SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2017 Supreme(Gau) 1174

IN THE HIGH COURT OF GAUHATI, KOHIMA BENCH
SONGKHUPCHUNG SERTO, J.
General Manager, North East Frontier Railway and Ors. - Appellants
Versus
J.A. Brothers - Respondent
First A. No. 3(K) of 2015
Decided On : 31-03-2017

Advocates Appeared:
For the Appellants :Nuksungtila, Advocate
For the Respondent:C.T Jamir, Sr. Advocate, Wati Jamir, N. Longkumer, Imkong Jamir, Chubatola and Nukshinaro Pongen, Advocates

Headnote:

Civil Procedure Code, 1908 – Section 96 – Arbitration and Conciliation Act, 1996 – Section 8 – Obstructing and Delaying – Illegal Gratification – Advocate to General Manager, N.F. Railway Lumding – Only thereafter appellants/defendants responded and fixed for doing same but no one from appellants/defendants side came forward for measurement of work done wrote a letter on same day to appellants/defendants requesting for same another was again fixed for joint measurement but on that day also same could not be carried out as appellant/defendant assaulted and criminally intimidated people who were at work site on behalf of respondent for purpose – Complaint regarding incident was submitted to Railway authorities but no action was taken petitioner did not get positive response from appellants he filed a suit before Dimapur praying – Held, Power of Attorney by proprietor of firm to execute contract work and also to represent plaintiff firm in any suit which may arise in connection or relation to work – He exhibited power of Attorney bearing registration executed by Sri. James as exhibit power of Attorney at Prasad to represent firm in any suit in connection with contract work cross-examination, nothing was asked by appellants/defendants counsel to discredit his claim evidence given by D Ws there is nothing which prove otherwise one can only conclude that was duly authorised agent/power of Attorney Holder of plaintiff firm M/s. J.A. Brothers in connection with contract work and suit and he is legally competent to represent firm in this case – Appeal Dismissed.

JUDGMENT :

Songkhupchung Serto, J.

1. Heard Ms. Nuksungtila, learned counsel who appeared on behalf of the appellants and also heard Mr. C.T. Jamir, learned Sr. Advocate who appeared on behalf of the respondent. This is an appeal under section 96 of the Code of Civil Procedure, 1908 r/w Rule 29 of the Rules for the Administration of Justice and Police in Nagaland, 1937 directed against the judgment and order dated 30.5.2014, passed by the learned District & Sessions Judge, Dimapur in Civil Suit No. 15/2007.

2. The brief facts of the case leading to this appeal are as follows:

The appellants/defendants floated a Tender Notice No. 105/2003 (IT-3) on 2003, for Execution of the work, "At LMG-Repairs to main road from 1st BN RPSF/LMG Complex to Recreation Club with Colony road at Loco Colony; BF Colony; S.H. Colony et. Under SSE (W)/S/LMG" for an amount of Rs. 38,18,035/-. In response, the respondent/plaintiff submitted his tender vide his letter dated 17.02.2005 and he was selected for the work. Accordingly, on 24.02.2005, an agreement was signed and according to the same the petitioner was to finish the work on or before 16.08.2005. Thereafter, a subsidiary contract agreement was signed by the parties on 12.06.2006, by which the respondent/plaintiff was given additional work and the value of the contract was enhanced to Rs. 44,45,096/- and time limit for completion of the work was also extended till 30.05.2006. The contract agreement was signed by Sri. James Akham on behalf of the respondent firm M/s. J.A. Brothers and on behalf of the President of India by Divisional Engineer, N.E.F. Railway, Lumding. The respondent/plaintiff claimed that as per the contract agreement he had completed execution of the work on 21.07.2006. So, he informed the appellants/defendants and requested for final measurement and payment of the bill through a letter dated 22.07.2006, but due to non-payment of illegal gratification demanded by the appellants/defendants No. 5, final measurement could not take place even after 2(two) months from the date of his report. Having no choice the plaintiff with his authorised Engineer and staffs took final measurement of the work done and the result of the same tallied with the records of the quantities of the materials used and volume of the work done and signed by both the parties in the register maintained by defendant No. 5. Thereafter, he submitted the same to the Divisional Railway Manager, N.F. Railway at Lumding vide his letter No. Final Bill/NFR/LMG/06-07 dated 4.10.2006 for payment of the outstanding bill amounting to Rs. 19,52,012/-. However, he did not get any response for payment of the bill. Therefore, he was compelled to issue a legal notice through his Advocate to the General Manager, N.F. Railway, Lumding. Only thereafter, the appellants/defendants responded and fixed 23.12.2006 for doing the same but no one from the appellants/defendants side came forward for measurement of the work done. As such, he wrote a letter on the same day to the appellants/defendants requesting for the same. Thereafter, another date i.e. 12.2.2007 was again fixed for the joint measurement but on that day also the same could not be carried out as the appellant/defendant No. 5, assaulted and criminally intimidated the people who were at work site on behalf of the respondent for the purpose. A complaint regarding the incident was submitted to the Railway authorities but no action was taken. Since the petitioner did not get positive response from the appellants, he filed a suit before the Addl. District Judge, Dimapur praying for a decree for the sum of Rs. 19,52,012/- and for a decree of Rs. 20,00,000/- as cost for the delay along with interest @ 18% p.a. on the decreetal amount with pendente lite and future interest till the amount is paid in full.

The learned Addl. District Judge, Dimapur by an ex-parte judgment and order passed on 20.06.2008, disposed the suit and directed the appellants/defendants to pay the sum of Rs. 19,52,01





































































































Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top