2022 Supreme(Gau) 560
IN THE HIGH COURT OF GAUHATI, NAGALAND, MIZORAM AND ARUNACHAL PRADESH
Devashis Baruah, J.
M/s S.R. Engineering Construction Through Ghanshyam Das Dhiman – Petitioner
Versus
The Commander Works Engineer – Respondent
Arb.A./7 of 2018
Decided On : 11-08-2022
Important Points
Subject
Arbitration Law - Setting Aside of Arbitral Award
Act Referred
Headnote
Arbitration and Conciliation Act, 1996 – Section 37, 34, 18 – Appeal - Arbitrator – Appointment of Arbitration - Case are that certain disputes and differences arose between parties in respect to a contract agreement which was in relation to construction of Pump House with allied services in remote area of Arunachal Pradesh Initially, one SE was appointed as Sole Arbitrator who resigned - Thereupon, one, SE was appointed as Sole Arbitrator - Section 18 of Act of 1996 mandates that both parties shall be treated with equality and each party shall be given full opportunity to present his case (Para 10).
Findings of Court :
If this Court looks into materials on record, it would be seen that Arbitrator did not decide claims on merit. Arbitrator decided entire claim proceedings on question of locus-standi, petitioner-in-person to represent M/s S. R. Engineering, appellant although both Power of Attorneys in question were on record - If it was only question of locus-standi, Arbitrator ought to have permitted claimant to produce necessary documents in support thereof and said opportunity was being sought for by claimant before Arbitrator but it is seen that Arbitrator was more in a hurry to dispose of Arbitration proceedings in view of direction passed by this Court to dispose of arbitration proceedings - It is, however, relevant to take note of that a party not been able to prove his case on basis of producing documents to substantiate a claim is different from a party being non-suited on ground of locus-standi and this very aspect of matter touches on Section 18 of Act of 1996. It, however, appears that Court of District Judge, did not take into consideration said aspect of matter, and consequently, dismissed said application.
Result : Appeal disposed of.
Advocate Appeared:
For the Petitioner: Mr. G. D. Dhiman
For the Respondent:Ms. M. Bhattacharjee, Advocate.
JUDGMENT :
Heard Mr. Ghanshyam Das Dhiman, the petitioner-in-person and Ms. M. Bhattacharjee, the learned counsel appearing on behalf of the respondent.
2. This is an appeal under Section 37 of the Arbitration and Conciliation Act, 1996 (for short, the Act of 1996) challenging the order dated 20.05.2016 passed in Misc. Arbitration Case No.44/2013 whereby the application under Section 34 of the Act of 1996 was dismissed.
3. The brief facts of the instant case are that certain disputes and differences arose between the parties in respect to a contract agreement No.CWE/TEZ/39 of 1989-90 which was in relation to construction of Pump House with allied services in remote area of Arunachal Pradesh under GE 859 EWS. Initially, one Shri Praveen Kumar, SE was appointed as Sole Arbitrator who resigned on 25.08.2010. Thereupon, one Sant Ram, SE was appointed as the Sole Arbitrator.
4. The appellant herein submitted the statement of claim on 14.04.2011. The respondent filed its statement of defence on 21.04.2011. Thereupon, the arbitration proceedings commenced. The respondent herein before the Arbitrator raised locus-standi of the appellant stating inter-alia that Mr. G. D. Dhiman was authorized to file the claim proceedings on behalf of the appellant. It is relevant, however, to take note of that the petitioner-in-person Mr. Ghanshyam Das Dhiman had submitted two Power of Attorneys, one dated 15.09.2011 and the other dated 9.08.2011. Thereupon, it appears from the perusal of the arbitration award that there was a proceeding initiated before this Court on the ground that there was a delay in disposal of the arbitration proceedings and this Court had directed the Arbitrator to complete the arbitration proceedings by 31st of January, 2013 subject to the appellant furnishing the required documents by 31st of July, 2012. It further appears from the arbitration award that the issue as regard the locus-standi of the appellant continued to be pivotal on the ground that there was no document produced that the person(s) authorizing Mr. Ghanshyam Das Dhiman to file arbitration proceedings vide the two Power of Attorneys had the power on behalf of the appellant in question. It further appears that the appellant herein had on various occasions requested the Arbitrator to grant opportunity. From the arbitral award it though appears some opportunities were being granted but it is the case of the appellant herein that the said opportunities were nothing but an eye wash in as much as the opportunity so granted was inadequate. It further appears that the arbitration proceedings were decided only by hearing the respondent in the said arbitration proceedings and the claimant, i.e., the appellant herein were not heard. It further appears on record from the arbitration award that the Arbitrator did not take into consideration the claims so raised in the claim proceedings but rather accepted the stand of the respondent therein that the claimant had no locus-standi for filing and getting any claim on behalf of M/s S. R. Engineering Construction. It is on the basis thereof, the Arbitrator passed a NIL award. It is also pertinent herein to mention that though the respondent herein sought for imposition of cost of Rs.40,000/-being the cost involved in the arbitration proceedings, but the Arbitrator in the facts of the case directed both the parties to bear their own costs. The said award was published on 15.01.2013.
5. Being aggrieved and dissatisfied, the appellant herein preferred a proceeding under Section 34 of the Act of 1996 before the Court of District Judge, Sonitpur at Tezpur for setting aside the said award dated 15.01.2013. The said case was registered and numbered as Misc. Arbitration Case No.44/2013.
6. The Court of the District Judge, Sonitpur at Tezpur vide the order dated 20.05.2016 dismissed the said application on the ground that the objections so raised to the award in question do not come within the ambit of Section 34 of the Act of 1996.
7. Feeling