SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2021 Supreme(Gau) 22

IN THE GAUHATI HIGH COURT (HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) KOHIMA BENCH
S. HUKATO SWU, J.
Toshi Longkumer Proprietor Of M/s T.L Constructions - Appellant
Versus
The Union Of India And Ors - Respondents
WP(C) 263 of 2018
Decided on : 09-04-2021

Advocates:
Advocate Appeared:
For the Appellant : IMTI LONGJEM
For the Respondent: YANGER WATI, Adv.

Point of Law: Contractual agreement - Whether existence of arbitral agreement between parties that High Court of Delhi alone will have jurisdiction to try dispute arising out of contract is enforceable in law - Unconscionable contractual agreement - Enforceability of - When arbitration is complete and parties are aggrieved, jurisdiction of Court begins. In our case, arbitration has neither started nor concluded - If two arguments of petitioner should survive that matter can be brought before a writ Court, and also, that there is an unconscionable agreement, nature of the issues involved requires leading of evidence, which explains hesitancy of this Court's indulgence in matter.

Headnote:

Constitution of India, 1950 - Payment of Contractual Amount - Issuance of writ of mandamus - Petitioner came into contractual agreement with respondents for construction works - Respondent No.3 acting as construction agency for and on behalf of respondent No.2 floated Tender Notice for construction - Petitioner participated in tender bid - Petitioner was successful in tender bid for construction of school building, kitchen and dining external development work, construction of UG tank, tube well, drainage system, water supply system, road work open surface drains, internal and external electrical works. - Scope of work of contract is mentioned in Price Bid Document (Volume-II) of tender document of contract - Contract work was for a total price- Agreement was executed between respondent No.3 and the petitioner's firm M/s T.L. Constructions - However, when petitioner's firm started work as per agreement, there was delay in completion of work due to several attending factors beyond control of petitioner. - Seeks direction of like nature for enforcement of the rights of the petitioner guaranteed under the Constitution of India and the laws framed thereunder.

Finding of the court: When arbitral agreement is in existence between parties, Court normally do not intervene unless there are exceptional prevailing circumstances. - Plea of petitioner is that an arbitral agreement between parties cannot oust jurisdiction of writ Court. - It may be applicable in other cases. - In arbitration cases Courts must always allow process of arbitration to complete. - Only when arbitration is complete and parties are aggrieved, jurisdiction of Court begins. - Arbitration has neither started nor concluded. - Only fact that is brought before this Court is that, first work was left incomplete as admitted by petitioner in bar. - An inventory was prepared, wherein respondents were directed to pay a sum of Rs. 23,78,174/- whereupon, respondents, after deduction had paid a sum of Rs. 9,38,000/-. - Thereafter, petitioner issued 'No Due Certificate'. - Contract was terminated. - Again contractual agreement was revived and three new additional works were granted. - Petitioner claims that works were completed and he was only paid a sum of Rs. 21,59,322/- out of total contractual amount of Rs. 1.74 lakhs in the old rate. - This he claims to be an unconscionable agreement. - There is total denial of fact by respondent who has submitted that the additional works were not completed. - There is dispute with facts and figures. - There is claim and counter claim. - This cannot be adjudicated by a writ Court. - Court is of view that writ Court cannot adjudicate into matter. -Court deems it proper that a direction may be given that matter may be placed before appropriate forum.

Result: Petition Disposed of

JUDGMENT :

This is an application under Article 226 of the Constitution for issuance of writ of mandamus or any other appropriate writ or direction of the like nature for enforcement of the rights of the petitioner guaranteed under the Constitution of India and the laws framed thereunder.

2. The petitioner herein functions in the name and style of M/s T.L. Constructions came into contractual agreement with the respondents for construction works at the Jawahar Navodaya Vidyalaya at Chare, District-Tuensang, Nagaland. The respondent No.3 acting as construction agency for and on behalf of respondent No.2 floated Tender Notice bearing NO.RITES/CP/TC/NVS/TUENSANG/PH-A/Pkg-II/2005/2R on 17-02-2005 for construction of Phase-(Pkg-II) Buildings for Jawahar Navodaya Vidyalaya at Chare, District-Tuensang, Nagaland. The petitioner participated in the tender bid.

3. The petitioner was successful in the tender bid for construction of school building, kitchen and dining external development work, construction of UG tank, tube well, drainage system, water supply system, road work open surface drains, internal and external electrical works. The scope of work of the contract is mentioned in the Price Bid Document (Volume-II) of the tender document of the contract. The contract work was for a total price of Rs.4,36,01,897.26/-. Agreement was executed between respondent No.3 and the petitioner’s firm M/s T.L. Constructions on 22-08-2005. However, when the petitioner’s firm started the work as per the agreement, there was delay in the completion of the work due to several attending factors beyond the control of the petitioner. The petitioner’s firm was granted extension of time on several occasions. The factors mainly hampering the progress of the work was cited as increased insurgency activities in Tuensang District. In the year 2006, one staff of RITES Ltd was kidnapped from the project site. At another point of time, an insurgent group camped at the construction site forcing the workers to desert the site resulting in dislocation of the project. There were multiple demands of extortion which also interrupted the work. Added to this problems, were the road conditions which was not favourable for smooth transportation of materials resulting in the delay of the work. The respondent No.3 granted time to the petitioner’s firm for completion of work as many as eight times. Despite all these, the works could not be completed.

4. Besides the work of the petitioner, construction of Phase-A buildings for JNV at Tuensang District, apart from the works awarded to the petitioner’s firm, which included boys and girls hostels, residential quarters, etc. were awarded to other contractors and it is learnt that the construction of these buildings and quarters have also stopped by the contractors due to unworkable rates.

5. Respondent No.4 vide letter No.RITES/CO/CP/NVS-Tuensang Ph A/3592/Folder/09 dated 25-11-2010 forwarded the re-revised Preliminary Estimate to the respondent No.2 incorporating the cost/details required for completion of the construction of Phase-A works at JNV, Tuensang including that of additional works desired by the Principal, JNV-Tuensnag. Consequently, the respondent No.2 by letter No.F.2-55(135)2001-NVS (W)/243 dated 29-09-2011 approved the revised estimates. This approval also included the additional works which were required as per the site at the work/project awarded to the petitioner. The three additional works were awarded to the petitioner which included playfield, boundary wall fencing and retaining wall. These additional works were sanctioned vide letter dated 29-09-2011 at the cost of Rs. 36.02 lakhs, Rs. 42.46 lakhs and Rs. 96.22 lakhs, respectively. Copies of the letter dated 25-11.2010 and 29-09-2011 are reproduced herein below:-

 

              Click Here to Read the rest of this document
              1
              2
              3
              4
              5
              6
              7
              8
              9
              10
              11
              SupremeToday Portrait Ad
              supreme today icon
              logo-black

              An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

              Please visit our Training & Support
              Center or Contact Us for assistance

              qr

              Scan Me!

              India’s Legal research and Law Firm App, Download now!

              For Daily Legal Updates, Join us on :

              whatsapp-icon Back to top