultural University (AAU), Jorhat, within 15 days and to complete the work within 12 (twelve) months from the date of issue of the order. The plaintiff, accordingly, started work as per approved drawing and placed order for steel windows with ventilator of size 94.86 Sq.mtrs, Tubular truss of 988 Sq. mtrs, steel rod of 6, 8, 16 and 20 mm weighing 4000 Kgs. and also for construction of labour shed/Brick of 4 (four) trucks, Sand 3 (three) trucks, Chips ¾” 5 (five) trucks and also performed other miscellaneous works like dismantling of existing house. The plaintiff claimed to have made advance payment to mason, carpenter and others amounting to Rs. 7,00,000/- (Rupees seven lakh). In the mean time on 19.11.1992 the defendant No. 3 issued a letter informing the petitioner that the bank guarantee submitted by the petitioner could not be accepted and thereupon the plaintiff was asked to deposit Rs. 49,050/- in the shape of Deposit at Call. By letter dated 12.12.1992, the plaintiff expressed his inability to do so and renewed his prayer for acceptance of the Bank Guarantee which was turned down by the University on 18.02.1993. However, on 20.03.1993 defendant No. 3 purporting to represent the university, asked the plaintiff to sign an addendum containing recital to the effect that the plaintiff could not deposit 2% earnest money in cash due to non-receipt of huge amount due to him from the University against works already done by him and so as per letter dated 31.10.1992, issued by the Legal Advisor, the Bank Guarantee in lieu of bank draft be accepted for accepting the agreement subject to the condition that amount covered by the bank guarantee would be recovered from th









































1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
whatsapp-icon Back to top